Can I Be Required to Mediate, Arbitrate or Litigate a California Construction Dispute in Some Other State?
September 19, 2022 —
William L. Porter - Porter Law GroupIt is not uncommon in the construction industry for an out-of-state general contractor to include a provision in a subcontract requiring a California subcontractor to resolve disputes outside the state of California, even though the work is to be performed within California. Fortunately, most California subcontractors are immune from this tactic. California law generally prohibits clauses requiring subcontractors to travel outside California to resolve construction disputes.
California Code of Civil Procedure Section 410.42, [CCP 410.42 Link] renders “void and unenforceable,” any provision in a contract that “purports to require any dispute to be litigated, arbitrated, or otherwise determined outside this state,” so long as the contract is “between the contractor and a subcontractor with principal offices in the state, for the construction of a public or private work of improvement in this state.” Similarly, this law voids any similar contractual term that might prevent the California subcontractor from commencing an action, obtaining a judgment, or resolving its dispute in the courts of California.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Can’t Get a Written Change Order? Document, Document, Document
August 29, 2018 —
Todd M. Heffner - Smith CurrieMost construction contracts require that any changes to the work be made formally, in writing, via a change order, work directive, or similar written document. Frequently, however, changes to the work or extra work are communicated orally by the architect, engineer, or owner’s representative, instead of in writing. What is the contractor to do in such a situation? The best option is follow the provisions of the contract and demand a written change order before performing changed work. Unfortunately, the realities of construction sometimes make it impossible to get the changes in the proper format in a timely manner. Savvy contractors will maintain schedule and produce written documentation of the change in lieu of a formal change order or directive. But many contractors will simply proceed with the changed work, relying on the owner, architect, or engineer to do the right thing and stand by their oral instructions.
Read the court decisionRead the full story...Reprinted courtesy of
Todd M. Heffner, Smith CurrieMr. Heffner may be contacted at
tmheffner@smithcurrie.com
San Diego’s NFL Stadium Dream Counts on Munis for Chargers’ Home
June 10, 2015 —
James Nash and Darrell Preston – BloombergSan Diego, still dealing with the legacy of a pension crisis that led politicians to consider bankruptcy a decade ago, may throw taxpayer money behind municipal bonds for a football-stadium bidding war.
The city and the National Football League’s Chargers are negotiating on a proposed $1.3 billion coliseum to keep the team from leaving for Los Angeles. A plan backed by a city panel would have San Diego pay $121 million of the new stadium’s debt, even though it still owes $52 million for the Chargers’ current home. San Diego County would chip in, too.
The quest to keep the team has triggered a debate over whether to finance professional football as the city deals with $2 billion of deferred maintenance brought about in part by mounting pension costs. The city’s retirement system has a shortfall just as large, which led voters three years ago to approve reducing benefits for city workers.
Reprinted courtesy of
James Nash, Bloomberg and
Darrell Preston, Bloomberg Read the court decisionRead the full story...Reprinted courtesy of
Virginia Allows Condominium Association’s Insurer to Subrogate Against a Condominium Tenant
August 10, 2020 —
Gus Sara - The Subrogation StrategistIn Erie Insurance Exchange v. Alba, Rec. No. 190389, 2020 Va. LEXIS 53, the Supreme Court of Virginia considered whether the trial court erred in finding that a condominium association’s property insurance provider waived its right of subrogation against a tenant of an individual unit owner. The Supreme Court reversed the lower court’s decision, holding that the insurance policy only named unit owners as additional insureds, not tenants, and thus the subrogation waiver in the insurance policy did not apply to tenants. The court also found that the condominium association’s governing documents provided no protections to the unit owner’s tenant because the tenant was not a party to those documents. This case establishes that, in Virginia, a condominium association’s insurance carrier can subrogate against a unit owner’s tenant where the tenant is not identified as an additional insured on the policy.
The Alba case involved a fire at a condominium building originating in a unit occupied by Naomi Alba (Alba), who leased the condominium under a rental agreement with the unit owner, John Sailsman (Sailsman). The agreement explicitly held Alba responsible for her conduct and the conduct of her guests. An addendum to the lease stated that Sailsman’s property insurance only applied to the “dwelling itself” and that Alba was required to purchase renters insurance to protect her personal property. Along with the rental agreement, Alba received the condominium association’s Rules & Regulations, Declarations and Bylaws.
