Alaska District Court Sets Aside Rulings Under New Administration’s EO 13795
May 06, 2019 —
Anthony B. Cavender - Gravel2GavelOn March 29, the U.S. District Court for the District of Alaska issued two separate rulings that reversed and set aside energy and environmental decisions made by the current administration, which had revoked decisions made in these same matters by the prior administration. The cases are League of Conservation Voters, et al., v. Trump (concerning the development of oil and gas leases on the Outer Continental Shelf (OCS)) and Friends of Alaska National Wildlife Refuges, et al., v. Bernhardt, Acting Secretary of the U.S. Department of the Interior (which concerns a Land Exchange that would facilitate the construction of a road between two remote Alaska communities when that road would traverse parts of a designated national wilderness).
In the League of Conservation Voters matter, the District Court held that the President’s Executive Order 13795 (released on April 28, 2017), which purported to revoke President Obama’s decisions to withdraw certain OCS tracts from oil and gas exploration and development, was unlawful because it was not authorized by Section 12(a) of the Outer Continental Shelf Lands Act (OCSLA). In 2015 and 2016, President Obama issued Presidential Memorandums and an Executive Order withdrawing these particular tracts.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Arizona Supreme Court Confirms a Prevailing Homeowner Can Recover Fees on Implied Warranty Claims
August 30, 2017 —
Rick Erickson - Snell & Wilmer Real Estate Litigation BlogOn August 9th, in Sirrah Enterprises, L.L.C. v. Wunderlich, the Arizona Supreme Court settled the question about recovery of attorneys’ fees after prevailing on implied warranty claims against a residential contractor. The simple answer is, yes, a homeowner who prevails on the merits can recover the fees they spent to prove that shoddy construction breached the implied warranty of workmanship and habitability. Why? Because, as Justice Timmer articulated, “[t]he implied warranty is a contract term.” Although implied, the warranty is legally part of the written agreement in which “a residential builder warrants that its work is performed in a workmanlike manner and that the structure is habitable.”
In other words, a claim based on the implied warranty not only arises out of the contract, the claim is actually based on a contract term. Since, in A.R.S. § 12-341.01, Arizona law provides for prevailing parties to recover their fees on claims “arising out of contract” and because the implied warranty is now viewed by the courts as a contract term, homeowners can recover their fees after successfully proving breach of the implied warranty.
Read the court decisionRead the full story...Reprinted courtesy of
Rick Erickson, Snell & WilmerMr Erickson may be contacted at
rerickson@swlaw.com
Mass Timber Reduces Construction’s Carbon Footprint, But Introduces New Risk Scenarios
March 04, 2024 —
Michael Bruch & Franck Fumat - Allianz CommercialMass timber has the potential to be a critical building component for the cities of the near future given the need for the construction sector to reduce its reliance on concrete and steel to lower its Co2 emissions. However, as this market grows and mass timber buildings evolve to greater heights, the construction risk landscape will also be transformed, bringing risk management challenges for companies, according to the new Emerging Risk Trend Talk
report from Allianz Commercial.
“The emergence of mass timber as a sustainable construction alternative represents a significant opportunity for the building sector to reduce its carbon footprint while also satisfying a demand for a material that is more cost-efficient but as durable as steel and concrete,” says Michael Bruch, Global Head of Risk Advisory Services at Allianz Commercial. “However, in any industry, deployment of new materials or processes can result in new risk scenarios, potential defects, or unexpected safety consequences, as well as bringing benefits, and mass timber is no different. Given this market’s expected future growth, companies should do all they can to develop a greater understanding of their exposures including fire, water damage, repetitive loss scenarios and even termite infestation, and ensure they have robust loss prevention measures in place to combat these.”
The need for mass timber
The building and construction sector is among the largest contributors to Co2 emissions, accounting for over 34% of energy demand and around 37% of energy and process related Co2 emissions in
2021 [1]. Given emissions reduction is essential to meet climate change commitments around the world, the need for more sustainable solutions in the built environment has become increasingly important, driven by growing investor and consumer concerns, and legislation, regulation and reporting requirements evolving quickly in many jurisdictions around the world.
Read the court decisionRead the full story...Reprinted courtesy of
Allianz Commercial
Nevada Supreme Court to Decide Fate of Harmon Towers
June 28, 2013 —
CDJ STAFFThe Nevada Supreme Court started hearings on Tuesday, June 4 over the fate of Harmon towers. MGM Resorts is hoping to obtain permission from the court to tear down the tower, which they claim could collapse should an earthquake strike Las Vegas. Perini Corp, the builder, wants the building to remain standing in order to support their claim that the building’s flaws are through design and not construction errors.
