Unlicensed Contractor Shoots for the Stars . . . Sputters on Takeoff
September 20, 2017 —
Garret Murai - California Construction Law BlogElon Musk . . .
Eccentric engineer.
Technology billionaire.
And, now, litigation bad ass.
Frequent readers of the California Construction Law Blog know that we’ve talked about the importance of being properly licensed when doing construction work and the risks to you if you don’t.
One California contractor recently found this out the hard way.
In Phoenix Mechanical Pipeline, Inc. v. Space Exploration Technologies Corp., California Court of Appeals for the Second District, Case No. B269186 (June 13, 2017), contractor Phoenix Mechanical Pipeline, Inc. (Phoenix) lost its boosters . . . err britches . . when it sued Elon Musk’s Space Exploration Technologies Corp. (Space X) due to its failure to have a California contractor’s license.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Colorado Defective Construction is Not Considered "Property Damage"
September 12, 2022 —
Saxe Doernberger & Vita, P.C.In the July 5, 2022, case of Indian Harbor Ins. Co. v. Houston Casualty Co., the United States District Court for Colorado addressed the issue of whether damage to defectively installed balconies is considered “property damage” under Colorado law, requiring payment by a commercial general liability policy.
Facts of the Case
The case stems from a construction project where a subcontractor improperly installed balconies on an apartment complex. The owner of the project secured commercial general liability (CGL) coverage through an OCIP insured by Houston Casualty Company (HHC). The OCIP insured the general contractor and subcontractors. The general contractor also purchased a subcontractor default insurance policy insured by Indian Harbor.
All parties agreed that the subcontractor improperly installed portions of various balconies, including flashing, water-proof sealing, and water-resistant barriers, among other defects with the installation process. The parties also agreed that other portions of the balconies were properly installed. However, in order to repair the defects in the installations, every bit of each balcony had to be torn off and re-constructed.
Read the court decisionRead the full story...Reprinted courtesy of
Saxe Doernberger & Vita, P.C.
Be Sure to Bring Up Any Mechanic’s Lien Defenses Early and Often
November 27, 2023 —
Christopher G. Hill - Construction Law MusingsAs those of you who regularly read Musings are aware, mechanic’s liens are a big part of my law practice and a big issue here at this construction law blog. I’ve discussed the picky requirements of the mechanic’s lien statutes in Virginia and how the 90 and 150-day rules are strictly enforced. However, a recent case out of the City of Norfolk Virginia Circuit Court cautions that while failure to meet these strict requirements may invalidate a lien, it only does so if the owner or general contractor seeking to invalidate the lien argues the invalidity and/or presents evidence of that invalidity either pretrial or during trial.
In Premier Restoration LLC v. Barnes, the Court considered the following facts. The defendant homeowners had a house fire and the resulting damage was the subject of an insurance claim that was paid and checks sent to the homeowners. Premier filed a mechanic’s lien in response to Barnes’s failure to pay for Premier’s restoration construction services after Barnes’s home was destroyed by fire. Premier seeks a decree to enforce the lien, asking the court to order the sale of Barnes’s property to recover its damages or, alternatively, a judgment in its favor. With the Complaint seeking enforcement of the lien and damages for breach of contract, and this is a key point, Premier provided a copy of the mechanic’s lien along with the affidavit that is part of the statutory form swearing that the Owner was justly indebted to Premiere. The homeowners filed a counterclaim for unfinished work, including unfinished punch list work. After a trial during which no evidence regarding either the timeliness of the lien recording or whether any of the work sought to be encompassed in the lien was performed outside of the statutory 150-day window was presented by either side, the defendants filed a post-trial motion seeking to invalidate the lien as including sums for work outside of the 150-day window.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
2021 Executive Insights: Leaders in Construction Law
August 16, 2021 —
Donald Berry - Construction ExecutiveGregory Cokinos, President and CEO, Cokinos | Young
First, experience in the construction industry is of primary importance and vital to successfully negotiating construction contracts and handling construction claims and disputes. Even a mildly complex construction dispute is more than most non-construction lawyers can properly handle. Issues concerning scheduling, productivity, change management and risk shifting (among many others) are complex and unique to construction and can be further complicated by the procedural and substantive law that differs from jurisdiction to jurisdiction.
Second, it is essential that your law firm has a culture of representing construction professionals. Understanding construction nomenclature and how construction projects are staffed, organized and documented saves time and money in an already expensive and time-consuming process.
You cannot overstate the advantage of shared resources within an established construction firm when evaluating and handling construction matters. A law firm that dedicates a significant portion of its practice to the construction industry is uniquely positioned to realize this advantage. Finally, as I tell our young lawyers, “success” only comes before “work” in the dictionary. Hard work is the key to successfully negotiating a contract or executing a litigation plan in this complex industry. So, look for a firm that is not afraid of working long days and weekends to achieve success.
