New Jersey Court Adopts Continuous Trigger for Construction Defect Claims
November 15, 2017 —
Tred R. Eyerly - Insurance Law HawaiiThe New Jersey Superior Court, Appellate Division, adopted the continuous trigger for establishing which insurers were on the risk for construction defect claims. Air Master & Cooling, Inc. v. Selective Ins. Co. of Am., 2017 N.J. Super. LEXIS 144 (N.J. Super. Ct., App. Div. Oct. 10, 2017).
The insured, Air Master, worked as a subcontractor on the construction of a condominium building. Air Master performed HVAC work in the building between November 2005 and April 2008. Air Master's work consisted of installing condenser units on rails on the building's roof, and also HVAC devices within each individual unit.
Starting in early 2008, some of the unit owners began to notice water infiltration and damage in their windows, ceilings, and other portions of their units. On April 29, 2010, an expert consultant, Jersey Infrared Consultants, performed a moisture survey of the roof for water damage. A report identified 111 spots on the roof damaged by moisture from water infiltration. The report noted it was impossible to determine when moisture infiltration occurred. The expert recommended that these damaged areas of the roof be removed and replaced.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Hurdles with Triggering a Subcontractor Performance Bond
April 05, 2017 —
David Adelstein – Florida Construction Legal UpdatesThere have been a couple of decisions as of late, particularly in federal court, that have gone in favor of a performance bond surety and against a general contractor’s claim against a subcontractor’s performance bond. These decisions have been so unfavorable that they may be swaying certain internal decisions to move to subcontractor default insurance with, perhaps, subcontractors that pose less risk. From the general contractor’s perspective, if they have to stop the management of the job and progress to jump through hoops to trigger the performance bond’s obligations, rightfully or wrongfully, the bond may not provide them the value they need. Performance bonds are an appropriate product in many instances, but there should be more consistency regarding the actual trigger of a subcontractor’s performance bond obligations. Project teams need to absolutely understand what efforts they need to take, and how they need to take such efforts, in order to properly trigger a performance bond’s obligations. This is a must (and I have presented many seminars on this very issue). Or, the general contractor should move away from the traditional AIA /standard performance bond form, which is the direction I always go when I am involved in the drafting of a performance bond.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Presidential Memorandum Promotes Reliable Supply and Delivery of Water in the West
November 14, 2018 —
Anthony B. Cavender - Gravel2GavelIn a Memorandum dated October 19, 2018 and entitled Promoting the Reliable Supply and Delivery of Water in the West, the President has directed the Secretaries of the Interior and Commerce to work together to minimize “unnecessary regulatory burdens and foster more efficient decision-making” so that major federal water projects are constructed and operated in a manner that delivers water and power in an “efficient, cost-effective way.” More specifically, they will take steps to streamline the western water infrastructure regulatory processes and remove unnecessary burdens in accordance with the timetables set forth in the Memorandum.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Long-Planned Miami Mega Mixed-Use Development Nears Initial Debut
September 25, 2018 —
Jim Parsons - Engineering News-RecordEconomic crises, lawsuits and other complications have thrown multiple wrenches into plans for downtown Miami’s massive Worldcenter mixed-use project over the past 12 years. But to hear the master development group’s managing principal Nitin Motwani tell it, the timing for the $2-billion “city within a city” to finally come to fruition couldn’t be better.
Read the court decisionRead the full story...Reprinted courtesy of
Jim Parsons, ENRENR may be contacted at
ENR.com@bnpmedia.com
Seattle Independent Contractor Ordinance – Pitfalls for Unwary Construction Professionals
October 09, 2023 —
Travis Colburn - Ahlers Cressman & SleightChapter 14.34 of the Seattle Municipal Code is a relatively new ordinance that can affect the parties to a construction contract for work performed within the City of Seattle’s city limits. The Independent Contractor Protection Ordinance (“ICPO”) was enacted to provide self-employed persons, or entities composed of not more than one person, regardless of corporate form, recourse for timely payment for work performed. The ICPO applies to contracts of $600[i] or more between an independent contractor and a hiring entity where the work, in whole or in part, is known to be performed within the City of Seattle’s city limits.[ii] The ICPO cannot be waived by parties to a contract.[iii]
Historically, the primary legal recourse for non-payment or late payment for work performed under a contract involves an expensive breach of contract action, and one reason the ICPO was enacted was to give greater protection to a growing number of Washington independent contractors who report problems with timely and accurate payment.
The ICPO affects “hiring entities” or any individual, partnership, association, corporation, business trust, or any entity, person or group of persons, or a successor thereof, that hires independent contractors to provide services within the scope of a hiring entity’s business or commercial activities. In the construction context, most general contractors, subcontractors, design professionals, and design consultants should be aware of this ordinance, as well as certain owners[iv] and development-side entities.
