Being the Bearer of Bad News (Sounding the Alarm on Construction Issues Early and Often) (Law Note)
October 02, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaOur recent look into termination brings up another issue important to architects and engineers– how to sound the alarm about construction or building code violations. Sometimes, a project owner may be so focused on project completion that they want to overlook the sub-par work that may be occurring in an effort to get project open “on time.” In such cases, only if a life safety violation is reported to the authority having jurisdiction will the owner finally terminate a faulty contractor from a construction project.
Even if the work is not a life/safety issue, it is important that when delivering bad news about the quality of work that your notice be early, loud, and frequent. Basically, everyone involved should be aware, through written communications, that there is an issue that needs to be addressed on site, the contractor is messing up the construction, and what needs to be done to fix the issue(s). If the owner is willing to live with the faulty work (and it is not a life/safety matter), then at least you’ve provided notice and warned them of the issue.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
“Bee” Careful: Unique Considerations When Negotiating a Bee Storage Lease Agreement
March 27, 2019 —
Colton Addy - Snell & Wilmer Real Estate Litigation BlogAs demand for commercial bees used to pollinate crops (such as almond trees) has grown, so has the demand for facilities to store bees. Entering a lease agreement for the storage of live bees presents some unique issues the parties need to consider when negotiating the lease agreement.
Don’t Bee Short-Sighted: Bees are often transported to different areas depending on the time of year, which means bees are not stored in the same facility all year. The lease agreement will often only provide for the storage of bees during the season when the bees are used for pollination in that particular area, but that does not mean the parties must limit the term of the lease agreement to a single season. The parties may consider entering into a lease agreement for multiple years that only applies during the pollination season each year.
Bee Mindful of the Rent: Whereas the parties usually base rent in a typical commercial lease agreement off of the square footage of space the tenant uses in the premises, it often makes more sense for both parties negotiating a lease for the storage of bees to base the rent on the number of beehives or bee colony boxes stored at the facility. Basing the rent on the number of beehives or bee colony boxes provides the landlord with flexibility in storing the bees of multiple tenants in the same facility, and it can give the tenant flexibility with the number of bees it may need stored at the facility in any given season. With such a rental arrangement, a landlord should consider asking for a commitment from the tenant to deliver at least a certain number of beehives or colonies for storage, and the tenant should consider asking for a commitment from the landlord to reserve space in the facility for at least that same number of beehives or colonies as the tenant is giving a commitment for. Additionally, the parties will need to determine when rent will be paid. In a general commercial lease agreement, rent is usually paid monthly. With a bee storage lease agreement, however, a landlord may want to require the tenant to pay all of the rent for the season upon delivery of the bees, and the landlord may also want the tenant to pay a percentage of the rent to reserve space in the facility prior to delivery of the bees. This allows the landlord to get an early indication of what space in the facility it will have available in the facility for other tenants given the somewhat flexible rental arrangement of the parties.
Read the court decisionRead the full story...Reprinted courtesy of
Colton Addy, Snell & WilmerMr. Addy may be contacted at
caddy@swlaw.com
Insurer's Summary Judgment Motion on Business Risk Exclusions Fails
November 15, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe insurer unsuccessfully moved for summary judgment on the CGL policy's business risk exclusions. Scottsdale Ins. Co. v. TL Spreader, LLC, (W.D. La. Oct. 20, 2017).
Helena Chemical Company contracted with its customer Wild Farms to sell and apply certain herbicides and pesticides to Wild Farms' 123 acre rice filed. Helena subcontracted the TL Spreader, LLC (TLS) to apply the chemicals to Wild Farm's rice field. The TLS employee failed to properly neutralize a chemical being used in the spray.
TLS finished its work on May 6, 2014, completing all its work for Helena's contract with Wild Farms. Three days after completion of the spraying, the rice crop first began to exhibit physical damage in the form of abnormal stunting, lesions, yellowing and death.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Update Relating to SB891 and Bond Claim Waivers
June 10, 2015 —
Christopher G. Hill – Construction Law MusingsSeveral bills were passed and will go into effect on July 1, 2015 that affect the construction industry here in Virginia. The most interesting of these was an amendment to the mechanic’s lien statutes relating to waivers of lien rights.
