Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion for summary judgment, deciding that there was no breach of the policy for failure to pay for flood damage when the insured failed to obtain a policy under the National Flood Insurance Program (NFIP). 570 Smith St. Realty Corp. v. Seneca Ins. Co. Inc., 2019 N.Y. Misc. LEXIS 1773 (N.Y. Sup. Ct. April 4, 2019).
The insured's property in Brooklyn was insured by Seneca. Included in the policy was flood coverage in the amount of $1 million with a $25,000 deductible. While the policy was in effect, Hurricane Sandy hit, damaging the property. Plaintiffs timely filed a claim seeking reimbursement of up to policy limits. Seneca paid only $35,883 and later made an additional payment of $33,015.
The insured sued for, among other things, breach of the policy for failure to properly indemnify for the losses. Seneca moved for partial summary judgment dismissing the breach of policy claims. Seneca pointed out that the "Other Insurance" provision in the Flood Coverage Endorsement of the policy stated that if the loss was eligible to be covered under a NFIP policy, but there was no such policy in effect, the insurer would only pay for the amount of loss in excess of the maximum limit payable for flood damage under the policy. The maximum NFIP coverage was $500,000. The insured's loss caused by flood was less than $500,000.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
DC Circuit Issues Two Important Clean Air Act and Administrative Law Decisions
December 16, 2019 —
Anthony B. Cavender - Gravel2GavelThe U.S. Court of Appeals or the District of Columbia has recently issued two important rulings on the Clean Air Act in particular and administrative law in general: California Communities Against Toxics, et al., v. EPA and Murray Energy Corporation v. EPA.
The Battle of the Memos: Seitz Makes Way for Wehrum
In the California Communities case, decided on August 20, 2019, the court held, in a 2 to 1 decision, that a petition to review a change in EPA policy announced in an agency memorandum which reversed an agency policy announced nearly 25 years ago in another agency memo must be rejected because the memo at issue was not a “final agency action” subject to the Administrative Procedure Act (APA). In 1995, the “Seitz Memo,” which interpreted Section 112 of the Clean Air Act and addresses the regulation and control of hazardous air pollutants from stationary sources, stated that once a source of toxic emissions is classified as “major,” the facility remains subject to regulation as a major source even if the facility makes changes to the facility to limit its potential to emit such toxics below the major source threshold. Then, in 2018 under a new administration, the “Wehrum Memorandum” was issued which reversed this policy and its interpretation of the law. (Both memos were issued without any kind of advance notice or opportunity to comment.) If a source takes steps to limit its potential to emit, then it may be regulated as an area source, and subject to less rigid regulation. The court majority held that the Wehrum Memo was not a final agency action and was not subject to judicial review when it was measured against both prongs of the “finality test” devised by the Supreme Court in the cases of Bennet v. Spear, 520 US 154 (1997) and US Army Corps of Engineers v. Hawkes, 136 S. Ct. 1807 (2016). While the memo undoubtedly represented the consummation of the agency’s decision-making process, the memo had no direct and appreciable legal consequences, and not therefore being a final action, the case must be dismissed. Judge Rogers filed a strong dissenting opinion.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Texas Federal District Court Dismisses COVID-19 Claim
October 25, 2020 —
Tred R. Eyerly - Insurance Law HawaiiJudge Ezra, formerly on the bench in Hawaii, dismissed a COVID-19 claim pursued by a Texas policy holder. Diesel Barbershop, LLC v. State Farm Lloyds, 2020 U.S. Dist. LEXIS 147276 (W.D. Texas Aug. 13, 2020).
Local and state officials in Texas issued shutdown orders in March 2020 due to the spread of the cornavirus. All non-essential businesses, including the insureds' barbershop businesses, were ordered closed from April 2, 2020 until April 30, 2020. The insureds submitted a claim for business interruption and civil authority coverage to their carrier, State Farm. The claim was denied based on the policy's exclusion for loss caused by enforcement of ordinance or law, virus, and consequential losses. For Civil Authority coverage, State Farm contended the policy required that there by physical damage within one mile of the described property and that the damage be the result of a Covered Cause of Loss, which, State Farm asserted, a virus was not.
