Colorado Passes Construction Defect Reform Bill
June 05, 2017 —
David Suggs – Bert L. Howe & Associates, Inc.According to Daniel E. Evans of Gordon & Rees Scully Mansukhani, Colorado’s state legislature recently passed a bill “designed to reduce litigation risk associated with building condos by requiring a majority of actual condo unit owners, as opposed to a majority of the HOA board members, to approve the filing of a lawsuit over construction defects.” Evans stated that this “legislation cannot be viewed as sweeping reform” and that “future legislative sessions will undoubtedly see additional efforts to reform construction defect litigation.”
Perhaps the most significant aspect of HB 1279 is the requirement for a majority of condo owners in a development to approve a lawsuit, Evans reported. Furthermore, HB 1279 “requires the HOA board to notify all condo unit owners and builders about plans to pursue a construction lawsuit. It further requires the HOA board to hold a meeting to allow the board and the developer to present facts and arguments to the individual condo unit owners, including arguments of the potential benefits and detriments of filing a lawsuit.”
Unlike its failed predecessors, HB 1279 does not require arbitration.
Read the court decisionRead the full story...Reprinted courtesy of
Town Sues over Defective Work on Sewer Lines
January 13, 2014 —
CDJ STAFFThe Handy Sanitary District in North Carolina has filed a lawsuit against one of the subcontractors on the Badin Lake Sewer Project, which the Lexington Dispatch describes as “delay riddled.” The town claims that the materials used by Hobbs, Upchurch and Associates “were not adequate for the project.” Additionally, the town claims that valves were improperly installed or damaged, and that pipes were of the incorrect type and improperly connected.
The Sanitary District Board of Commissioners has additionally settled a lawsuit over non-payment for work on the sewer project. The Handy Sanitary District has settled claims brought by Monroe Roadways Contractors and Young Construction with a payment of $250,000.
Read the court decisionRead the full story...Reprinted courtesy of
Life After McMillin: Do Negligence and Strict Liability Causes of Action for Construction Defects Still Exist?
January 24, 2018 —
Thomas Balestreri and Amanda Crawley - Balestreri, Potocki, & HolmesThe ruling is in but the battle will likely continue over the practical application of SB 800. On January 18, 2018 the California Supreme Court issued its decision in
McMillin Albany, LLC v. Superior Court (Van Tassel) (January 18, 2018, S229762) __ Cal.4th __, holding that the statutory prelitigation scheme in The Right to Repair Act (“the Act”) that provides for notice and an opportunity for the Builder to repair defects applies to all claims for construction defects in residential construction sold on or after January 1, 2003, regardless whether the claim is founded on a violation of the Act’s performance standards or a common law claim for negligence or strict liability. (
McMillin Albany, LLC v. Superior Court (Van Tassel) (January 18, 2018, S229762) __ Cal.4th __.) With this holding, has the Court ruled that common law causes of action for construction defect still survive? If so, what will they look like and what standards will be applied?
The short answer is that it appears that common law causes of action still survive, at least for now, but it is not clear from this decision what they will look like and what standards will apply.
Portions of the decision seem to suggest that the Act is the sole and exclusive remedy for construction defect claims: “…even in some areas where the common law had supplied a remedy for construction defects resulting in property damage but not personal injury, the text and legislative history [of the statute] reflect a
clear and unequivocal intent to supplant common law negligence and strict product liability actions under the Act.” (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 6].) (Italics added for emphasis) However, at the end of the decision, the Court seems to be saying that there may still be a place for common law claims for negligence and strict liability alongside the Act but that these causes of action may be subject to the performance standards in the Act.
The
McMillin case went up to the Supreme Court on a procedural issue: whether a common law action alleging construction defects resulting in both economic loss and property damage is subject to the Act’s prelitigation notice and cure procedures. The Van Tassels had dismissed their claims under the Act opting to proceed solely on their common law claims including negligence and strict liability. McMillin sought a stay to force the Van Tassels to comply with the Act’s prelitigation procedures. The Supreme Court held that the Van Tassels must comply with the statutory procedures and affirmed the stay issued by the trial court. But the question remained: now that the Van Tassels were left only with common law claims, how would they proceed under the Act?
To understand how the Court dealt with this question, one must first understand how the Court dealt with the narrow procedural question presented by the case. The Court provides a very detailed, clear explanation of the reasons why it felt the Legislature intended for all construction defect claims involving residential construction must comply with the prelitigation requirements of the Act. In summing up its conclusions the Court makes three definitive holdings.