KLAS quoted one of Perini’s lawyers claiming that MGM had pursued a media strategy to prejudice potential jurors against the contractor. “CityCenter hired Cedric and Bunting to place advertisements with the media to win the hearts and minds of the community and to convince the public pretrial that Perini was, quote, ‘scum of the earth.’”
If the Supreme Court gives the go-ahead, demolition would begin soon. Still pending, is the $500 lawsuit over the allegations of construction defects.
Read the court decisionRead the full story...Reprinted courtesy of
RDU Terminal 1: Going Green
June 30, 2014 —
Melissa Dewey Brumback – Construction Law in North CarolinaLast week, I had the fortune to join the Triangle USGBC for its “Talk & Walk” about the RDU Terminal 1 renovation project and its sustainable features. For those who haven’t had the chance, I recommend you check out the new terminal specifics the next time you find yourself jet-setting in or out of Raleigh on Southwest airlines.
Terminal 1 has been in operation since 1981, with the last upgrade in 1991. The 2010 opening of the new Terminal 2 had, until now, cemented Terminal 1′s status as the airport’s ugly duckling- complete with the long, featureless metal addition abandoned to times past.
While the $68 million Terminal 1 renovation cannot compete with the Terminal 2 $580 million budget, it nevertheless is an entirely re-imagined space. Better traffic flow (yes, you can now find where to go through security!), increased daylighting, a new canopy system, and commercial curb canopy (see photo) all complete the new architectural image.
Clark Nexsen principals Irvin Pearce and Doug Brinkley explained the renovation, which included energy saving escalators- the first escalator system in North Carolina that slows down during non-use. Other sustainable features include LEED complaint flooring, 86% structural building re-use (slabs on grade, composite decks, and structural roof deck), and 28% reuse of exterior walls.
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Construction Law in North CarolinaMs. Brumback can be contacted at
mbrumback@rl-law.com
Waiving Consequential Damages—What Could Go Wrong?
March 19, 2024 —
Curtis W. Martin & Kellie M. Ros - Peckar & Abramson, P.C.You are inexcusably late with construction of a football stadium, a casino, or similar project that generates large income for the owner. The indirect damages, often referred to as consequential damages, that flow from the delay can be astronomical to the point of breaking your company if it must pay them. As a result, many construction contracts, at every tier, contain a provision that waives consequential damages. By this waiver, a party seeks to limit its risk for these damages.
Over the years, courts have interpreted these provisions in a widely variable and inconsistent manner. The courts typically start with the specific language of the waiver to discern the parties’ intent. Thus, the language of the provision itself is critical. But construction professionals should not overlook other provisions in the contract that may have an impact on a court’s analysis of the parties’ intent. As one of my colleagues likes to say, “the large print giveth and the small print taketh away.”
Reprinted courtesy of
Curtis W. Martin, Peckar & Abramson, P.C. and
Kellie M. Ros, Peckar & Abramson, P.C.
Mr. Martin may be contacted at cmartin@pecklaw.com
Ms. Ros may be contacted at kros@pecklaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Turner Construction Selected for Anaheim Convention Center Expansion Project
May 21, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Anaheim, California city council selected Turner Construction Company “to manage a $180 million expansion of the Anaheim Convention Center, a venue that hosted 238 tradeshows, conventions, meetings and consumer events in 2013,” according to Construction Digital.
“Turner’s Southern California office calls Anaheim home, and we are pleased to be working on such a great project in our own backyard,” Kevin Dow, Vice President and General Manager of Turner’s Southern California office told Construction Digital.
Read the court decisionRead the full story...Reprinted courtesy of
Appropriation Bill Cuts Military Construction Spending
June 15, 2011 —
CDJ STAFFThe Hill reports that HR 2055, the Military Construction, Veterans Affairs (VA) and Related Agencies bill, has passed with only five votes in opposition. The bill cuts the budget for military construction spending by $2.6 billion due to anticipated base closures.
The bill includes $186 million for family housing construction by the Army, $100 million for family housing construction by the Navy and Marines, and $84 million for family construction by the Air Force, with an additional $50 million allocated for the DOD outside the military branches. By the act, these funds will remain available until September 30, 2016.
Read the full story…
Read HR 2055
Read the court decisionRead the full story...Reprinted courtesy of