Brooklyn Atlantic Yards Yields Dueling Suits on Tower
September 03, 2014 —
Erik Larson – BloombergForest City Ratner Cos., the initial developer of Brooklyn’s $4.9 billion Atlantic Yards project surrounding Barclays Center arena, exchanged lawsuits with the Swedish construction firm Skanska AB (SKAB) over claims of design flaws and delays in building a stalled residential tower.
The lawsuits, filed today in Manhattan state court, focus on a contract for the 34-floor “modular” residential high-rise building under construction next to the arena for the National Basketball Association’s Brooklyn Nets that opened in 2012 as the centerpiece of the former rail yard and a symbol of the New York borough’s resurgence.
Skanska, a Stockholm-based firm that has grown to become New York’s second-largest building contractor, seeks at least $50 million in damages for changes to the building that were made without consultation, according to its complaint. Brooklyn-based Forest City Ratner blames Skanska for the project’s problems, citing “tens of millions of dollars” in cost overruns caused by a lack of skill and a failure to adhere to terms of the 2012 contract.
Read the court decisionRead the full story...Reprinted courtesy of
Erik Larson, BloombergMr. Larson may be contacted at
elarson4@bloomberg.net
It Has Started: Supply-Chain, Warehouse and Retail Workers of Essential Businesses Are Filing Suit
June 22, 2020 —
Robert G. Devine, James Burger & Douglas Weck - White and Williams LLPSupply-chain businesses that are appropriately characterized as “essential” have remained open for the delivery of critical supplies while everyone else has been told to close up shop and stay home. Now essential-business employees are contracting COVID-19 and filing suit. Following up on our earlier piece — “Is a Violation of a COVID-19 Order the Basis For Civil Liability?” — it is important to recognize that government directives, oftentimes couched as “recommendations,” can come to define what it means to provide a reasonably safe workplace that protects employees from COVID-19. While common law negligence defenses consider the reasonableness of conduct, these directives will likely become the standard.
The cases that have been filed are overwhelmingly premised upon the timeless negligence construct. The negligence construct, simply put, imposes a duty to act as a reasonable person would under the circumstances. Nonetheless, while the negligence construct lives in the ordinary world of “reasonableness,” infection-control guidance lives in the rapidly developing world of the science of COVID-19. Guidance on seemingly basic questions, such as the methods of transmission (e.g., personal contact, mucus membrane only, airborne transmission) or even the virus’s shelf life on different surfaces, of particular interest packaging and material handling equipment, can change by the day. All of this provides challenges for the supply-side business looking to protect its workforce.
Reprinted courtesy of White and Williams LLP attorneys
James Burger,
Robert Devine and
Douglas Weck
Mr. Burger may be contacted at burgerj@whiteandwilliams.com
Mr. Devine may be contacted at deviner@whiteandwilliams.com
Mr. Weck may be contacted at weckd@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida District Court Finds That “Unrelated” Design Errors Sufficient to Trigger “Related Claims” Provision in Architects & Engineers Policy
March 02, 2020 —
Jason Taylor - Traub LiebermanMost professional liability polices include some form of a “related claims” provision that generally provides where two or more claims or wrongful acts are causally or logically related, they will be deemed to constitute a single claim. Importantly, these provisions typically provide that those “claims” are then deemed to have been “first made” at the time the first claim or act was committed for purposes of the policy’s claims-made and reporting requirements. Understandably, these provisions provide insurers and insureds with some clarity over the number and timing of claims that could involve multiple errors or omissions, and potentially aggregate all related claims or acts into a single policy period. While reasonable in principle, application of such provisions, especially involving large scale design and construction projects, is not always so easy.
Nova Southeastern University, Inc. v. Continental Cas. Co., 18-cv-61842 (S.D. Fla. Dec. 27, 2019), involved such an insurance coverage dispute with a design project gone wrong. DeRose Design Consultants, Inc. (“DeRose”) was hired as a structural engineer to design “ice tanks” to store and chill water for an energy efficient air conditioning facility constructed on the campus of Nova Southeastern University (“NSU”). An early water test on one of the tanks determined the walls of the ice tank deflected, leaked, and cracked when the tank was filled with water. DeRose later discovered that the problems with the ice tank were caused by a structural design error.
The first errors were discovered in early 2009, and reported under DeRose’s professional liability policy with Evanston. DeRose then created a remedial design to repair the tanks, which involved strengthening repairs. Additional leaking and an early indication of corrosion involving the Remedial Design arose as early as October 25, 2009. Several field investigation reports were prepared in 2011 and 2012 confirming these issues with the Remedial Design. A third report in February 2012, however, identified a new error involving the concrete slab under the ice tanks also designed by DeRose. The third report concluded that the concreate slab was overstressed and could not handle the loads of the ice tanks. The report also concluded, however, that the design defects in the concrete slab were “unrelated” to the original design defect of the ice tank walls or Remedial Design.
Read the court decisionRead the full story...Reprinted courtesy of
Jason Taylor, Traub LiebermanMr. Taylor may be contacted at
jtaylor@tlsslaw.com
Differing Site Conditions Produce Differing Challenges
February 18, 2019 —
Sarah E. Carson - Smith CurrieThe saying “The best laid plans of mice and men often go awry” can too often apply in the construction industry. A contractor may receive a description of site conditions that is ultimately found flawed or misleading. The costs associated with addressing these surprise conditions often fall on the contractor to pay. The following article details proactive steps to avoid costly obstacles that may cause a project’s success to go awry.
