Encinitas Office Obtains Complete Defense Verdict Including Attorney Fees and Costs After Ten Day Construction Arbitration
May 23, 2022 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPartner Vik Nagpal and Associate Attorney Tim McNulty of the Encinitas office recently obtained a substantial victory on behalf of BWB&O’s client after a 10-day binding construction arbitration before a three-arbitrator panel of the American Arbitration Association.
BWB&O’s client was sued by the Owner of a commercial office building related to a multimillion-dollar tenant improvement project in San Diego. The Owner asserted construction defect damages, delay damages, architectural negligence, fraudulent billing practices and consequential damages of $3.6 million dollars. BWB&O’s client claimed breach of contract damages against the owner for failure to pay invoices.
The Owner who had substantial financial resources and a personal spite against the general contractor, unreasonably pursued the case with an extensive team of lawyers and experts. At an earlier full-day mediation, the owner rejected a reasonable settlement offer which included a settlement payment to the Owner and the client’s agreement to dismiss their affirmative claim for damages.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Designing a Fair Standard of Care in Design Agreements
February 21, 2022 —
ConsensusDocsOne of the concerns faced by construction companies is now design liability. Design liability concerns are not limited to just design-build projects. It is a hot-button issue for builders because the line between an architect’s responsibility to create sufficient design documents and a builder’s responsibility to execute the means, methods, and techniques is increasingly blurry. Problems arise when owners, design professionals, and builders point fingers, rather than truly collaborate, and communicate. While construction technologies used to assemble complex systems within buildings are increasingly sophisticated, such sophistication is unfortunately not matched with increased information sharing and effective communication.
Another reason for growing design liability is unclear and inadequate specifications. Too often projects rush as well as shortchange design budgets. And some projects use hybrid prescriptive and performance specifications. This hybrid approach often confuses and obfuscates rather than clarifies design requirements.
Read the court decisionRead the full story...Reprinted courtesy of
ConsensusDocs
The Five-Step Protocol to Reopening a Business
August 03, 2020 —
Amy R. Patton & Rana Ayazi - Payne & FearsOver the past few months, guidance on how to create a safer, low-risk workplace has frequently changed. Fortunately, the state of California has finally reached a point where comprehensive and concrete advice is now available.
On June 24, 2020, the California Statewide Industry Guidance to Reduce Risk website was updated. In addition to providing industry-specific guidance and opening checklists for approximately 40 different industries, the website now unambiguously requires all businesses—regardless of which “phase” they reopen—to follow a five-step protocol (as described in greater detail throughout this article):
- Perform a detailed risk assessment and create a site-specific protection plan.
- Train employees on how to limit the spread of COVID-19. This includes how to screen themselves for symptoms and when to stay home.
- Set up individual control measures and screenings.
- Put disinfection protocols in place.
- Establish physical distancing guidelines
Reprinted courtesy of
Amy R. Patton, Payne & Fears and
Rana Ayazi, Payne & Fears
Ms. Patton may be contacted at arp@paynefears.com
Ms. Ayazi may be contacted at ra@paynefears.com
Read the court decisionRead the full story...Reprinted courtesy of
How Tech Is Transforming the Construction Industry in 2019
July 08, 2019 —
Ginger Butz - Construction ExecutiveThe immediate applications and benefits of Industrial Internet of Things technologies are obvious in industries like manufacturing and computing, but these digital transformation technologies may not be top of mind for construction managers.
It’s time for that mindset to change. Worldwide spending on IIoT is expected to reach nearly $2 trillion in 2022, proving that these technologies hold a significant amount of value to the industries using them. That rings especially true in construction, where IIoT stands to bolster an already significant commitment to safety and communication. Construction managers should keep these technologies firmly on the radar when making investments in 2019.
Smart equipment
With sensors and radio-frequency identification (RFID) tags, even legacy construction equipment can become part of a construction company’s IIoT fleet. The data collected from these machines provides construction managers with a wealth of knowledge around downtime, safety, labor, efficiency and more.
Additionally, the next era of smart construction equipment will feature more autonomous vehicles and automatic equipment shutdown, both of which promote worker safety. Autonomous vehicles, which self-correct based on feedback and environmental factors, also free up human engineers to move from maintenance tasks into more complex roles that leverage the feedback data reported by IIoT machinery.