As I posted in March, SB891 amended the mechanic’s lien statute, Va. Code Section 43-3, to remove proactive waivers of lien and bond rights. This bill has been signed into law with a minor modification.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Digitalizing the Hospital Design Requirements Process
April 02, 2019 —
Aarni Heiskanen - AEC BusinessDecisions made at the early stages of a hospital project can have a huge impact on its life cycle value. To make sure that a hospital will be a good investment, its future users should be involved in helping set out the design requirements. A Finnish team of experts wanted to see if they could improve the process and set up an experiment to see how it could be done digitally.
Currently, over one billion euros are budgeted to hospital construction and renovation in Finland. Globally, the sum is around US$400 billion. You would imagine that the design for such large investments would be very efficient from the start. Unfortunately, that is not the case.
During the design phase, doctors, specialists, nurses, and other stakeholders take part in workshops in which they express their needs and requirements. For a large hospital project, 40 to 100 workshops are the norm. The work is done with a variety of tools, with sticky notes being the predominant technique.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Hurricane Handbook: A Policyholder's Guide to Handling Claims during Hurricane Season
October 11, 2021 —
Tracy Alan Saxe, Kelly A. Johnson, Samantha M. Oliveira & R. G. Nelson - Saxe Doernberger & VitaSDV's Natural Disaster Recovery Group presents the Hurricane Handbook: A Policyholder's Guide to Handling Claims during Hurricane Season. This handbook intends to be a practical guide on policyholder issues, both homeowners and business owners alike, when preparing for hurricane season and handling claims after a loss due to a hurricane. The handbook is a living document that will evolve over time, as our Natural Disaster Recovery Group members continue to contribute new and expansive content on the complex issues arising in this area. Remember to check back for additional information and updated content regarding the Hurricane Season Policyholder’s Handbook.
I. Are You Adequately Insured for a Hurricane?
Understanding the various types of coverage policyholders can purchase is vital to weathering the financial storm following a natural disaster.
Reprinted courtesy of
Tracy Alan Saxe, Saxe Doernberger & Vita,
Kelly A. Johnson, Saxe Doernberger & Vita,
Samantha M. Oliveira, Saxe Doernberger & Vita and
R. G. Nelson, Saxe Doernberger & Vita
Mr. Saxe may be contacted at TSaxe@sdvlaw.com
Ms. Johnson may be contacted at KJohnson@sdvlaw.com
Ms. Oliveira may be contacted at SOliveira@sdvlaw.com
Ms. Nelson may be contacted at RNelson@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Is Your Website Accessible And Are You Liable If It Isn't?
January 06, 2020 —
Kyle Janecek and Jeffrey Dennis - Newmeyer DillionTo anyone who does business online - beware. While the ADA has been in play for years, it did not necessarily account for all the technological advances that have been made over time. Specifically, when it comes to accommodations - what accommodations can and should be made within a website, and whether accommodations should be made on all websites or just some. However, because of this, a new type of lawsuit has emerged, and is slowly becoming more prominent. Since the Supreme Court refused to clarify this particular area of law, we must turn to the recent Ninth Circuit Ruling in Robles v. Domino's for guidance.
What Happened in Robles v. Domino's?
As part of a spree of litigation, Guillermo Robles had sued Domino's Pizza due to the lack of accessibility for the Domino's smartphone application and website. Mr. Robles is blind, and neither the website nor application, which allowed users to order Domino's food for pickup or delivery, and offer exclusive discounts, were accessible to him. The Domino's website and application were both incompatible with his chosen software, prompting a lawsuit in 2016. After a short success in the trial court due to the lack of guidance given to websites and applications in how to accommodate for the ADA, the Ninth Circuit overruled the trial court, finding that: (1) the ADA applied to Domino's as there was a nexus between the Domino's website and app, and physical restaurants; and (2) the lack of guidance to Domino's did not violate its right to due process.
The ultimate effect of Robles v. Domino's found that businesses cannot necessarily avoid ADA litigation, even though the federal government hasn't given guidelines on how to make a website or mobile application accessible.
What Happened at the Supreme Court?
Back in June, Domino's appealed the Ninth Circuit decision, prompting a flurry of amicus briefs. This was done, in part, because there is a circuit split between the Sixth, Ninth, and Eleventh Circuits requiring that a website has a physical nexus to a place of public accommodation (i.e. a "brick-and-mortar" location), and the First, Second, Fifth and Seventh Circuits, which will rule that a website is a place of public accommodation if it does something a place of public accommodation would do (i.e. Netflix showing films). In addition, parties aside from Domino's have been looking for further guidance given the lack of comments from the Department of Justice and Congress. This is especially relevant because the Department of Justice has been considering the application of the ADA to the internet from 1996 to 2018, resulting in some inconsistent comments regarding the need for rule making.