First, for claims involving economic loss only—the kind of claims involved in
Aas—the Court holds that the Legislature intended to supersede
Aas and provide a statutory basis for recovery. (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 10].) In other words, the Court clearly agrees that the Act was meant to allow recovery of damages based solely on economic damages. No surprise there. Second, the Court held for personal injuries, the Legislature made no changes to existing law that provides common law remedies for the injured party. (Id.) Nobody has ever contested that. Finally, the Court held that for construction defect claims involving property damage and not just economic loss “the Legislature replaced the common law
methods of recovery with the new statutory scheme.” (
Id.,) (Italics added for emphasis.)
In other words, the Court is not saying that negligence and strict liability are not permitted causes of action. The Court is merely stating that these causes of action must comply with the Act’s statutory scheme just as the same as a claim for economic loss. Here the Court is focusing on the procedure that must be followed. “The Act, in effect, provides that construction defect claims not involving personal injury will be treated the same procedurally going forward whether or not the underlying claims gave rise to any property damage.” (
Id.)
Having laid out its fundamental premise, the Court then deals with Plaintiff’s arguments regarding the intent of the Legislature and makes light work of them all. In the process, the Court disapproves
Liberty Mutual Ins. Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal. App. 4th 98, and
Burch v. Superior Court (2014) 223 Cal. App. 4th 1411, to the extent they are inconsistent with the views expressed in the
McMillin opinion.
This is where the decision gets interesting. The Court reminds us that the Van Tassels had dismissed their statutory causes of action for violation of the performance standards under Section 896. One would think at that point that Plaintiffs had to be wondering if they had any claims left given that the Court had ruled that the Act was the sole means of recovery for construction defects. Not so fast. The Court points out that the complaint still rests on allegations of defective construction and that the suit remains an “ ‘action seeking recovery of damages arising out of, or related to deficiencies in, the residential construction’ of the plaintiffs’ homes (§896)
and McMillin’s liability under the Van Tassels’ negligence and strict liability claims depends on the extent to which it [McMillin] violated the standards of sections 896 and 897.” (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 19].) (Emphasis added.) WHAT DID THE COURT JUST SAY? Did the Court just say that a plaintiff could bring a common law cause of action for negligence or strict liability based on a violation of the performance standards under Section 896? What exactly would that claim look like? What would be the elements of such a cause of action?
To answer these questions, the Court states in the very next paragraph, which also happens to be the last paragraph in the decision: “In holding that claims seeking recovery for construction defect damages are subject to the Act’s prelitigation procedures regardless of how they are pleaded,
we have no occasion to address the extent to which a party might rely upon common law principles in pursuing liability under the Act.” (
McMillin (January 18, 2018, S229762) __Cal.4th.__ [p. 19].) (Italics added for emphasis) Is the Court answering “No” to the questions posed above? Probably not. It is simply following the age old rule that an appellate court will
not rule on an issue that is not specifically presented by an appeal, leaving that question for another day.
All we know for sure from
McMillin is that every claim for construction defects falling within the scope of the Act must follow the prelitigation procedure. There are no hall passes for negligence and strict liability. The larger question posed by the last two paragraphs in the decision, is whether the law recognizes a cause of action for negligence and strict liability for construction defects based on the standards in Section 896. The answer will have to be worked out by judges and trial attorneys in courtrooms across the State! The parameters of this hybrid cause of action that the Court seems to have posited will need more careful consideration than can be offered on first reading of
McMillin v. Superior Court.
Read the court decisionRead the full story...Reprinted courtesy of
Balestreri, Potocki, & Holmes
Insurer's In-House Counsel's Involvement in Coverage Decision Opens Door to Discovery
January 11, 2021 —
Tred R. Eyerly - Insurance Law HawaiiThe Mississippi Supreme Court held that the insurer must produce written communications from and make available for deposition the in-house counsel who orchestrated the denial of coverage. Travelers Pro. Cas. Co. of Am. v. 100 Renaissance, LLC, 2020 Miss. LEXIS 409 (Miss. Oct. 29, 2020).
An unidentified driver struck a flagpole owned by the insured Renaissance, causing $2,134 in damages. Renaissance filed a claim with Travelers for uninsured-motorist coverage. The Travelers' claims handler, Charlene Duncan, determined there was no coverage because the flagpole was not a covered auto. Before corresponding with the insured, Duncan sought legal advice from Travelers' in-house counsel, Jim Harris.
Renaissance sued Travelers for coverage and bad faith. Renaissance then took Duncan's deposition and asked that she explain both the denial letter and the reasons Travelers denied the claim. Duncan repeatedly said she did not know the basis of the denial and that she had consulted with Harris.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Insurer Could Not Rely on Extrinsic Evidence to Circumvent Its Duty to Defend
February 14, 2023 —
Lorelie S. Masters & Yaniel Abreu - Hunton Insurance Recovery BlogIn
First Mercury Insurance Co. v. First Florida Building Corp., et al., a federal district court ordered that an insurer had a duty to defend its insured against an underlying personal injury lawsuit. 2023 WL 23116, at *1 (M.D. Fla. Jan. 3, 2023). First Mercury is a cautionary tale about how insurers may try to circumvent their obligations by improperly considering extrinsic evidence when determining whether they have a duty to defend their insureds.
