Navigating Complex Preliminary Notice Requirements
March 30, 2016 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome back a good friend, Scott Wolfe. Scott is the founder of zlien, a cloud-based platform that gives construction industry participants control over their financial risk and payment processes. The zlien platform manages the mechanics lien compliance process for all parties in the contracting chain, automating and optimizing the exchange of preliminary notices, monitoring lien rights and exposure, and exchanging lien waivers. zlien empowers over 10,000 companies to optimize their credit and financial risk management, and works to promote a fair and transparent construction payment process, improve B2B relationships, facilitate faster payments, and reduce legal and financial risk.
Sending preliminary notice is the most important step in mechanics lien compliance. A majority of states require preliminary notice (sometimes called a pre-lien notice or notice to owner) from contractors, material suppliers, and other construction parties. Even if preliminary notice is not required, however, it is best practice to send this document on all projects for a variety of reasons.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Loss of Use From Allegedly Improper Drainage System Triggers Defense Under CGL Policy
February 28, 2018 —
Katherine E. Miller and Michael S. Levine – Hunton Insurance Recovery BlogThe Eleventh Circuit, in
Mid-Continent Casualty Co. v. Adams Homes of Northwest Florida, Inc., No. 17-12660, 2018 WL 834896, at * 3-4 (11th Cir. Feb. 13, 2018) (per curiam), recently held under Florida law that a homebuilder’s alleged failure to implement a proper drainage system that allowed for neighborhood flooding triggered a general liability insurer’s duty to defend because the allegations involved a potentially covered loss of use of covered property.
Reprinted courtesy of
Katherine E. Miller, Hunton & Williams and
Michael S. Levine, Hunton & Williams
Ms. Miller may be contacted at kmiller@hunton.com
Mr. Levine may be contacted at mlevine@hunton.com
Read the court decisionRead the full story...Reprinted courtesy of
Where Do We Go From Here?
March 21, 2022 —
Christopher G. Hill - Construction Law MusingsGreen Builder CoalitionFor this week’s Guest Post Friday, I welcome an old friend and past Guest Post Friday contributor, Mike Collignon. Mike is the Co-Founder and Executive Director of the Green Builder® Coalition. He engages in national and state-level advocacy and publishes regular content for Green Builder® Media. Mike is also the Chair of the WERS Development Group and has served as the moderator or host for Green Builder® Media’s Impact Series webinars from 2012– present.
This post originally appeared on Green Builder® Media’s Code Watcher.
Do you ever have a line from a song just pop into your head? I get that… a lot. It’s probably due to my lifelong love of music. Anyway, while I was researching this column, the line that cites the title of “Where Do We Go From Here?” by Filter started playing between my ears. You’ll see why in a couple of minutes.
In case you didn’t
read about it here or elsewhere, the IECC development process has undergone an overhaul. It is now following a standards process, yet it retains the word “code” in the name. The residential committee (which is the scope of this column) is now a consensus committee and has been greatly expanded. Proposals are still submitted, reviewed and voted on by the committee. On the surface, it doesn’t sound like much has changed. As they say, the devil is always in the details.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Newmeyer & Dillion Welcomes Three Associates to Newport Beach Office
January 26, 2017 —
Newmeyer & Dillion LLPNEWPORT BEACH, Calif. – JANUARY 24, 2017 – Enjoying rapid expansion in many primary practice areas, Newmeyer & Dillion LLP is pleased to welcome new associates
Jenny Guzman and
Jason Moberly Caruso, and welcomes back
Lily (Toubi) Razai to the Newport Beach office. The addition of these three associates fortifies the firm’s commitment to provide unparalleled service to our clients.
Firm Managing Partner,
Jeff Dennis, explained that each hire addresses the immediate and long-term needs of our clients, and firm's desire for strategic growth. "We always remain focused on what will allow us to better represent our clients, not just now but far into the future. We are excited to bring these three talented lawyers aboard as we continue to expand our capabilities across practice areas.”
Guzman, Caruso and Razai each practice business and real estate litigation, with Razai’s practice including land use and eminent domain matters. Caruso also practices construction law and Guzman's practice also focuses on business and real estate transactions.
Each attorney has unique strengths that continue to diversify the firm’s approach to their clients. In addition to serving clients in state and federal courts, Razai has extensive experience in alternative dispute resolution proceedings, and has served as a mediator in state courts. Awarded Super Lawyers 2016 Rising Star, Caruso utilizes his extensive judicial experience to argue on behalf of his clients at various levels from arbitration to the Ninth Circuit Court of Appeals. Guzman draws on her past experience in private equity and venture capital to protect businesses and help them achieve their full potential. These three associates, along with their diverse experience and cohesive strengths, further reinforce N&D’s foundation for continued growth and excellence.
About Newmeyer & Dillion
For more than 30 years, Newmeyer & Dillion has delivered creative and outstanding legal solutions and trial results for a wide array of clients. With over 70 attorneys practicing in all aspects of business, employment, real estate, construction and insurance law, Newmeyer & Dillion delivers legal services tailored to meet each client’s needs. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer & Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949-854-7000 or visit www.ndlf.com.