Read the court decisionRead the full story...Reprinted courtesy of
Gus Sara, White and WilliamsMr. Sara may be contacted at
sarag@whiteandwilliams.com
California Supreme Court Finds that the Notice-Prejudice Rule Applicable to Insurance is a Fundamental Public Policy of the State
October 14, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Pitzer College v. Indian Harbor Ins. Co. (No. S239510, filed 8/29/19), the California Supreme Court held that California’s notice-prejudice rule is a fundamental public policy in the insurance context, supporting the application of California law under a choice of laws analysis. In addition, the Court held that the rule generally applies to consent (aka “no voluntary payments”) provisions in first party insurance policies but not to consent provisions in third party liability policies.
Pitzer College discovered soils contamination while building a new dormitory. Under pressure to complete construction before the start of the school year, Pitzer proceeded to remediate the soils, incurring $2 million in expense. Pitzer submitted a claim to Indian Harbor, which provided Pitzer insurance covering legal and remediation expenses resulting from pollution conditions discovered during the policy period.
The policy contained a notice provision requiring Pitzer to provide oral or written notice of any pollution condition to Indian Harbor and, in the event of oral notice, to “furnish … a written report as soon as practicable.” In addition, a consent provision required Pitzer to obtain Indian Harbor’s written consent before incurring expenses, making payments, assuming obligations, and/or commencing remediation due to a pollution condition. The consent provision had an emergency exception for costs incurred “on an emergency basis where any delay … would cause injury to persons or damage to property or increase significantly the cost of responding to any [pollution condition],” in which case Pitzer was required to notify Indian Harbor “immediately thereafter.” Lastly, a choice of law provision stated that New York law governed all matters arising under the policy.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Excess-Escape Other Insurance Provision Unenforceable to Avoid Defense Cost Contribution Despite Placement in Policy’s Coverage Grant
April 20, 2016 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel, LLPIn Certain Underwriters at Lloyds, London v. Arch Specialty Ins. Co. (No. C072500; filed 4/11/16), a California appeals court found an “other insurance” provision unenforceable to excuse defense contribution between successive primary insurers, regardless of the fact that the limiting language was contained in the policy’s coverage grant.
Certain Underwriters and Arch each insured Framecon over successive policy periods. Framecon was sued by a developer in a series of construction defect actions, and tendered to both insurers. Underwriters agreed to defend under a reservation of rights but Arch declined, citing the wording of its insuring agreement, which stated:
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Chambers USA 2023 Recognizes Six Partners and Three Practices at Lewis Brisbois
June 19, 2023 —
Lewis Brisbois NewsroomNew York, N.Y. (June 6, 2023) – Six Lewis Brisbois partners and three Lewis Brisbois practices were recently ranked by Chambers in its 2023 USA rankings list.
Kansas City & Wichita Managing Partner Alan L. Rupe and Phoenix Managing Partner Carl F. Mariano were both ranked Band 1 for “Labor & Employment – Kansas” and “Insurance – Arizona,” respectively. Phoenix Partner Gina M. Bartoszek was ranked Band 2 for “Insurance – Arizona.” Washington, D.C. Managing Partner Jane C. Luxton and Minneapolis Partner Tina A. Syring were both ranked Band 4 for “Environment – District of Columbia” and “Labor & Employment – Minnesota,” respectively. Additionally, Washington, D.C. & Fort Lauderdale Partner J. Mario Fontes, Jr. was ranked Band 5 for “Corporate/M&A & Private Equity – Florida: South.”
Read the court decisionRead the full story...Reprinted courtesy of
Lewis Brisbois
Florida’s Fourth District Appeals Court Clarifies What Actions Satisfy Florida’s Construction Defect Statute of Repose
November 14, 2018 —
Rahul Gogineni - The Subrogation SpecialistIn Gindel v. Centex Homes, 2018 Fla.App. LEXIS 13019, Florida’s Fourth District Court of Appeal recently concluded that the date on which the plaintiffs provided a pre-suit notice in compliance with §558.004 of Florida’s construction defect Right-to-Cure statute, Fla. Stat. §§ 558.001 to 558.005, et. seq., is the date on which the plaintiff commenced a “civil action or proceeding,” i.e. an “action,” within the meaning of Florida’s construction defect statute of repose, Florida Statue § 95.11(3)(c). Thus, reversing the decision of the trial court, the Fourth District held that the plaintiffs timely-filed their construction defect action against the defendants.
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com