10 Answers to Those Nagging Mechanics Lien Questions Keeping You Up at Night. Kind of
November 05, 2014 —
Garret Murai - California Construction Law BlogConstruction lawyers may not ponder the great questions in life.
We leave that to the estate planning attorneys.
But ponder we do.
And the next case, as I’ll explain below, “kind of” answers 10 important mechanics lien questions we construction attorneys toss and turn over at night.
Background
In Palomar Grading & Paving, Inc. v. Wells Fargo Bank, Case Nos. G049907 and G049910 (October 14, 2014), developer Inland-LGC Beaumont, LLC (“Inland”) hired general contractor 361 Group Construction Services, Inc. (“361″) to construct a Kohl’s department store in Beaumont, California.
The Kohl’s department store was to be constructed on one parcel of a three-parcel tract. Inland later sold the parcel on which the Kohl’s department store was to be located to Kohl’s and the two other parcels were later acquired by Wells Fargo who foreclosed on the construction loan for the project.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Kronick Moskovitz Tiedemann & GirardMr. Murai may be contacted at
gmurai@kmtg.com
Edison Utility Accused of Igniting LA Fire in Lawsuits
January 21, 2025 —
Jef Feeley, Mark Chediak & Malathi Nayak - BloombergEdison International Inc.’s southern California utility faces lawsuits blaming the energy provider’s equipment for igniting one of the wildfires still raging in the second-largest US metropolis.
The first of several suits filed Monday was brought on behalf of a group of homeowners, renters, business owners and others with properties destroyed by the deadly Eaton Fire in the Pasadena area. The complaints allege that Southern California Edison power lines were the cause of the blaze that leveled the community of Altadena. The initial suits are expected to be followed by thousands more legal claims.
Reprinted courtesy of
Jef Feeley, Bloomberg,
Mark Chediak, Bloomberg and
Malathi Nayak, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Update: Amazon Can (Still) Be Liable in Louisiana
December 31, 2024 —
Michael Ciamaichelo - The Subrogation StrategistOn November 25, 2024, in Pickard v. Amazon.com, Inc., No. 5:20-cv-01448, 2024 U.S. Dist. LEXIS 215377, the United States District Court for the Western District of Louisiana (District Court) ruled that Amazon.com, Inc. (Amazon) could be liable for manufacturer-seller liability under the Louisiana Products Liability Act (LPLA) for a defective product sold by a third-party seller through the “Fulfillment by Amazon” program (FBA). The court also dismissed two tort claims against Amazon as follows: (i) Amazon does not qualify as a “seller” for purposes of non-manufacturer seller liability (because passing title is required for that claim); and (ii) there is insufficient evidence to prove the decedent, Archie Pickard (Pickard), relied on Amazon’s safety practices when purchasing the defective product, precluding a claim for negligent undertaking.
Background
Pickard died from injuries sustained in a house fire allegedly caused by a defective battery charger he purchased on Amazon. Jisell, a Chinese company and a third-party seller, manufactured and sold the charger. Amazon never took title to the charger but stored it in its warehouse and delivered it to Pickard through the FBA. Pickard’s children filed a wrongful death lawsuit against Amazon alleging three claims: (i) manufacturer-seller liability under the LPLA; and tort-based claims of (ii) non-manufacturer seller liability and (iii) negligent undertaking. After Amazon moved for summary judgment on all claims, the District Court certified questions to the Supreme Court of Louisiana (Supreme Court) seeking guidance as there was minimal guidance regarding the application of products claims to online marketplaces.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
Earth Movement Exclusion Bars Coverage
March 19, 2015 —
Tred R. Eyerly – Insurance Law HawaiiDamage to the YMCA recreation center was not covered due to application of the earth movement exclusion. YMCA of Pueblo v. Secura Ins. Co., 2015 U.S. Dist. Lexis 15249 (D. Colo. Feb. 6, 2015).
On October 11, 2013, the insureds discovered a leaking water line in the men's shower, where one of the shower's on/off valves had detached from the water pipe behind the wall. The leak was repaired the same day.
On October 13, 2013, the pool deck near the therapy pool and surrounding block walls shifted and collapsed. The insurer admitted there was damage to the property. Several leaks were discovered in the pipes under and near the therapy pool, and the pool lost several inches of water.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
One More Mechanic’s Lien Number- the Number 30
March 06, 2023 —
Christopher G. Hill - Construction Law MusingsI’ve spoken here often about the numbers
90 and 150 as they relate to
Virginia mechanic’s liens. These numbers are important for all mechanic’s liens in Virginia, whether commercial or residential (meaning liens for 1 and 2-family homes). There is another number, 30, that is important for those construction contractors that perform work on single and two-family homes. Where a mechanic’s lien agent is named on the building permit (or possibly just named if not stated on the permit), and
among other requirements,
Va. Code 43-4.01 requires that, in order to have lien rights at the project, the contractor must provide notice to the mechanic’s lien agent within 30 days of beginning work that it is performing work and shall seek payment for the work.