This had pushed Domino's and others to attempt to end the ongoing regulation through litigation and furthermore, due to the decision in the Ninth Circuit, to avoid the Domino's holding from creating a "defacto" requirement.
How Do You Prepare?
While there is an off-chance that this kind of civil ADA litigation will resurface to the Supreme Court, these claims tend to settle relatively quickly, and ultimately may prevent courts from providing any solid or concrete guidance on accessibility until either the Department of Justice provides guidelines or Congress amends the ADA to specifically address website accessibility.
However, a determination of what is "accessible" may be put forward due to the new proposed regulations for the CCPA set forth by California's Attorney General. The proposed regulations specifically state that a privacy policy should be accessible to consumers with disabilities, and at a minimum, should provide information on how a consumer with a disability can access the notice in an alternative format. Importantly, this removes the arguments on whether or not the website would have to be a place of public accommodation. It is now widely applicable to every website. Given the CCPA is to be enforced by the Attorney General, this presents a possible situation where the state of California will determine what is accessible through enforcement actions.
In the absence of guidelines however, you have four actions you can take to protect your business.
- Learn the standards. There are unofficial accessibility guidelines such as WCAG 2.0AA that are treated as an industry standard. While this may not completely protect you from claims made by litigants, this will help your business move towards compliance.
- Know and negotiate. When dealing with third party service providers or developers, make sure that accessibility is brought up, discussed, and addressed before moving forward with using that service provider or developer. If the developer or service provider cannot assure that their product is accessible, be prepared to walk away. A business may be found liable for the inaccessibility of an online service provider used by the business to provide the business's services.
- Beta test often. As technology changes or websites are updated to be more device-friendly, new code or functions may make a website less accessible for accessibility devices and software. In addition, just because a website meets the WCAG 2.0AA, this may not account for all accessibility issues, so it would be prudent and beneficial to be thorough.
- Get help. Consider hiring third parties to help you evaluate a plan for accessibility and keep you up-to date for online accessibility issues.
Nonetheless, there is still a significant risk and uncertainty for anyone who does business online, as any business has to be aware of the current general framework of laws and industry accessibility guidelines to hope they meet the murky definition of "accessible."
Kyle Janecek is an associate in the firms Privacy & Data Security practice, and supports the team in advising clients on cyber related matters, including policies and procedures that can protect their day-to-day operations. For more information on how Kyle can help, contact him at kyle.janecek@ndlf.com.
Jeff Dennis (CIPP/US) is the Head of the firm's Privacy & Data Security practice. Jeff works with the firm's clients on cyber-related issues, including contractual and insurance opportunities to lessen their risk. For more information on how Jeff can help, contact him at jeff.dennis@ndlf.com.
About Newmeyer Dillion
For 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that align with the business objectives of clients in diverse industries. With over 70 attorneys working as an integrated team to represent clients in all aspects of business, employment, real estate, privacy & data security and insurance law, Newmeyer Dillion delivers tailored legal services to propel clients' business growth. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
California Pipeline Disaster Brings More Scandal for PG&E
September 17, 2014 —
Mark Chediak – BloombergA deadly pipeline explosion that shattered a California town four years ago continues to rip through the state agency weighing a record penalty for the disaster.
The president of the California Public Utilities Commission asked his chief of staff to resign and recused himself from the case after “inappropriate e-mail exchanges” with PG&E Corp. (PCG) raised questions about bias, according to a statement from the commission yesterday. The CPUC may decide within weeks whether to levy a proposed $1.4 billion penalty -- the biggest safety fine in the state’s history -- against PG&E for the 2010 explosion of a natural gas pipeline that killed eight people in San Bruno.
Commission President Michael Peevey, who has been accused by San Bruno officials and consumer advocates of being too close to the utility, said in the statement he would not take part in penalty deliberations to eliminate any appearance of impropriety. The move is a step toward regaining credibility for the CPUC after two years of political infighting has created an ongoing climate of scandal.
Read the court decisionRead the full story...Reprinted courtesy of
Mark Chediak, BloombergMr. Chediak may be contacted at
mchediak@bloomberg.net