Reprinted courtesy of
Donald Berry, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Reconciling Prompt Payments and Withholding of Retention Payments
March 30, 2016 —
Eric J. Rollins, Esq. – Newmeyer & Dillion, LLPIt is common in California for the owners of a project to make monthly payments to a contractor for work as it is completed, but withhold a certain percentage as a guarantee of future satisfactory performance. Contractors almost always pass these withholdings on to their subcontractors. Unsurprisingly, disputes can arise regarding when the withheld retentions must be paid.
Civil Code section 8814, subdivision (a), states that a direct contractor must pay each subcontractor its share of a retention payment within ten days after receiving all or part of a retention payment. However, an exception exists -- a direct contractor may withhold from the retention paid to a subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount, whenever a “good faith dispute exists between the direct contractor and a subcontractor.” (See Cal. Civ. Code, § 8814, subd. (c).) The problem with the statute is that it offers no help in defining a “good faith dispute,” and the California courts have historically not provided much guidance either. Can a “good faith dispute” be any dispute between the contracting parties, e.g., a dispute regarding change orders, mismanagement, etc.? Or must the dispute relate specifically to the retention? Unfortunately for California litigants, the answer may depend on the appellate district in which the parties find themselves.
Read the court decisionRead the full story...Reprinted courtesy of
Eric J. Rollins, Esq., Newmeyer & Dillion, LLPMr. Rollins may be contacted at
eric.rollins@ndlf.com
Construction Needs Collaborative Planning
January 20, 2020 —
Aarni Heiskanen - AEC BusinessWhat makes construction different from manufacturing is its dynamic nature. Unlike a systemized production plant, a construction site is a mesh of interconnected processes that are far from optimized. The traditional top-down planning practice does not solve problems on the construction site, as recent research reveals. Making planning collaborative is a necessary step in making construction less wasteful.
Everybody in the industry has felt frustration with inefficiencies in construction, but seeing the data is still disconcerting. I’ve had the pleasure of attending several workshops organized by the Finnish Aalto University’s research teams. These eye-opening events both revealed how much waste we have in construction today and suggested solutions to this problem.
Four Aalto University graduate students shared insights from their research at a workshop of the Waste Workgroup of the Building 2030 consortium. They focused on projects where takt production, a lean construction method, had been used. Takt production breaks the work down into equally timed work batches and typically shortens project lead time considerably—up to 50%. However, even these well-planned projects included waste and unnecessary movement, as the researchers found out.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Third Circuit Affirms Use of Eminent Domain by Natural Gas Pipeline
November 28, 2018 —
Anthony B. Cavender - Gravel2GavelOn October 30, the U.S. Court of Appeals for the Third Circuit decided the case of Transcontinental Gas Pipe Line Co., LLC v. Permanent Easements for 2.14 Acres, et al. , affirming the District Court’s grant of a preliminary injunction to Transcontinental Gas Pipe Line Company, LLC (Transcontinental). This case involves the construction of the “Atlantic Sunrise Expansion Project,” a natural gas pipeline that runs through Pennsylvania, Maryland, Virginia, North Carolina and South Carolina.
Under the Natural Gas Act (NGA), pipeline companies can exercise powers of eminent domain when they are acting in the public interest. The Third Circuit cautions that this is a “standard” eminent domain power, and not a “quick take” that is permitted under another statute.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Strategy for Enforcement of Dispute Resolution Rights
May 30, 2018 —
Whitney Judson - Smith CurrieArbitration and litigation each offer their own benefits and drawbacks to litigants looking to resolve a construction dispute. A careful analysis of these benefits and drawbacks may be helpful in determining whether to avoid or pursue either dispute resolution process. Arbitration is oftentimes regarded as the more economically feasible dispute resolution option and is therefore attractive to many construction dispute litigants. Although arbitration may prove to be less expensive than litigation in the long run, some litigants may prefer to file a case in court because the upfront filing fees in litigation are less expensive than the filing fees of arbitration.
Litigants may also prefer the decision makers of one process for dispute resolution over another. Arbitrators in a construction dispute oftentimes have a background in the construction industry, whereas a judge or jury may not. Strategy may dictate whether the preferable decision maker should have experience within the construction industry or be free of any construction industry knowledge and possible biases. The finality of decisions may also be a reason to strategically choose one dispute resolution process over another. Arbitration decisions are overturned only under very narrow and specific circumstances. The losing party in litigation however, has a right to appeal decisions to a higher court and has more options for recourse when the findings of the court are not supported by the evidence or the law.
Read the court decisionRead the full story...Reprinted courtesy of
Whitney Judson, Smith CurrieMs. Judson may be contacted at