Reprinted courtesy of
Ginger Butz, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Ms. Butz may be contacted at
info@moreycorp.com
Year and a Half Old Las Vegas VA Emergency Room Gets Rebuilt
March 07, 2014 —
Beverley BevenFlorez-CDJ STAFFLess than two years have passed since the billion dollar Las Vegas VA Medical Center construction was completed, and “earthmovers have begun churning the site again, this time to expand the hospital’s emergency room because the existing one is inadequate,” according to the Las Vegas Review-Journal. The new emergency room project is estimated to cost $16 million.
The current emergency room’s design is flawed. “VA officials this week couldn’t explain why the ambulance parking area was designed to be roughly 50 yards from the emergency room’s south entrance, a distance that adds critical seconds to a lifesaving situation,” reported the Las Vegas Review-Journal. Furthermore, VA officials did not confirm “who drew up the flawed design” or who “was responsible for checking the blueprints.”
The Las Vegas Review-Journal also reported that another reason for the expansion is that the current emergency room is too small. A VA spokesman had told the journal that “the emergency room ‘was built based on the workload and the funding that was available at the time,’” yet the journal pointed out that “the number of potential veterans projected to use the center” has remained constant.
Read the court decisionRead the full story...Reprinted courtesy of
Manhattan Home Sales Rise at Slower Pace as Prices Jump
July 02, 2014 —
Prashant Gopal – BloombergManhattan apartment sales rose at the slowest pace in more than a year, indicating a surge in demand is easing as prices jump and inventory climbs from record lows.
Purchases of co-ops and condominiums increased 6.3 percent in the second quarter from a year earlier, the smallest gain since the start of 2013, according to a report today from appraiser Miller Samuel Inc. and brokerage Douglas Elliman Real Estate. The median price rose 5.2 percent to $910,000, and the average price per square foot surged 10 percent to $1,268.
Higher prices are encouraging more sellers to list properties and softening competition among buyers. The market is taking a “breather” after sales rose by an average of 28 percent in each of the previous four quarters, said Jonathan Miller, president of New York-based Miller Samuel.
Read the court decisionRead the full story...Reprinted courtesy of
Prashant Gopal, BloombergMr. Gopal may be contacted at
pgopal2@bloomberg.net
Building Group Has Successful 2012, Looks to 2013
February 14, 2013 —
CDJ STAFFThe North State Building Industry Association has looked back at 2012, and feels that they are “well-positioned to addressed future challenges in 2013 and beyond.” The organization, which represents home builders in Northern California, had several major accomplishments in 2012.
The NSBIA has managed to reduce fees that builders must pay. Due to their work with the Sacramento Regional County Sanitation District and the Sacramento Area Sewer District over the last several years, a new rate and fee methodology has been adopted, saving builders $3,000 per single family unit in SRCSD fees and $1,000 per acre in SASD fees. Fees were also reduced through agreements with the Folsom Cordova unified and Elk Grove school districts. The city of Rancho Cordova reduced its transportation fee by $3,500 per home.
In addition to their advocacy work, the NSBIA has continued its worker training programs. During 2012, 113 people participated in their Journeyman Upgrade classes, an increase of 20 from the prior year.
Read the court decisionRead the full story...Reprinted courtesy of
Define the Forum and Scope of Recovery in Contract Disputes
March 02, 2020 —
Phillip L. Sampson Jr. & Richard F. Whiteley - Construction ExecutivePrivate and public companies spend billions of dollars every year on construction projects. For these projects, time is money, and incorporating the most advantageous legal terms in the construction contract can minimize the number and extent of disputes, and ultimately save money.
It is important to remember that the provisions in construction contracts are negotiable. In a common scenario, the contractor and owner informally agree to the scope of a construction project and its cost. When it is time to reduce the deal to writing, the contractor and owner decide to use an AIA contract that appears to be a standard form. The document looks to be on point, and the parties simply need to fill in a few blanks with the cost and scope-specific information. Presuming that the AIA provisions are mutually protective and beneficial, the parties do not think about altering the “standard” terms. They sign the contract, and the project begins.
Months later, the owner and contractor end up disputing delays on the project, entitlement to various payments, and whether certain aspects of the work are defective. At this point, the parties realize that some of the contract’s terms could have been drafted a bit more favorably—but by that time it’s too late. So remember, construction contracts are negotiable, even provisions within “standard” AIA contracts.
Reprinted courtesy of
Phillip L. Sampson Jr. and Richard F. Whiteley, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Sampson may be contacted at phillip.sampson@bracewell.com.
Mr. Whiteley may be contacted at richard.whiteley@bracewell.com.
Read the court decisionRead the full story...Reprinted courtesy of