The insureds sued and State Farm moved to dismiss. The court noted cases in which courts had found physical loss even without tangible destruction to the covered property. Yet, the court found that the line of cases requiring tangible injury to property were more persuasive. Therefore, the court found that the insureds failed to plead a direct physical loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Clean Water Act Cases: Of Irrigation and Navigability
January 06, 2020 —
Anthony B. Cavender - Gravel2GavelThe federal courts have recently decided two significant Clean Water Act (CWA) cases: State of Georgia, et al. v. Wheeler, where the US District Court for the Southern District of Georgia held that the 2015 rulemaking proceeding of EPA and the U.S. Army Corps of Engineers redefining the term “Waters of the United States” in the CWA violated the Act as well as the Administrative Procedure Act; and the Ninth Circuit’s decision in Pacific Coast Federation of Fishermen’s Associations, et al. v. Glaser, where the appeals court ruled that the lower court erroneously interpreted a CWA NPDES permitting exception involving agricultural return flows.
An Absence of Navigability: State of Georgia, et al. v. Wheeler
Decided on August 21, 2019, the district court, one of the few courts to grapple with the rule’s compliance with the CWA and the Administrative Procedure Act (APA), held that the agencies’ redefinition of the terms “Interstate Waters,” “Tributaries” and “Adjacent Waters” violated the CWA by reading “navigability” out of the new definitions, or by failing to adhere to the Supreme Court’s rulings in the 2005 case of Rapanos v. United States, in particular Justice Kennedy’s concurrence regarding the application of the “significant nexus” in case-by-case adjudications as to whether a particular body of water was covered by the Act. Moreover, some provisions of the rule conflicted with the APA because they were not a logical outgrowth of the rules proposed by the agencies in 2014, and on which they solicited comments, and other determinations were not supported by a reasonable explanation. In addition, without a clear statement from Congress that it supported the rule’s effect of increasing the nature and extent of enhanced federal jurisdiction over waters subject to the CWA, the court was loathe to approve the rule. Accordingly, the rule was remanded to the agencies for additional review consistent with this decision.
This decision is of particular importance as it may well be the first case to subject this new EPA rule—the linchpin of much of EPA’s regulation under the CWA—to extended review. (Other courts have only been asked to enjoin the rule, which involves a different type of review.)
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Appellate Court Endorses Discretionary Test for Vicarious Disqualification of Law Firms Due To New Attorney’s Conflict
February 07, 2018 —
David W. Evans and Stephen M. Tye – Publications & Insights In
California Self-Insurer’s Security Fund et al. v. The Superior Court of Orange County (1/26/2018 – No. G054981), the Fourth Appellate District considered whether vicarious disqualification of a law firm is mandatory or discretionary where an attorney with a conflict joins a firm and the firm enacts an ethical screen to prevent transmission of confidential information between the new attorney and the rest of the firm.
This case arose from an effort by the California Self-Insurer’s Security Fund (the “Fund”) to be reimbursed for workers’ compensation benefits advanced on behalf of the Healthcare Industry Self-Insurance Program (the “Program”). The Fund hired Nixon Peabody LLP (“Nixon Peabody”) to represent it in connection with this matter. In November 2013, represented by members of Nixon Peabody’s San Francisco office, the Fund filed a lawsuit naming 304 members of the Program as defendants. Approximately 170 defendants have since settled.
Two of the non-settling defendants (“Moving Parties”), were represented by Michelman & Robinson, LLP (“M&R”). From approximately 2009 until February 1, 2017, attorney Andrew Selesnick served as Chair of M&R’s Health Care Department at the firm’s Los Angeles office, managing a team of attorneys who represented clients in the healthcare industry. Commencing in 2014, a team of four attorneys at M&R, including Selesnick, represented the Moving Parties and four other defendants, the latter of whom have since settled. Selesnick was actively involved, including participating in a confidential discussion pertaining to Moving Parties’ liability and damages and receiving many e-mails containing communications about the common defense of the remaining 170 defendants.
