Architects and Engineers Added to Harmon Towers Lawsuit
February 12, 2013 —
CDJ STAFFSince the beginning of the Harmon Towers construction defect lawsuit, it has been CityCenter making claims against Perini, the property owner against the builder. CityCenter now has a new legal team, and with it apparently a new strategy. The Las Vegas Review Journal reports that papers were filed in court on February 8, adding the architect and the engineer as defendants in the case.
According to the filings, the engineering firm Halcrow Yolles should have noticed during inspections that parts of the building’s steel skeleton were improperly installed and should have been repaired. Instead these structures were encased in concrete. CityCenter also contends that there were deficiencies in Halcrow’s blueprints. AAI Architects has been named because its contract made it responsible for Halcrow’s work.
Perini has contended that some problems at the building were due to bad plans and therefore not their responsibility. They have claimed that they can fix the building for $20 million, of which $4 million would be due to their actions.
Read the court decisionRead the full story...Reprinted courtesy of
Housing Advocacy Group Moved to Dissolve New Jersey's Council on Affordable Housing
November 05, 2014 —
Beverley BevenFlorez-CDJ STAFFThe New Jersey Law Journal reported that "[a]n affordable housing advocacy group in New Jersey is asking the state Supreme Court to remove from the administration of Gov. Chris Christie the authority to determine municipalities’ obligations for low- and moderate-income housing and to instead place that responsibility in the hands of trial judges."
New Jersey's state constitution mandates affordable housing obligations (referred to as the Mount Laurel decisions).
“It is no longer possible to trust that COAH can or will faithfully implement the Mount Laurel doctrine,” wrote the center’s associate director, Kevin Walsh, in the motion to enforce litigants’ rights, as quoted by the New Jersey Law Journal. “This should be the end; there should be no more extensions, no further last chances.”
Municipalities are protected from being sued by developers, however, last year the court stated "that it would consider lifting that protection if COAH failed to adopt new regulations that passed constitutional muster," according to the New Jersey Law Journal.
Read the court decisionRead the full story...Reprinted courtesy of
Oregon Courthouse Reopening after Four Years Repairing Defects
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Courthouse Square in Marion County, Oregon is due to reopen after four years and nearly $23 million of repair costs to fix structural defects, according to the Statesman Journal. The square includes a courthouse building and bus mall, and is jointly owned by the county and transit district.
Two years after the Courthouse Square had been built, cracks were observed “in the building’s walls” and “paving stones on the bus mall shifted and settled.” A construction defect suit was filed in 2006.
However, the situation worsened in July of 2010 when “engineers determined that the entire complex was dangerous,” according to the Statesman Journal. “Building safety officials gave Courthouse Square’s occupants 60 days to move out, forcing county and transit district operations into temporary leased space.”
Now that the structural repairs have been completed, Dave Clark, project manager with Structural Preservation Systems LLC (the company awarded the repair contract), stated that the building’s structure is now stronger than most buildings. “If there’s an earthquake, come to this building,” Clark said.
Read the court decisionRead the full story...Reprinted courtesy of
Window Installer's Alleged Faulty Workmanship On Many Projects Constitutes Multiple Occurrences
May 10, 2017 —
Tred R. Eyerly - Insurance Law HawaiiLawsuits filed for recovery due to the faulty design and installation of doors and windows by homeowners across the country were found to allege multiple occurrences. Pella Corp. v. Liberty Mut. Ins. Co., 2017 U.S. Dist. 53631 (C.D. Iowa March 31, 2017).
The underlying lawsuits alleged that Pella Corporation's windows were defectively designed, manufactured, or installed, and allowed water intrusion to buildings that resulted in third-party property damage or personal injury.
Pella sued Liberty Mutual for declaratory judgment and filed a motion for partial summary judgment to determine how many occurrences the underlying cases presented. Pella sought a determination that each of the 15 underlying cases presented one "occurrence" as the term was defined in the CGL policies issued by Liberty Mutual. Liberty Mutual argued that only three or four occurrences were presented, relying on common fact patterns.
Pella argued that there were separate and distinct causes of different injuries and damage and thus, each underlying case constituted a separate occurrence. Liberty Mutual, on the other hand, highlighted language within the definition of "occurrence," which stated that an "occurrence" included "continuous or repeated exposure to the same general harmful conditions." The "substantially the same general harmful conditions" language dictated that the scope of "occurrence" be understood to be broad, such that various instances of damage-causing water intrusion in different times and places constituted "substantially the same general harmful conditions."
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly - Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
New York Condominium Association Files Construction Defect Suit
December 10, 2015 —
Beverley BevenFlorez-CDJ STAFFAccording to The Real Deal, “The condominium association at 15 Union Square West has filed a $5 million lawsuit against developer Brack Capital Real Estate eight years after the building first launched sales, alleging that the firm did not deliver the quality of units it promised when residents originally signed their contracts.”
