Is Your Contract “Mission Essential?” Recovering Costs for Performing During a Force Majeure Event Under Federal Regulations
May 10, 2022 —
Joneis M. Phan & Sarah K. Bloom - ConsensusDocsFederal contractors have faced unprecedented challenges performing during the COVID-19 pandemic. Additional costs have included delays and inefficiencies, site closures, quarantines, unavailability of supplies and materials, and full shutdowns of subcontractor operations. For contractors performing under fixed price contracts, the cost impact of COVID-19 was likely severe.
The Federal Acquisition Regulation (“FAR”) recognizes “epidemics” as a force majeure event that may excuse non-performance. Many federal contracts include some version of the Default clause, which prevents the government from terminating a contractor for default due to impacts of force majeure events that are beyond a contractor’s control, such as an epidemic. See, e.g., FAR 52.249-10. See also Pernix Serka Joint Venture v. Dep’t of State, CBCA No. 5683 (Apr. 20. 2020). The Default clause, however, operates as a shield from liability, not a sword authorizing recovery. Contractors are now left wondering whether any avenue exists to recover additional costs incurred after performing in the face of the COVID-19 pandemic.
In response to a likely influx of claims and requests for equitable adjustment due to COVID-19 impacts, the federal government largely took the position that contractors were entitled to extensions of time, but not to additional costs. This article explores the avenues that may be available for contractors to recover costs for performing during a force majeure event that would otherwise be non-compensable.
Reprinted courtesy of
Joneis M. Phan, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs and
Sarah K. Bloom, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs).
Mr. Phan may be contacted at jphan@watttieder.com
Ms. Bloom may be contacted at sbloom@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Amazon Hits Pause on $2.5B HQ2 Project in Arlington, Va.
March 27, 2023 —
Jim Parsons - Engineering News-RecordAmazon is tapping the brakes on its $2.5-billion HQ2 second headquarters project in Arlington County, Va., announcing an indefinite delay to the start of the program’s 2.8-million-sq-ft second phase, known as PenPlace.
Reprinted courtesy of
Jim Parsons, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
California Construction Bill Dies in Committee
July 21, 2011 —
CDJ STAFFAB 20, which its sponsor, Linda Halderman (R-Fresno), stated would discourage class action lawsuits against builders and protect jobs in the construction industry, has died in committee. Although the Business Journal reported in June that Haldeman was promoting the bill during a talk in her district and the bill is still on her web site, the California Assembly reports that the bill failed in committee on March 15, 2011. It is possible that the bill could be reconsidered, but the Assembly Committee on Judiciary sees the bill as responding to issues quieted by SB 800 which gives builders the right to repair alleged defects before any suit can be filed.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Georgia Court Clarifies Landlord Liability for Construction Defects
June 02, 2016 —
Chadd Reynolds - AHHC Construction Law BlogIn Cowart v. Schevitz, the Georgia Court of Appeals clarified the instances in which an out-of-possession landlord can be liable in a premises liability claim. No. A15A2036, 2016 WL 563114, at *4 (Ga. Ct. App. Feb. 15, 2016).
In this case, the plaintiff was leaving a restaurant and injured herself stepping down off of a sidewalk near the bottom of a ramp. The plaintiff filed a premises liability claim against the owner of commercial property (the “landlord”) and the operator of the restaurant (who later settled), seeking medical expenses and costs of litigation. An expert testifying on behalf of the plaintiff stated that the ramp was required to have railings pursuant to building codes and, had the railings been installed on the ramp, the plaintiff’s fall more than likely would not have occurred. The landlord moved for summary judgment, arguing that as an out-of-possession landlord, his liability to third persons for the use of the property by his tenant was precluded under O.C.G.A. § 44-7-14. The trial court denied the motion without comment, and the owner subsequently appealed.
Read the court decisionRead the full story...Reprinted courtesy of
Chadd Reynolds, Autry, Hanrahan, Hall & Cook, LLPMr. Reynolds may be contacted at
reynolds@ahclaw.com
Mediation Confidentiality Bars Malpractice Claim but for How Long?
