Performance Bond Surety Takeover – Using Terminated Contractor To Complete The Work
January 06, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen a contractor is defaulted under a performance bond, can its surety hire the same defaulted contractor to complete the work? Stated differently, can the performance bond surety engage its defaulted bond-principal in taking over and completing the same work the contractor was defaulted under? The answer is “yes” if you are dealing with a standard form AIA A312 performance bond (and other bond forms that contain analogous language), as demonstrated by the recent decision in Seawatch at Marathon Condominium Association, Inc. v. The Guarantee Company of North America, 2019 WL 4850194 (Fla. 3d DCA 2019).
In this case, a condominium association hired a contractor in a multi-million dollar contract to renovate condominium buildings. The contractor provided the association, as the obligee, a performance bond written on an AIA A312 performance bond form. During construction, the association declared the contractor in default and terminated the contractor. In doing so, the association demanded that the performance bond surety make an election under paragraph 4 of the AIA A312 bond form that gave the surety the following options:
4.1 Arrange for the CONTRACTOR, with consent of the OWNER, to perform and complete the Contract; or
4.2 Undertake to perform and complete the Contract itself, through its agents or through independent contractors; or
4.3 Obtain bids or negotiated proposals from qualified contractors acceptable to the OWNER for a contract for performance and completion of the Contract, arrange for a contract to be prepared for execution by the OWNER and the contractor selected with the OWNER’S concurrence, to be secured with performance and payment bonds executed by a qualified surety equivalent to the Bonds Issued on the Contract, and pay to the OWNER the amount of damages as described in paragraph 6 in excess of the Balance of the Contract Price incurred by the OWNER resulting from the CONTRACTOR Default; or
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Hard to Believe It, Construction Law Musings is 16
January 07, 2025 —
Christopher G. Hill - Construction Law MusingsOn this date back in 2008 (wow, that seems so long ago), I began Construction Law Musings on the Blogger platform with a brief announcement. Little did I know that this corner of the internet (or is it Blawgosphere?) would still be around in 2024!
In the time since I made that short entry 16 years ago (I know, I can’t believe it either), I’ve met several construction lawyers here in Virginia who refer to me as the “blog guy.” To be recognized for the work I do here at Construction Law Musings, something that benefits me (and I hope the readers), and which I do for the fun of it, is an honor.
The blog has since taken on a life of its own in many respects, allowing me to meet some of the great construction pros who have provided a guest post or two for Musings and added their different perspectives. Musings also kept me up on at least most of the trends in Virginia construction law by making me post consistently (though sometimes less consistently than others). Now, around 975 posts and 16 years later, I find it hard to believe that so much time has passed and effort has been put into what started on a whim and the plan that I’d post thoughts on the legal landscape and construction from the perspective of a Virginia construction lawyer.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Litigation Roundup: “The New Empty Chair.”
June 04, 2024 —
Daniel Lund III - LexologyIn a unanimous opinion, the United States Supreme Court ruled that cases in litigation in federal court but which are determined to be governed by the Federal Arbitration Act should be stayed pending arbitration, not dismissed.
Traditionally, some federal circuits treated the text of 9 U.S.C. §3 – which speaks in terms of a stay of a matter filed in court but referred to arbitration (“…shall on application of one of the parties stay the trial of the action until such arbitration has been had in accordance with the terms of the agreement…”) – as discretionary, dismissing suits when all of the claims brought in the court were referred to arbitration.
In the case, the plaintiffs sued in Arizona state court on labor law violations, and the case was removed to federal court. When the defendant moved to compel arbitration and to dismiss, the plaintiffs “conceded that all of their claims were arbitrable.” Nonetheless, the plaintiffs requested a stay of the case, which the district court refused, dismissing the case without prejudice.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Discussion of the Discovery Rule and Tolling Statute of Limitations
February 26, 2015 —
Beverley BevenFlorez-CDJ STAFFAttorney Clay Olson analyzed a recent South Carolina appeals case that “discussed the threshold for ‘notice’ as it pertains to statute(s) of limitations in construction defect cases. At the root of this action was a 2003 forensic report obtained by the HOA which was not acted upon until 2009.”
Olson presented the background of the case as well as the case progression. Olson concluded, “It is well settled that an expert’s findings, when presented to a claimant, trigger the statute of limitations as to the specific defective conditions and locale where defects are present. This case is interesting in its treatment of the initial report as a trigger of all defects in not only the main building which was subject of the 2003 report, but additional structures.”
Read the court decisionRead the full story...Reprinted courtesy of
BIM Legal Liabilities: Not That Different
February 10, 2020 —
Christopher G. Hill - Construction Law MusingsFor this week’s Guest Post Friday here at Musings, we welcome Scott P. Fitzsimmons. Scott is an attorney with the construction law firm Watt, Tieder, Hoffar & Fitzgerald, where he represents contractors, subcontractors, owners, and engineers. He is also a LEED AP and an instructor for AGC of D.C., where he teaches BIM Contract Negotiation and Risk Allocation as part of AGC’s Certificate of Management, Building Information Modeling program.