Alleged problems include roof leaks, lack of terrace landscaping, and patchy electrical work, The Real Deal reported.
A spokesperson for Brack stated, “We stand behind our product and are very proud of it.”
Read the court decisionRead the full story...Reprinted courtesy of
Buy a House or Pay Off College? $1.2 Trillion Student Debt Heats Up in Capital
June 11, 2014 —
Janet Lorin – BloombergJennifer Day spends 12 percent of her monthly take-home pay on debt that funded a master’s degree in urban and regional planning, money she’d rather be saving toward a home.
“I spend $364 a month for student loans,” said Day, 33, who conducts market research for the hospitality industry at a consulting firm in New Orleans. “To me, that is a down payment or ultimately savings down the line.”
Under legislation sponsored by U.S. Senator Elizabeth Warren of Massachusetts, Day would save about $75 a month on her payments. The bill, which could come up for a vote on the Senate floor as soon as tomorrow, would let 25 million borrowers with federal and private loans refinance their balances at lower interest rates, according to Education Department estimates.
Read the court decisionRead the full story...Reprinted courtesy of
Janet Lorin, BloombergMs. Lorin may be contacted at
jlorin@bloomberg.net
Wyncrest Commons: Commonly Used Progress Payments in Construction Contracts Do Not Render Them Installment Contracts
December 11, 2023 —
Benjamin J. Hochberg - Peckar & Abramson, P.C.In BIL-JIM Construction Company, Inc. v. Wyncrest Commons, LP, 2023 WL 7276637 (Unpublished, decided November 3, 2023), the New Jersey Appellate Division was asked to consider two issues regarding the interpretation and application of a construction contract that utilized the standard form American Institute of Architects owner/contractor agreement (AIA Document A101-2007) (the “AIA Contract”). Specifically, it was asked to consider: 1) whether a modified AIA Contract was an “installment contract,” whereby each progress payment was subject to its own statute of limitations; and 2) whether and when work had been approved in the context of New Jersey’s Municipal Land Use Law. While the decision is presently unpublished, it provides guidance as to how form contracts utilizing the same or similar terms will be treated by New Jersey’s courts and is a reminder that the potential for future claims must be considered during contract negotiations.
Discussion
The primary issue in Wyncrest was whether an AIA Contract was an “installment contract,” and the remaining issues turned on the resolution of this question. Wyncrest, the owner for the project at issue, did not dispute that its contractor, BIL-JIM Construction Company, Inc., had not been fully paid for work that it had performed in connection with a construction project located in Ocean County, New Jersey. Instead, Wyncrest argued that because its AIA Contract with BIL-JIM required that invoices be presented and paid monthly, it constituted an “installment contract.” As such, older payments would be treated as individual transactions and were time barred by the applicable statute of limitations. The trial court agreed with Wyncrest’s characterization of the AIA Contract as an “installment contract,” and found that BIL-JIM’s invoices were each subject to their own statute of limitations. However, the trial court disagreed with Wyncrest’s argument that BIL-JIM’s claim for retainage—which was submitted at the end of its work at the project—was time barred.
Read the court decisionRead the full story...Reprinted courtesy of
Benjamin J. Hochberg, Peckar & Abramson, P.C.Mr. Hochberg may be contacted at
bhochberg@pecklaw.com
For Whom Additional Insured Coverage Applies in New York
November 11, 2024 —
Bill Wilson - Construction Law ZoneSimply including a requirement in a contract to add certain parties as additional insureds under a commercial general liability insurance (CGL) policy may not be enough to ensure such coverage is provided in New York. In New York City Hous. Auth. v. Harleysville Worcester Ins. Co., 226 A.D.3d 804 (2024), the New York Supreme Court Appellate Division – Second Department ruled that the language in an insurance endorsement required privity of contract with the insured party subcontractor to obtain additional insured status and denied coverage to others despite a provision in a subcontract requiring such additional insured coverage.
In this case, an owner entered into a contract with a general contractor for construction services. The general contractor entered into a subcontract with a subcontractor. The subcontractor agreed to procure and maintain a CGL policy naming the owner, the general contractor, and another related party as additional insureds thereunder. An employee of the subcontractor was injured on the project and sued the three additional insureds and several other parties. Subcontractor’s insurance company refused to defend and indemnify any party other than the general contractor. All the parties sued by the subcontractor’s employee brought an action against the subcontractor’s insurance company, seeking coverage for defense and indemnification as additional insureds under the subcontractor’s CGL policy.
Read the court decisionRead the full story...Reprinted courtesy of
Bill Wilson, Robinson & Cole LLPMr. Wilson may be contacted at
wwilson@rc.com