April 01, 2015 —
Jennifer K. Saunders – Haight Brown & Bonesteel LLPThe California Court of Appeal yesterday upheld application of the mediation confidentiality statutes to bar a malpractice action which was based on the attorneys’ actions during mediation. John Amis vs. Greenberg Traurig LLP, et al. (3/18/15) Court of Appeal, Second Appellate District, No. B248447. Inferences about the attorneys’ conduct during mediation were also determined to be unusable in an attempt to circumvent the privilege.
Plaintiff, John Amis, filed an action against his former attorneys, Greenberg Traurig, alleging they were negligent by “causing” him to execute a settlement agreement during a two-day mediation which converted a corporate obligation into a personal obligation. The causes of action included breach of fiduciary duty, malpractice and breach of a conflict waiver, in support of which Amis alleged that the attorneys failed to advise him of the risk involved in entering into the settlement agreement, “drafted, structured and caused it to be executed” during mediation and breached a conflict waiver by failing to negotiate a settlement that provided him with financial security. During plaintiff’s deposition he admitted that all of the advice he had received in connection with the settlement agreement occurred during mediation and that all the damages incurred were from his execution of that agreement during mediation. Greenberg Traurig filed a motion for summary judgment based upon plaintiff’s deposition admissions and argued that since the mediation confidentiality statutes barred each side from presenting testimony as to what occurred during mediation, the plaintiff could not establish the elements of his claims and they could not defend against those allegations. The trial court agreed with the defense, granting summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer K. Saunders, Haight Brown & Bonesteel LLPMs. Saunders may be contacted at
jsaunders@hbblaw.com
Limitations: There is a Point of No Return
September 06, 2023 —
Amy Anderson - ConsensusDocsAfter nearly any event that causes inefficiency, delay, or extra cost on a project, there are some things you should always do: review the contract and document the inefficiency, delay, or cost. However, how you document the particular issue likely changes depending on what is in your contract, your position on the project, and the outcome you hope to reach. In reviewing the inefficiency, delay, or cost, one thing to always consider is how long you have to actually recoup damages you may incur if they were caused by another party on the project. In every jurisdiction (state or federal), there is likely to be some outer limit to when you can bring litigation or arbitration against an opposing party to recover damages another party causes to you. This is generally called a statute of limitations or statute of repose, although it goes by other names depending on your state.
The length of time will be specific to the locality. For example, in Texas, you have four years to bring a breach of contract claim but only two years to bring a negligence claim. Whether you fall under the two year or four year period may be highly fact intensive, depending on your claims. Do you have a contract directly with the party that is at fault? Is the claim based on your contract or some tort outside of the contract?
Read the court decisionRead the full story...Reprinted courtesy of
Amy Anderson, Jones Walker LLP (ConsensusDocs)Ms. Anderson may be contacted at
aanderson@joneswalker.com
Congratulations to BWB&O’s 2021 Super Lawyers Rising Stars!
July 05, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara, LLP is excited to announce Partners Kyle Carroll, Nicole Nuzzo, and Michael D’Andrea, as well as Associates Andy Arakelian and Andrew Steinberg, have been selected to the 2021 Super Lawyers Southern California Rising Stars for their work in Civil and Family litigation!
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The patented selection process includes independent research, peer nominations, and peer evaluations.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Attorney’s Fees Entitlement And Application Under Subcontract Default Provision
May 06, 2019 —
David Adelstein - Florida Construction Legal UpdatesMany subcontracts contain a provision in the default section that reads something to the effect:
“Upon any default, Subcontractor shall pay to Contractor its attorney’s fees and court costs incurred in enforcing this Subcontract or seeking any remedies hereunder.”
Oftentimes, a party may wonder as to the enforceability of the provision and how it is applied in the context of a dispute between a contractor and its subcontractor where both parties have asserted claims against the other.
In an opinion out of the Middle District of Georgia, U.S. f/u/b/o Cleveland Construction, Inc. v. Stellar Group, Inc., 2019 WL 338887 (M.D.Ga. 2019), a subcontractor and prime contractor on a federal construction project each asserted claims against the other in the approximate amount of $4 Million, meaning there was a potential $8 Million swing in the dispute.
The subcontract contained a provision entitling the contractor to recover attorney’s fees incurred in enforcing the subcontract or seeking remedies under the subcontract upon any default, identical to the provision above.
Read the court decisionRead the full story...Reprinted courtesy of