What are Differing Site Conditions?
There are generally two recognized types of differing site conditions. The first, often referred to as a “Type I Changed Condition,” exists when a specification in the conditions indicated in the contract documents varies from what is represented. The second category, generally referred to as a “Type II Changed Condition,” is a variance so unusual in its nature that it materially differs from conditions ordinarily encountered in performing the type of work called for in the geographic area where the project is located.
Read the court decisionRead the full story...Reprinted courtesy of
Sarah E. Carson, Smith CurrieMs. Carson may be contacted at
secarson@smithcurrie.com
Single-Family Home Starts Seen Catching Up to Surging U.S. Sales
May 07, 2015 —
David Wilson – BloombergNew single-family houses are selling fast enough in the U.S. that homebuilders will have to pick up the pace of starting them, according to Neil Dutta, head of U.S. economics at Renaissance Macro Research LLC.
The attached chart compares annual growth rates in sales and starts, as compiled by the Commerce Department, during the past 25 years. The top panel shows the rates, while the bottom panel tracks the percentage-point gap between then.
Last month’s sales of one-family homes totaled 510,000 at an annual rate, according on the average estimate of economists in a Bloomberg survey. The projection amounts to a 26.6 percent increase from a year ago. Builders began working on 2.7 percent fewer homes in March, according to data released yesterday. The 29.3-point differential would be the widest since July 1995.
Read the court decisionRead the full story...Reprinted courtesy of
David Wilson, BloombergMr. Wilson may be contacted at
dwilson@bloomberg.net
Duty to Defend Triggered by Damage to Other Non-Defective Property
February 20, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court found the insurer must defend because there was a possibility of damage to property due to work not performed by the insured. B&W Paving & Landscape, LLC v. Employers Mut. Cas. Co., 2022 U.S. Dist. LEXIS 225783 (D. Conn. Dec. 15, 2022).
In 2010, Whiting Turner Contracting Company (WT) contracted with United Illuminating Company (UI) to act as general contractor for the construction of UI's new central facility. WT subcontracted with Cherry Hill Construction, Inc. (Cherry Hill) for work underneath the parking lot and driveways, including installing base and sub base materials. WT also subcontracted with B&W Paving and Landscape, LLC (B&W) for the asphalt paving.
In 2018, UI sued WT for defective and incomplete work. WT then filed a third-party compact against its subcontractors, including B&W. WT sued for contribution for any liability it may have to UI for the paving work.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Specification Challenge; Excusable Delay; Type I Differing Site Condition; Superior Knowledge
January 02, 2024 —
David Adelstein - Florida Construction Legal UpdatesAn Armed Services Board of Contract Appeals dispute, Appeal of L.S. Black-Loeffel Civil Constructors JV, ASBCA No. 62402, 2023 WL 5827241 (ASBCA 2023), involved which party bore liability for delay—the federal government or the prime contractor–based on various legal theories. Without detailing the factual details, a number of interesting legal issues were raised in this dispute including (1) a defective specification challenge, (2) excusable delay, (3) Type I differing site condition, and (4) superior knowledge. These legal issues are discussed below.
1. Specification Challenge (Defective Specifications)
The contractor claimed that the government’s specifications were defective in regard to a thermal control plan. The government countered that the specifications were not design specifications but performance specifications. The specifications were performance based because they did not tell the contractor how to achieve the performance-based criteria.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
The CA Supreme Court Grants Petition for Review of McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist.) As to Whether the Right to Repair Act (SB800) is the Exclusive Remedy for All Defect Claims Arising Out of New Residential Construction
December 02, 2015 —
Richard H. Glucksman, Esq., Glenn T. Barger, Esq., Jon A. Turigliatto, Esq., & David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinAs anticipated in a prior CGDRB 2015 Bulletin that discussed the Fifth Appellate District Court’s noteworthy opinion in McMillin Albany LLC v. Super Ct. 2015 F069370 (Cal.App.5 Dist), the California Supreme Court has granted the petition for review of the McMillin Albany decision. The Supreme Court will attempt to resolve the conflict of authority presented by the Fourth Appellate District Court’s opinion in Liberty Mut. Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98 and the Fifth Appellate District Court’s rejection of the Liberty Mutual holding in McMillin Albany.
In Liberty Mutual, the Fourth District Court of Appeal held that compliance with SB800’s pre-litigation procedures prior to initiating litigation is only required for defect claims [violations of SB 800’s building standards] that have not yet resulted in actual property damage. Where damage has occurred, a homeowner may initiate litigation under common law causes of action without first complying with the pre-litigation procedures set forth in SB 800.
Two years later, the Fifth District Court of Appeal, in McMillin Albany, held that the California Legislature intended that all construction defect claims arising out new residential construction are subject to the standards and requirements of the Right to Repair Act [SB800], including specifically, the requirement that the claimant provide the builder with notice and an opportunity to repair prior to filing a lawsuit. According to the Court, SB 800 is the exclusive remedy for all defect claims arising out of new residential construction sold on or after January 1, 2003.
The holdings in Liberty Mutual and McMillin Albany present a conflict of authority that the California Supreme Court has appropriately deemed worthy of review. The parties will now be permitted to file briefs on the merits and amicus briefs will certainly be submitted by the defense and plaintiff bars.
Our firm will be closely monitoring this case, the outcome of which will significantly impact pre-litigation construction defect claims going forward. We will provide updates as to further activities and the Supreme Court’s decision.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Glenn T. Barger,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Barger may be contacted at gbarger@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of