More Clear, But Not Yet Crystal: Virginia Amends its Prompt Payment Law and Legislation Banning “Pay-If-Paid Clauses in Construction Contracts Effective July 1, 2023
November 16, 2023 —
Hanna Lee Blake - ConsensusDocsThe Virginia General Assembly has joined a minority of jurisdictions that ban pay-if-paid clauses in construction contracts on public and private projects. Senate Bill 550 went into effect applying to contracts executed after January 1, 2023, and most recently has been amended effective July 1, 2023. This update highlights the recent amendments to Virginia’s prohibition against pay-if-paid provisions, of which owners and contractors should be aware to ensure that their contracts comply with developing law in the Commonwealth.
Recap on Senate Bill 550
On April 27, 2022, the Virginia General Assembly passed Senate Bill 550, which amended Virginia Code §§ 2.2-4354 and 11-4.6, which govern both public and private sector contracts. In short, SB 550 (as the bill is commonly known) prohibited pay-if-paid clauses, and established fixed deadlines for the payment of invoices on private projects. Previously, Virginia’s Prompt Payment Act only applied to public projects.
Read the court decisionRead the full story...Reprinted courtesy of
Hanna Lee Blake, Watt TiederMs. Blake may be contacted at
hblake@watttieder.com
Determining the Cause of the Loss from a Named Windstorm when there is Water Damage - New Jersey
March 23, 2020 —
Anna M. Perry - Saxe Doernberger & VitaWater damage, while one of the leading causes of loss under a property policy, often results in some of the most complex claims due to the intersection of exclusions, sublimits, and complex wording within the policy. One particularly difficult issue is whether water damage caused by a storm surge is covered by the flood sublimit, or under the general policy or water limit. In New Jersey Transit Corp. v. Certain Underwriters at Lloyd’s (“NJTC v. Lloyd’s”), the New Jersey Appeals Court found that the “flood” sublimit of the policy should not apply as the cause of the loss was a “named windstorm” and not a “flood.”
In NJTC v Lloyd's the court was asked to determine whether a flood sublimit applied to losses sustained during Superstorm Sandy. The court found that although there was “flooding,” the water damage was more closely related to the “named windstorm”, and therefore, the $400 million policy limits should apply. The court focused its analysis on the definitions for “flood” and “named windstorm” and by applying the efficient proximate cause doctrine to determine which would apply.
When reviewing the definitions within the property policies, the court determined that although the loss would qualify under the definition of “flood,” the policy also contained a definition for “named windstorm” which “more specifically encompasses the wind driven water or storm surge associated with a ‘named windstorm’”1. In addition, the policy did not specifically state that “storm surge” associated with a “named windstorm” should be considered a “flood” event and fall under the “flood” sublimit.
Read the court decisionRead the full story...Reprinted courtesy of
Anna M. Perry, Saxe Doernberger & VitaMs. Perry may be contacted at
amp@sdvlaw.com
Landlords Challenge U.S. Eviction Ban and Continue to Oust Renters
October 25, 2020 —
Kriston Capps - BloombergIn September, the Trump administration announced a national moratorium on evictions, via an order by the Centers for Disease Control and Prevention aimed at reducing the spread of coronavirus. The four-month temporary suspension applies to any tenant who can’t make rent due to economic conditions and who presents a written declaration about their circumstances to their landlord.
But the CDC ban now faces legal challenges on multiple fronts, even as landlords continue to routinely file evictions for nonpayment of rent — the very outcome that the order was designed to prevent.
On Oct. 20, the U.S. District Court for the Northern District of Georgia heard the first case against the moratorium, Richard Lee Brown, et al. v. Secretary Alex Azar, et al.. That challenge, brought by a nonprofit called the New Civil Liberties Alliance, has been joined by the National Apartment Association, which represents some 85,000 landlords responsible for 10 million rental units. Lawyers and scholars working on behalf of plaintiffs in the cases say that the CDC lacks the constitutional authority to enact a policy affecting rents.
Read the court decisionRead the full story...Reprinted courtesy of
Kriston Capps, Bloomberg
OSHA Releases COVID-19 Guidance
June 15, 2020 —
L. Stephen Bowers & Joshua Tumen - White and Williams LLPThe United States Department of Labor’s Occupational Safety and Health Administration (OSHA) ensures safe and healthful working conditions for employees by setting and enforcing standards and by providing training, outreach, education and assistance.
The COVID-19 outbreak has increased demand for N95 filtering face piece respirators (N95 FFRs), limiting availability for workers in healthcare and emergency response. On April 3, 2020, OSHA issued interim guidance for employers to combat the supply shortages of N95 FFRs and to comply with the respiratory protection standard (29 CFR § 1910.134). This guidance will remain in effect until further notice and applies in all industries.
Employers must continue to manage their respiratory protection programs and be mindful of N95 FFR shortages. Specifically, employers should identify and evaluate respiratory hazards in the workplace, and develop and implement written respiratory protection programs. Businesses should reassess their engineering controls, work practices, and administrative controls to identify any changes they can make to decrease the need for N95 FFRs. Some examples provided in the guidance include using portable local exhaust systems or moving operations outdoors. Employers may also consider temporarily suspending non-essential operations, to the extent such operations are not already suspended due to state mandates.
