That’s What I have Insurance For, Right?
December 31, 2014 —
Craig Martin – Construction Contractor AdvisorAh, the age old question, What does my insurance really cover? A federal court in Georgia recently weighed in on this issue in Standard Contractors, Inc. v. National Trust Insurance Company, and ruled that a contractor’s commercial general liability insurer did not have to pay for damage caused by a subcontractor.
Standard Contractors was hired to renovate the pool on an army base. Standard hired a subcontractor to for design and installation work. The subcontractor’s work was subpar in that the subcontractor omitted a number of parts, installed the wrong parts, and caused more than $400,000 in damage to the pool. Standard submitted a claim to its insurer seeking coverage for the loss under its commercial general liability policy.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at
cmartin@ldmlaw.com
Structural Engineer Found Liable for Defects that Rendered a Condominium Dangerously Unsafe
June 22, 2016 —
Paul R. Cressman, Jr. – Ahlers & Cressman Construction Law BlogOn May 3, 2016, the Washington State Court of Appeals affirmed a jury’s verdict in favor of a condominium HOA against a structural engineer for $1,149,332 in damages.[1]
The project in question was The Pointe, an upscale condominium building in Westport, Washington. The developer was Dodson-Duus, LLC. The architect was Elkins Architects (“Elkins”). The structural engineer was Engineers Northwest, Inc. (“ENW”). ENW contracted with Elkins for the structural engineering work.
Birds flying past 3 construction cranesBoth the design and construction of the building suffered from defects. In particular, the lateral force resistance system was insufficient to withstand a large seismic event. The defects included improperly nailed shear walls, weak connections between shear walls and floor joists, improperly-sized floor sheathing, a weak second-floor diaphragm, and omitted hold-downs connecting shear walls to a steel beam. The use of gypsum sheathing also created a risk of corrosion to the building’s steel structure. Evidence tied each of these defects to some aspect of ENW’s structural calculations and designs. Evidence also tied omission of the hold-downs to the contractor’s construction decisions.
Read the court decisionRead the full story...Reprinted courtesy of
Paul R. Cressman, Jr., Ahlers & Cressman PLLC Mr. Cressman may be contacted at
pcressman@ac-lawyers.com
Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
Good News on Prices for Some Construction Materials
June 28, 2021 —
ABC - Construction ExecutiveThe elevated price of softwood lumber, a major talking point during much of the pandemic, appears to have peaked in early May at more than $1,700 per thousand board feet. As of June 23, the price has fallen below $900 per board feet, down about 49% in less than two months.
That’s still an unusually lofty price by historic standards—prices remain almost twice as high as in February 2020—but the trend is very much in the right direction. Builders that had been hoarding lumber have now begun to sell from their own inventory, other builders have delayed lumber purchases in anticipation of lower prices and sawmill operators have been adding shifts, as well as expanding capacity, all of which puts downward pressure on prices.
Reprinted courtesy of
ABC, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Communications between Counsel and PR Firm Hired by Counsel Held Discoverable
March 22, 2017 —
Kevin R. Crisp, David W. Evans, & Sarah A. Marsey – Haight Brown & Bonesteel LLPCounsel handling cases involving newsworthy facts and litigation often hire public relations (“PR”) consultants. In Nicholas Behunin v. The Superior Court of Los Angeles County, 2017 DJDAR 2405 (No. B272225 March 14, 2017) the California Court of Appeal, Second District, denied a petition for writ of mandate concerning a trial court discovery order holding that communications between a plaintiff’s attorney and a public relations firm counsel hired for the purpose of creating a website for the Plaintiff were discoverable, despite claims that such communications were protected from disclosure by attorney-client privilege.
Plaintiff sued Defendants -- (the) Charles Schwab and his son Michael Schwab -- over an unsuccessful real estate investment. Plaintiff’s attorneys hired a public relations consultant to create a website (www.chuck-you.com) that sought to link the Schwabs with the late Indonesian dictator Suharto’s family. The court succinctly described the web site as “a social media campaign to induce the Schwabs to settle the case.”
Reprinted courtesy of Haight Brown & Bonesteel LLP attorneys
Kevin R. Crisp,
David W. Evans and
Sarah A. Marsey
Mr. Crisp may be contacted at kcrisp@hbblaw.com
Mr. Evans may be contacted at devans@hbblaw.com
Ms. Marsey may be contacted at smarsey@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Seventh Circuit Remands “Waters of the United States” Case to Corps of Engineers to Determine Whether there is a “Significant Nexus”
July 10, 2018 —
Anthony B. Cavender - Gravel2Gavel Construction & Real Estate Law Blog On June 27, the U.S. Court of Appeals for the Seventh Circuit decided the case of Orchard Hill Building Co. v. U.S. Army Corps of Engineers. The Court of Appeals vacated the decision of the District Court granting the U.S. Army Corps of Engineers’ (Corps) motion for summary judgment dismissing the Orchard Hill Building Company’s (Orchard) complaint that the Corps’ jurisdictional determination erroneously found that the waters at issue were “jurisdictional waters” under the Clean Water Act (CWA) subject to the Corps’ jurisdiction. Acknowledging that the Corps and EPA had promulgated a new rule re-defining “waters of the United States” in 2015—which is now being challenged in the courts—the Court of Appeals noted that this case is controlled by the pre-2015 definition of “waters of the United States.” The Court of Appeals remanded the case to the Corps, directing it to determine if there was a significant nexus, as required.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, Pillsbury Winthrop Shaw Pittman LLPMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Formaldehyde-Free Products for Homes
March 05, 2015 —
Beverley BevenFlorez-CDJ STAFFBuilder Magazine reported that builders are “making indoor air quality a major concern,” including choosing healthier, formaldehyde-free products.
Builder explained the problems with certain chemicals: “Formaldehyde and other VOCs, most frequently found in wood products, finishes, and paints, have been chief among the pollutants targeted for potentially dangerous health effects, such as respiratory issues and irritation of the eyes, nose, throat, and skin.”
Read the court decisionRead the full story...Reprinted courtesy of
Thieves Stole Backhoe for Use in Bank Heist
July 31, 2013 —
CDJ STAFFYou can do a lot with a backhoe, but maybe not use it for bank robbery. The New York Daily News wasn’t clear on how many were involved, but described them as “a brazen crew of bandits.” They stole a backhoe from a construction site and used it to pry an ATM from a bank. When they couldn’t get the ATM open, they jumped into a black SUV and left the scene.
The bandits were engaging in a sort of ATM spree. They did manage to open two ATMs, each holding more than $7,000 in cash. They were less successful at their use of heavy machinery. In an earlier heist, they used a tow truck to try to remove an ATM, but the chain snapped and the bank’s alarm rang. The Daily News quotes one former tow truck driver who said that it was “stupid to use a tow truck.” In her experience, “those chains snap at any time.”
Read the court decisionRead the full story...Reprinted courtesy of