Read the court decisionRead the full story...Reprinted courtesy of
Travis Colburn, Ahlers Cressman & SleightMr. Colburn may be contacted at
travis.colburn@acslawyers.com
BHA at the 10th Annual Construction Law Institute, Orlando
January 13, 2017 —
Don MacGregor - Bert L. Howe & Associates, Inc.Bert L. Howe & Associates, Inc. is once again proud to be partnering with the Florida Bar Continuing Legal Education Committee and the Construction Law Committee of the Florida Bar Real Property, Probate and Trust Law Section, as a sponsor and exhibitor at the 10th Annual Construction Law Institute to be held March 16th, 17th & 18th, 2017 at the JW Marriott Orlando Grande Lakes in Orlando.
With offices in Miami serving all of Florida, Bert L. Howe & Associates, Inc. (BHA) offers the experience of over 20 years of service to carriers, defense counsel, and insurance professionals as designated experts in nearly 6,500 cases. BHA’s staff encompasses a broad range of licensed and credentialed experts in the areas of general contracting and specialty trades, as well as architects, and both civil and structural engineers, and has provided services on behalf of developers, general contractors and sub-contractors.
BHA’s experience covers the full range of construction and construction defect litigation, including single and multi-family residential (including high-rise), institutional (schools, hospitals and government buildings), commercial, and industrial claims. BHA specializes in coverage, exposure, premises liability, and delay claim analysis as well.
As the litigation climate in Florida continues to change, and as the number of construction defect and other construction related cases continues to rise, it is becoming more important for contractors and builders here to be aggressive in preparing for claims before they are made, and in defending against those claims once they are filed. Since 1993, Bert L. Howe & Associates has been an industry leader in providing construction consulting services, and has been a trusted partner with builders and insurance carriers, both large and small, across the Western and Southern United States. Here in Florida, we have been providing construction defect and construction-claims related forensic expert services for the past decade with a proven track record of successful results.
For those of you planning on attending the conference, or those who may know someone who will be, we encourage you to stop by the BHA booth and we welcome the opportunity to discuss further the broad range of services provided by BHA.
For your convenience, when registration information is made available, a link to the 10th Annual Construction Law Institute should be available here: http://www.rpptl.org/
Read the court decisionRead the full story...Reprinted courtesy of
Don MacGregor, Bert L. Howe & Associates, Inc.Mr. MacGregor may be contacted at
dmac@berthowe.com
Traub Lieberman Partner Stephen Straus Wins Spoliation Motion in Favor of Defendant
June 05, 2023 —
Stephen D. Straus - Traub LiebermanTraub Lieberman Partner Steve Straus represented a refrigeration installation and service company in a subrogation action filed by a property insurer after paying a claim related to extensive water damage at premises on Long Island, New York.
The premises owner purchased a refrigerator, which was sold without a hose to connect to the water source inside the premises. The defendant retailer retained Traub Lieberman’s client to install the refrigerator. Rather than complete the installation using a new water line, the installer used the existing line from the refrigerator that was being replaced. Approximately one week after installation, the owner’s son discovered water on the floor near the refrigerator, and significant water damage in the basement of the residence. The owner filed a claim with the insurer, which sent an investigator to the premises. The retailer also sent a technician to investigate and replace the water supply line. It was reportedly determined that the original line had failed, causing the water release. After the repair, the owner’s son took possession of the old water line, which he kept for a couple of years and then discarded. The insurer initiated a subrogation action against the retailer and the installation company, alleging that the water release was caused by the defendants’ failure to replace the water line when the new unit was installed. Plaintiff claimed that photographs of the old line established that it had been damaged or defective.
Read the court decisionRead the full story...Reprinted courtesy of
Stephen D. Straus, Traub LiebermanMr. Straus may be contacted at
sstraus@tlsslaw.com
Spotting Problem Projects
October 26, 2017 —
David R. Cook Jr. - Autry, Hanrahan, Hall & Cook, LLPPerhaps more than any other specialty contractor, electrical contractors bear the brunt of the “problem project.” Long after most other trades have completed their work and scattered in the wind, electrical contractors remain on site until the owner’s last inspection. And when the project is a “problem project,” the owner or prime contractor tend to liberally share their losses and liquidated damages among those specialty contractors remaining on site at the end. So what is an electrical contractor to do when the project starts coming off the rails?
What is a Problem Project?
First, it helps to identify the attributes of a problem project. While there are many negative qualities of a bad job, a problem project is one that busts budgets – whether labor, material, or time. Most commonly, the problem project will significantly exceed the labor budget. Because an electrical contractor’s most important (and understandably expensive) resource is its people, the labor budget is critical to the success of a job. When a project suffers delays or is ineptly managed, the labor costs soar, turning a potentially profitable job into a disaster.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com