Reprinted courtesy of
L. Stephen Bowers, White and Williams LLP and
Joshua Tumen, White and Williams LLP
Mr. Bowers may be contacted at bowerss@whiteandwilliams.com
Mr. Tumen may be contacted at tumenj@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Shifting the Risk of Delay by Having Float Go Your Way
July 05, 2021 —
Christopher J. Brasco & Matthew D. Baker - ConsensusDocsCritical path delay plays a central role in allocating responsibility for project delay. The interrelated concept of concurrency is also frequently determinative of entitlement on a range of claims including by owners for liquidated damages and by contractors for delay damages. What constitutes critical/concurrent delay, however, is hotly debated by scheduling experts. The lack of real consensus regarding how critical/concurrent delay should be determined and analyzed has created significant uncertainty in scheduling disputes. Indeed, courts have adopted differing and at times conflicting theories of concurrency that can produce divergent outcomes for the parties. In an effort to reduce uncertainty, stakeholders have increasingly adopted specialized contractual provisions and scheduling techniques which have significant implications for the evaluation of the companion concepts of criticality and concurrency. One such mechanism is float sequestration. Regardless of whether float sequestration is ultimately in the construction industry’s broader interest, stakeholders must be able to recognize its use and appreciate the implications for delay disputes on their projects.
Simply defined, float is the number of days an activity can be delayed before affecting the project’s critical path (i.e., the longest chain of activities which determines the project’s minimal duration). Typically, only delays affecting the critical path can produce concurrent delay. Consequently, the concept of float is integral to understanding and resolving issues of both criticality and concurrency.
Reprinted courtesy of
Christopher J. Brasco, Watt, Tieder, Hoffar & Fitzgerald, LLP and
Matthew D. Baker, Watt, Tieder, Hoffar & Fitzgerald, LLP
Mr. Brasco may be contacted at cbrasco@watttieder.com
Mr. Baker may be contacted at mbaker@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Two Architecturally Prized Buildings May be Demolished
January 17, 2014 —
Beverley BevenFlorez-CDJ STAFFThe historic Portland Public Services Building, designed by Michael Graves, may be demolished after a report showed that “the 32-year-old building needs more than $95 million worth of repairs,” Dezeen Magazine reported. The Portland, Oregon building “is credited with being one of the first major buildings of postmodernism.” According to The Oregonian, the Portland city commissioners have differing opinions as to how to proceed. Council member Amanda Fritz commented that she “doesn’t think the problems at The Portland Building are all that bad compared to other city facilities,” while council member Nick Fish stated, “There’s got to be a better option than putting another $100 million into a white elephant.”
Dezeen Magazine also reported that the former American Folk Art Museum in New York is scheduled to be demolished to make room to extend the Museum of Modern Art (MoMA). Glenn Lowry, the MoMA director, stated that the decision came after a six-month study: “The analysis that we undertook was lengthy and rigorous, and ultimately led us to the determination that creating a new building on the site of the former American Folk Art Museum is the only way to achieve a fully integrated campus.”
The decision is being criticized by “architects, conservationists, and critics” reported Dezeen Magazine. Architects Tod Williams and Billie Tsien designed the former American Folk Art Museum. Williams and Tsien stated, “Demolishing this human-scaled, uniquely crafted building is a loss to the city of New York in terms of respecting the size, diversity and texture of buildings in a midtown neighborhood that is at risk of becoming increasingly homogenized."
Read the full story at Dezeen Magazine re The Portland Building...
Read the full story at The Oregonian re The Portland Building...
Read the full story at Dezeen Magazine re American Folk Art Museum... Read the court decisionRead the full story...Reprinted courtesy of
68 Lewis Brisbois Attorneys Recognized in 5th Edition of Best Lawyers: Ones to Watch in America
September 23, 2024 —
Lewis Brisbois Newsroom(August 15, 2024) – 68 Lewis Brisbois attorneys across 26 offices have been named to the 5th edition of “Best Lawyers: Ones to Watch in America.” Congratulations to the following attorneys on this recognition!
You can see the list of Lewis Brisbois attorneys named to Best Lawyers' 30th edition of The Best Lawyers in America here.
Reprinted courtesy of
Lewis Brisbois
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Resolve to Say “No” This Year
January 26, 2016 —
Christopher G. Hill – Construction Law MusingsWe hear all of the time how to “get to ‘yes'” and how doing so can lead to more business and of course more business leads to more profits. Purely logical, right? Without construction owners with work for general contractors to perform and general contractors hiring subcontractors to perform that work, construction grinds to a halt and clients and friends of mine in the construction industry don’t make money. For this to happen, “yes” has to happen more often than not. So, why the title of this post?
Chalk it up to spending much if not all of my time as a construction attorney either anticipating or dealing with the Murphy’s Law ruled nature of the construction world or to the “Monday morning quarterback” nature of my profession, but I see numerous instances where not taking the job or signing the bad contract would have led to a better outcome than performing the work. What do I mean by this? I mean that as a construction company (particularly one that is lower down the “payment chain” and therefore less in control of the flow of money), you need to carefully evaluate not only the contract presented, but whether you get a good feeling about the party with whom you are contracting.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at