Further, the mechanic’s lien agent notice must contain the following:
(i) the name, mailing address, and telephone number of the person sending such notice, (ii) the person’s license or certificate number issued by the Board for Contractors pursuant to Chapter 11 (§ 54.1-1100 et seq.) of Title 54.1, if any, and the date such license or certificate was issued and the date such license or certificate expires, (iii) the building permit number on the building permit, (iv) a description of the property as shown on the building permit, and (v) a statement that the person filing such notice seeks payment for labor performed or material furnished.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Harmon Tower Construction Defects Update: Who’s To Blame?
August 17, 2011 —
CDJ STAFFReporting on the site VegasInc.com, Liz Benton notes that “nobody wants to take the fall for what happened at Harmon.” Work on the Harmon hotel building in Las Vegas’s CityCenter stopped in 2008 after 26 of the planned 49 stories were completed. Lorence Slutzky, a construction law professor at John Marshall Law School and a partner with the Chicago firm Robbins Schwartz Nicholas Lifton & Taylor told Benton that while inspectors and others are complicit, “the real responsibility rests with Perini, which has an obligation to comply with the plan specifications.” Perini’s claim is that they were given faulty design drawings. MGM disputes this.
Perini has offered to repair the building defects, however MGM has released a statement that they have “zero confidence or trust that Perini can and will properly fix a building it has so badly constructed thus far.” One MGM spokesperson likened these requests from Perini to “the director of ‘Ishar’ demanding a sequel.” “Ishtar,’ cost Columbia Pictures $55 million dollars and earned only $4.2 million in its initial run. Perini claims that MGM halted work because of the economy.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
False Implied Certifications in Making Payment Requests: What We Can Learn from Lance Armstrong
January 20, 2020 —
Brian S. Wood & Alex Gorelik - ConsensusDocsIn April 2018, the Department of Justice announced a $5M settlement reached in its lawsuit against former professional cyclist, Lance Armstrong. While the fallout from Armstrong’s latently-admitted use of performance-enhancing drugs (“PEDs”) was well-publicized, including lost sponsorship deals, stripped Tour de France titles, and damage to his reputation, few were aware of Armstrong’s exposure to liability and criminal culpability for false claims against the government. The DOJ’s announcement reminded Armstrong and the rest of us of the golden rule of dealing with the government: honesty is the best policy. The corollary to that rule is that dishonesty is costly.
Armstrong’s liability stemmed from false statements (denying the use of PEDs) he made, directly and through team members and other representatives, to U.S. Postal Service (“USPS”) representatives and to the public. USPS was the primary sponsor of the grand tour cycling team led by Armstrong. The government alleged in the lawsuit that Armstrong’s false statements were made to induce USPS to renew and increase its sponsorship fees, in violation of the False Claims Act.
The Statute
Enacted in 1863, the False Claims Act (“FCA”) was originally aimed at stopping and deterring frauds perpetrated by contractors against the government during the Civil War. Congress amended the FCA in the years since its enactment, but its primary focus and target have remained those who present or directly induce the submission of false or fraudulent claims. The current FCA imposes penalties on anyone who knowingly presents “a false or fraudulent claim for payment or approval” to the federal Government. A “claim” now includes direct requests to the Government for payment, as well as reimbursement requests made to the recipients of federal funds under federal benefits programs (such as Medicare). Thirty-one states, the District of Columbia, and Puerto Rico have also enacted laws imposing penalties for false claims against state agencies and their subdivisions, with most of these laws modelled after the federal FCA.
Reprinted courtesy of
Brian S. Wood, Smith, Currie & Hancock, LLP and
Alex Gorelik, Smith, Currie & Hancock, LLP
Mr. Wood may be contacted at bswood@smithcurrie.com
Mr. Gorelik may be contacted at agorelik@smithcurrie.com
Read the court decisionRead the full story...Reprinted courtesy of
Give Way or Yield? The Jurisdiction of Your Contract Does Matter! (Law note)
March 05, 2015 —
Melissa Dewey Brumback – Construction Law in North CarolinaHave you ever been to England? If so, you’ve likely seen their version of our “Yield” sign– the “Give Way” sign. It is a bit jarring to those from this side of the “big pond”.
Similarly, contracts can be worded differently– and, interpreted differently– depending on the state that you are in. This is why it is always a good idea to have your contract or proposal vetted for the state(s) where you provide professional services.
When confronted with a “give way” sign you have the general idea of yielding, but might be confused by that whole “left side of the road” thing in some countries, where if you are turning right, you must give way to all vehicles coming towards you including those turning left. Likewise, you might have a good understanding of your construction contract in one state, but not how it would be interpreted in another state.
Read the court decisionRead the full story...Reprinted courtesy of