When a new technology is introduced to the construction industry, contractors inevitably ask themselves one question “Great, how can this new gadget get me into trouble?” Building Information Modeling (BIM) is exactly the kind of technology that raises this fear. But, BIM has been around for a few years now, and the construction industry has done a good job of curtailing the fear of unanticipated legal liability.
Nevertheless, contractors should be aware of the pitfalls BIM introduces and should know how to limit their risk arising from this new “gadget.”
Often described as “CAD on Steroids,” BIM is truly much more than a simple design program. Along with early clash detection, BIM provides time and cost integration; calculates energy efficiency; and assists building maintenance long after project completion. Unlike CAD, BIM also modifies the collaborative nature of a construction project. Thus, subcontractors no longer review a design, submit shop drawings, and go to work. Rather, subcontractors are brought into the design process early in the project and often are asked to contribute to the design long before construction begins.
Asking a contractor or subcontractor to provide design services appears to shift the roles of an architect and a contractor. So, the questions abound: Is a contractor now responsible for design? Can the contractor be held responsible for defective design? Do not fret. To date, there has been only one advertised case addressing BIM liability. The reason is simple. For almost a hundred years, the United States Supreme Court has held that contractors are not responsible for defective design on a traditional design-bid-build project. Using BIM, therefore, should not modify a contractor’s responsibility. But, to ensure that your obligations do not extend beyond construction, all BIM requirements should be in writing and made part of your contract.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
More Hensel Phelps Ripples in the Statute of Limitations Pond?
February 03, 2020 —
Christopher G. Hill - Construction Law MusingsAs is always the case when I attend the Virginia State Bar’s annual construction law seminar, I come away from it with a few posts on recent cases and their implications. The first of these is not a construction case, but has implications relating to the state project related statute of limitations and indemnification issues for construction contracts brought out in stark relief in the now infamous Hensel Phelps case.
In Radiance Capital Receivables Fourteen, LLC v. Foster the Court considered a waiver of the statute of limitations found in a loan contract. The operative facts are that the waiver was found in a Continuing Guaranty contract and that the default happened more than 5 years prior to the date that Radiance filed suit to enforce its rights. When the defendants filed a plea in bar stating that the statute of limitations had run and therefore the claim was barred, Radiance of course argued that the defendants had waived their right to bring such a defense. The defendants responded that the waiver was invalid in that it violated the terms of Va. Code 8.01-232 that states among other things:
an unwritten promise not to plead the statute shall be void, and a written promise not to plead such statute shall be valid when (i) it is made to avoid or defer litigation pending settlement of any case, (ii) it is not made contemporaneously with any other contract, and (iii) it is made for an additional term not longer than the applicable limitations period.
The Circuit Court and ultimately the Supreme Court agreed with the defendants. In doing so, the Virginia Supreme Court rejected arguments of estoppel and an argument that a “waiver” is not a “promise not to plead.”
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Recent Opinions Clarify Enforceability of Pay-if-Paid Provisions in Construction Contracts
May 29, 2023 —
Patrick McKnight - The Dispute ResolverSeveral recent opinions and legislative actions have brought the controversial nature of pay-if-paid provisions into focus in early 2023. Pay-if-paid provisions are contractual mechanisms designed to shift the risk of non-payment from General Contractors to lower-tier subcontractors. In other words, pay-if-paid provisions generally do not require payment to downstream subs until after the GC or Prime are themselves paid in-full by the owner. Recent developments reflect the differing approaches taken by courts when addressing pay-if-paid provisions, ranging broadly from prohibition to full enforceability. Other jurisdictions fall somewhere in the middle, viewing such provisions with varying amounts of skepticism on the grounds heir impact on smaller downstream subs is disproportionate and unfair.
Pay-if-paid provisions are often contrasted against “pay-when-paid” provisions. Pay-when-paid provisions may require payment within a specified duration but remove the upstream contractor’s payment in-full as a condition precedent. The brief discussion below will not explore pay-when-paid, no damage for delay provisions, or statutory prompt payment acts. Instead, this article serves as a primer on recent legal developments related to pay-if-paid provisions exclusively.
Read the court decisionRead the full story...Reprinted courtesy of
Patrick McKnight, Fox Rothschild LLPMr. McKnight may be contacted at
pmcknight@foxrothschild.com
UK Agency Seeks Stricter Punishments for Illegal Wastewater Discharges
August 07, 2022 —
Peter Reina - Engineering News-RecordBosses of U.K. water and wastewater utilities that are responsible for illegal, serious pollution should be jailed, said Emma Howard Boyd, head of the government's Environment Agency. She made the recommendation along with release of the agency’s annual report on the nine major companies, which recorded the worst environmental performance in a decade.
Reprinted courtesy of
Peter Reina, Engineering News-Record
Mr. Reina may be contacted at reina@btinternet.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of