Read the court decisionRead the full story...Reprinted courtesy of
Failure to Meet Code Case Remanded to Lower Court for Attorney Fees
May 24, 2011 —
CDJ STAFFJudge Patricia J. Cottrell, ruling on the case Roger Wilkes, et al. v. Shaw Enterprises, LLC, in the Tennessee Court of Appeals, upheld the trial court’s conclusion that “the builder constructed the house in accordance with good building practices even though it was not in strict conformance with the building code.” However, Judge Cottrell directed the lower court to “award to Appellants reasonable attorneys' fees and costs incurred in their first appeal, as determined by the trial court.”
Judge Cottrell cited in her opinion the contract which specified that the house would be constructed “in accordance with good building practices.” However, after the Wilkes discovered water leakage, the inspections revealed that “that Shaw had not installed through-wall flashing and weep holes when the house was built.” The trial court concluded that:
“Separate and apart from the flashing and weep holes, the trial court concluded the Wilkeses were entitled to recover damages for the other defects they proved based on the cost of repair estimates introduced during the first and second trials, which the court adjusted for credibility reasons. Thus, the trial court recalculated the amount the Wilkeses were entitled to recover and concluded they were entitled to $17,721 for the value of repairs for defects in violation of good business practices, and an additional 15%, or $2,658.15, for management, overhead, and profit of a licensed contractor. This resulted in a judgment in the amount of $20,370.15. The trial court awarded the Wilkeses attorneys” fees through the Page 9 first trial in the amount of $5,094.78 and discretionary costs in the amount of $1,500. The total judgment following the second trial totaled $26,973.93.”
In this second appeal, Judge Cottrell concluded, that “the trial court thus did not have the authority to decide the Wilkeses were not entitled to their attorneys” fees and costs incurred in the first appeal.”
Read the court’s decision
Read the court decisionRead the full story...Reprinted courtesy of
Anthony Garasi, Jared Christensen and August Hotchkin are Recognized as Nevada Legal Elite
July 06, 2020 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is proud to announce Partners
Anthony Garasi and
Jared Christensen in our Las Vegas office, along with Associate
August Hotchkin in our Reno office are being recognized as Nevada Legal Elites in the Nevada Business Magazine.
The Nevada Legal Elite list includes the top 4 percent of attorneys in the state broken down by location. To qualify, each nominee goes through an extensive verification process resulting in the top attorneys in the state, chosen by their peers. Upon the nomination process closing, each ballot is individually reviewed for eligibility and every voting attorney is verified with the State Bar of Nevada.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Florida Self-Insured Retention Satisfaction and Made Whole Doctrine
March 11, 2014 —
Scott Patterson – CD CoverageIntervest Construction of Jax, Inc. v. General Fidelity Insurance Co., * So.2d * (Fla. 2014), the issue was whether the insured general contractor could satisfy the SIR in its CGL policy with funds it received from the insurer of a subcontractor in settlement of the general contractor’s contractual indemnity claim against that subcontractor. ICI was the general contractor for a residence sold to Ferrin. Several years after completion, Ferrin suffered injuries in a fall while using attic stairs installed by ICI’s subcontractor Custom Cutting. Ferrin sued ICI but not Custom Cutting. ICI was insured by General Fidelity with a $1M SIR. ICI sought contractual indemnity from Custom Cutting. The Ferrin suit was ultimately settled for $1.6M. Custom Cutting’s CGL insurer paid $1M to ICI to resolve ICI’s contractual indemnity claim. Using the $1M paid on behalf of Custom Cutting and $300K of its own funds, ICI paid $1.3M to Ferrin. General Fidelity paid the remaining $300K with an agreement with ICI that each was entitled to seek reimbursement of $300K from the other. ICI filed suit in Florida state court. General Fidelity removed to federal court. The Eleventh Circuit certified the relevant questions to the Supreme Court of Florida.
The Florida Supreme Court first held that the General Fidelity SIR allowed ICI to satisfy the SIR through indemnification payments received from a third party. While the SIR provision stated that it must be satisfied by the insured, it did not include any language proscribing the source of the funds used by the insured to satisfy the SIR. The court distinguished other decisions where the SIR endorsement expressly stated that payments by others, including other insurers, could not satisfy the SIR. The court also relied on the fact that ICI “hedged its retained risk” by paying for its entitlement to contractual indemnification from its subcontractor years prior to purchasing the General Fidelity policy.
Read the court decisionRead the full story...Reprinted courtesy of
Scott Patterson, CD Coverage
Williams v. Athletic Field: Hugely Important Lien Case Argued Before Supreme Court
June 17, 2011 —
Douglas Reiser, Builders Council BlogWell, it finally made it. The most important Washington lien case of recent memory was argued in front of the Washington Supreme Court on Tuesday, June 14, 2011. So, what should we all expect?
As I was reading through my RSS feeds this afternoon ? I was stopped dead in my tracks. Williams v . Athletic Field, the Division II case that has been a frequent topic here on Builders Counsel, has finally been argued before the Supreme Court. All of you who have been anxiously awaiting this day, you can check out the Supreme Court submissions by following this link.
The Williams case has been the center of attention for construction lawyers and construction organizations over the past year. Some have called for complete lien law reform, others have tried to patch a hole in the law. Now, we can expect a ruling from the highest court in the state. That ruling will have a major impact on whether the Legislature feels compelled to change lien law.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of