Reprinted courtesy of
David W. Evans, Haight Brown Bonesteel and
Stephen M. Tye, Haight Brown Bonesteel
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Tye may be contacted at stye@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Another Reason to Always Respond (or Hensel Phelps Wins One!)
September 16, 2019 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, Hensel Phelps Construction Co. is best known as the company that got whipsawed between indemnity rules and the lack of a statute of limitations for state agencies. However a recent case out of the Federal District Court for the Eastern District of Virginia gave them a win and illustrates, once again, that failing to appear or respond is never a good option.
In Hensel Phelps Construction Co. v. Perdomo Industrial LLC, the Alexandria, VA federal court looked at an arbitration award entered for Hensel Phelps and against Perdomo under the Federal Arbitration Act. The facts of the case showed that Perdomo “double dipped” into the deep end of refusal or failure to respond. First of all, the contract required arbitration and any award was enforceable in any state or federal court having jurisdiction. Based upon this language, Hensel Phelps filed a demand for arbitration with the American Arbitration Association against Perdomo and its surety, AAA sent notice to both Perdomo and Surety, and. . . neither responded or appeared at what was ultimately 8 days of hearings. After hearing Hensel Phelp’s evidence and the total lack of defenses from Perdomo and Surety, the panel issued an award in favor of Hensel Phelps, finding Perdomo LLC in default and holding Perdomo LLC and Allied World jointly and severally liable in the amount of $2,958,209.71 and Perdomo LLC individually liable in the amount of $7,917,666.30 plus interest.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Legislative Update: Bid Protest Law Changes to Benefit Contractors
November 24, 2019 —
Brett M. Hill - Ahlers Cressman & Sleight PLLCA new statute became effective July 28, 2019 that benefits contractors who have bid protests in Washington. A bid protest is the only way for disappointed bidders to challenge irregularities in the public bidding process on public works projects. Bid protests ensure the integrity of the public bidding system and are the contractor’s only remedy if its bid is improperly rejected or the winning bidder has errors in its bid that render it nonresponsive.
Under the old law, a contractor was required to submit their bid protest within 2 days after the bid opening. The problem was that a contractor often does not know the basis to protest an award without seeing the other bids to determine whether the winning bid was responsive. Many owners provide copies of the bids if requested at the bid opening, but some contractors found that owners were refusing to provide copies of the other bids until after the 2-day protest period expired.
The new law, which passed this last Legislative session[1], states that a contractor has two days after the bid opening to either submit a written protest or request copies of the competing bids. If the contractor requests copies of the competing bids from the owner, the contractor then has until 2 days after the competing bids are provided by the owner before the contractor is required to submit its bid protest.
Read the court decisionRead the full story...Reprinted courtesy of
Brett M. Hill, Ahlers Cressman Sleight PLLCMr. Hill may be contacted at
brett.hill@acslawyers.com
PSA: Latest Updates from AGC-VA on COVID Rules (UPDATED)
June 14, 2021 —
Christopher G. Hill - Construction Law MusingsThe recent changes in masking requirements and COVID-related restrictions have prompted questions and concerns throughout the construction industry. We understand your questions and continue to work closely with the Department of Labor and Industry (DOLI) and the Safety and Health Codes Board.
Here is what we know at this point:
- The Governor’s second order terminates the state of public emergency as of May 28, 2021. At that point, the DOLI Safety and Health Codes Board will have 2 weeks to meet and decide whether to rescind, modify, or continue the Final Permanent Standard for Prevention of Covid-19. Companies should continue to follow the standard until further notice.
- UPDATE: At present, the emergency order does not expire before June 30, unless amended or otherwise changed. Therefore, the two-week period to announce a meeting of the SCHB to review the permanent COVID-19 standard does not begin until July 1, though the meeting can occur after the two-week period. AGCVA has joined other groups in pushing for a meeting as soon as possible.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com