First Mercury is a coverage dispute over an underlying personal injury lawsuit that was filed against the insured, a construction company, for injuries the claimant allegedly sustained at a construction site. Id. The claimant alleged that he was at the construction site as an invitee who was “working with” the insured. Id. The insurer agreed to defend the insured against the personal injury lawsuit under a reservation of rights. Id. However, the insurer filed a coverage action seeking a declaration that coverage for the personal injury lawsuit was excluded under the policy. Id. Specifically, the insurer, on summary judgment, argued that the claimant was an employee of the insured who was injured in the course of his employment, thus falling within the employer’s liability and workers’ compensation exclusions in the policy. Id. Although the insurer acknowledged that the personal injury complaint against the insured triggered its duty to defend under the policy, the insurer argued that those exclusions relieved its duty to defend or indemnify the insured. Id.
Reprinted courtesy of
Lorelie S. Masters, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Ms. Masters may be contacted at lmasters@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
The Heat Is On
June 13, 2022 —
Christopher Durso - Construction ExecutiveEvery year, NASA and the National Oceanic and Atmospheric Administration (NOAA) team up to assess global temperatures and climate trends. (Yes, that NASA. A big part of the space agency’s mission is focused on Earth science, with the goal of better understanding the planet’s interconnected systems.) The two groups released their findings for 2021 this past January, with several predictably alarming highlights:
- 2021 was the sixth-warmest year on record, with the average global surface temperature about 1.5°F over the 20th-century baseline periods that the agencies use for comparison and nearly 2°F higher than in the late-19th century.
- The surface temperature in the Northern Hemisphere was also the sixth-highest on record, at nearly 2°F over baseline, with the land temperature exceeding the baseline by 2.8°F.
- Extreme climate events included an above-average Atlantic hurricane season, with 21 storms, and a severe heat wave in the northwestern United States and western Canada in June during which Canada recorded its highest temperature ever, at 121°F.
Reprinted courtesy of
Christopher Durso, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Near-Zero Carbon Cement Powers Sustainable 3D-Printed Homes
August 07, 2023 —
Aarni Heiskanen - AEC BusinessEco Material Technologies and Hive 3D have unveiled the first 3D-printed homes using near-zero carbon cement as part of a housing project called The Casitas @ The Halles.
The homes, ranging from 400 to 900 square feet, are constructed using Eco Material’s durable, longer-lasting cement called PozzoCEM Vite®. The cement replaces 100% of traditional Portland cement, has 92% lower emissions, and sets much faster.
Hive 3D has developed a system to mix Eco Material’s cement replacement products with locally-sourced aggregates on-site, enabling cost-efficient and affordable construction. The collaboration aims to offer sustainable housing solutions and transition the construction industry away from high-carbon materials.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Construction Defects in Home a Breach of Contract
September 09, 2011 —
CDJ STAFFThe Supreme Court of North Dakota has ruled in Leno v. K & L Homes, affirming the verdict of the lower court. K & L Homes argued that district court had erred in several ways, including by refusing to instruct the jury on comparative fault, denying a request for inspection, and not allowing a defendant to testify on his observations during jury viewing.
The Lenos purchased a home constructed by K & L Homes, after which they alleged they found cracks, unevenness, and shifting, which they attributed to improper construction. They claimed negligence on the part of K & L Homes. K & L Homes responded that the Lenos were responsible for damage to the home. The Lenos dropped their negligence claim, arguing breach of contract and implied warranties.
Before the trial, after the discovery period had passed, K & L Homes requested to inspect the home. This was rejected by the court. Kelly Moldenhauer, the owner of K & L Homes sought to testify about his observations during the jury’s viewing of the house. The court denied this too. The jury found that K & L was in breach of contract and awarded damages to the Lenos.
The North Dakota Supreme Court noted that K & L Homes gave “warranties that the home had been built according to local building codes and laws, and that the house was fit for its particular purpose as a residence.” The court found that a defective home breached this warranty. Further, the home violated an implied warranty of fitness.
The district court had denied K & L’s request to inspect the home, as the discovery period had ended and it would not give the Lenos time to do further discovery of their own. At the time of the request, there was only twenty-two days before the trial. The Supreme Court ruled that this was not an abuse of discretion of the part of the district court.
The Lenos had requested that Moldenhauer’s testimony not be permitted, as it would “have the same effect as if the court had granted K & L Homes’ pretrial request for inspection.” K & L Homes agreed to this in court, replying, “okay.”
The decision affirms the judgment of the district court and the damages awarded to the Lenos by the jury.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of