South Dakota Supreme Court Holds That Faulty Workmanship Constitutes an “Occurrence”
September 14, 2017 —
Samantha Martino - Saxe Doernberger & Vita, P.C.The South Dakota Supreme Court recently determined that damage resulting from a subcontractor’s failure to test soil compaction before constructing a home constituted an “accident” and was therefore an “occurrence” under a commercial general liability (CGL) policy.
In Owners Ins. Co. v. Tibke Construction, Inc., the homeowners hired Tibke Construction, Inc. to build a new house, and Tibke Construction hired subcontractor Jerry’s Excavating to perform excavation work. The homeowners contended that Jerry’s Excavating failed to do soil compaction testing before commencing construction, which resulted in the home being built on highly expansive soils, leading to damage including excessive settlement, cracking and structural unsoundness.
Read the court decisionRead the full story...Reprinted courtesy of
Samantha Martino, Saxe Doernberger & Vita, P.C.Ms. Martino may be contacted at
smm@sdvlaw.com
Reconciling Prompt Payments and Withholding of Retention Payments
March 30, 2016 —
Eric J. Rollins, Esq. – Newmeyer & Dillion, LLPIt is common in California for the owners of a project to make monthly payments to a contractor for work as it is completed, but withhold a certain percentage as a guarantee of future satisfactory performance. Contractors almost always pass these withholdings on to their subcontractors. Unsurprisingly, disputes can arise regarding when the withheld retentions must be paid.
Civil Code section 8814, subdivision (a), states that a direct contractor must pay each subcontractor its share of a retention payment within ten days after receiving all or part of a retention payment. However, an exception exists -- a direct contractor may withhold from the retention paid to a subcontractor an amount not in excess of 150 percent of the estimated value of the disputed amount, whenever a “good faith dispute exists between the direct contractor and a subcontractor.” (See Cal. Civ. Code, § 8814, subd. (c).) The problem with the statute is that it offers no help in defining a “good faith dispute,” and the California courts have historically not provided much guidance either. Can a “good faith dispute” be any dispute between the contracting parties, e.g., a dispute regarding change orders, mismanagement, etc.? Or must the dispute relate specifically to the retention? Unfortunately for California litigants, the answer may depend on the appellate district in which the parties find themselves.
Read the court decisionRead the full story...Reprinted courtesy of
Eric J. Rollins, Esq., Newmeyer & Dillion, LLPMr. Rollins may be contacted at
eric.rollins@ndlf.com
Terms of Your Teaming Agreement Matter
July 30, 2019 —
Christopher G. Hill - Construction Law MusingsThese days in construction, and other pursuits, teaming agreements have become a great method for large and small contractors to work together to take advantage of various contract and job requirements from minority participation to veteran ownership. With the proliferation of these agreements, parties must be careful in how they draft the terms of these agreements. Without proper drafting, the parties risk unenforceability of the teaming agreement in the evewnt of a dispute.
One potential pitfall in drafting is an “agreement to agree” or an agreement to negotiate a separate contract in the future. This type of pitfall was illustrated in the case of InDyne Inc. v. Beacon Occupational Health & Safety Services Inc. out of the Eastern District of Virginia. In this case, InDyne and Beacon entered into a teaming agreement that provided that InDyne as Prime would seek to use Beacon, the Sub, in the event that InDyne was awarded a contract using Beacon’s numbers. The teaming agreement further provided:
The agreement shall remain in effect until the first of the following shall occur: … (g) inability of the Prime and the Sub, after negotiating in good faith, to reach agreement on the terms of a subcontract offered by the Prime, in accordance with this agreement.
InDyne was subsequently awarded a contract with the Air Force and shortly thereafter sent a subcontract to Beacon and requested Beacon’s “best and final” pricing. Beacon protested by letter stating that it was only required to act consistently with its original bid pricing. Beacon then returned the subcontract with the original bid pricing and accepting all but a termination for convenience provision. Shortly thereafter, InDyne informed Beacon that InDyne had awarded the subcontract to one of Beacon’s competitors. Beacon of course sued and argued that the teaming agreement required that InDyne award the subcontract to Beacon.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Wendel Rosen’s Construction Practice Group Welcomes Quinlan Tom
January 06, 2016 —
Garret Murai – California Construction Law BlogThere’s been more cheer than usual at Wendel Rosen’s Construction Practice Group this holiday season.
Earlier this month, Quinlan Tom, a construction and business attorney, joined us from McInerney & Dillon, a venerable and well-respected construction boutique firm (we know a lot of folks there) with local roots like us in Oakland, California. We’ve all known Quinlan for a while, so when he decided to join our band of merry legal practitioners, we were quite thrilled.
Being lawyers though, and better at asking than answering questions, we decided to pose a few questions to Quinlan:
Q. So, you’ve just been sworn to tell the truth, the whole truth, and nothing but the truth, under penalty of perjury. So, tell us about your practice.
A. Let me just start with it’s quite an honor to appear in your blog; I’ve been a reader for a while (in secret of course before I got to Wendel Rosen). I’m also excited to join you and the other members of Wendel Rosen’s Construction Practice Group; as you mention, I’ve known each of you professionally for quite some time and respect each of you tremendously.
I started as a construction litigator right out of law school. I completed three years of mechanical engineering at UC Davis and put that on my resume when I was looking for a job after law school. (In addition, my dad retired after 40 years in the trenches as a union electrician). McInerney & Dillon (“M&D”) and a couple of other firms found that interesting and I ended up starting with M&D. I did find that my engineering studies helped with my acclimation to construction disputes. While I never pretend to be an engineer, it has provided me with a foundation of how the construction process works and how the projects are designed. 26 years later, I continue to enjoy counseling my clients in their construction disputes/issues and still find each construction project I am involved with fascinating.
I have tried, arbitrated and litigated cases for 26 years, from the United States District Court to the California Superior Court and the California Office of Administrative Hearings. I have argued cases before the Ninth Circuit Court of Appeals and the California Court of Appeal. I counsel my clients into hopefully making the best business decisions available melding the knowledge I have gleaned from my litigation experience with their financial and personal goals.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Local Government’s Claims on Developer Bonds Dismissed for Failure to Pursue Administrative Remedies
March 22, 2017 —
David R. Cook - Autry, Hanrahan, Hall & Cook, LLPThe Georgia Court of Appeals recently affirmed a trial court’s dismissal of a county’s claim on developer bonds based on its failure to exhaust administrative remedies. Douglas County v. Hamilton State Bank, — Ga. App. –, A16A1708 (Mar. 16, 2017). Specifically, because the bank was under FDIC receivership, the County was required to pursue administrative remedies under the Financial Institutions Reform, Recovery, and Enforcement Act of 1989 (the “Act”).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hanrahan, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
The Nightmare Scenario for Florida’s Coastal Homeowners
April 20, 2017 —
Christopher Flavelle - BloombergOn a predictably gorgeous South Florida afternoon, Coral Gables Mayor Jim Cason sat in his office overlooking the white-linen restaurants of this affluent seaside community and wondered when climate change would bring it all to an end. He figured it would involve a boat.
When Cason first started worrying about sea-level rise, he asked his staff to count not just how much coastline the city had (47 miles) or value of the property along that coast ($3.5 billion). He also told them to find out how many boats dock inland from the bridges that span the city’s canals (302). What matters, he guessed, will be the first time a mast fails to clear the bottom of one of those bridges because the water level had risen too far.
“These boats are going to be the canary in the mine,” said Cason, who became mayor in 2011 after retiring from the U.S. foreign service. “When the boats can’t go out, the property values go down.”
If property values start to fall, Cason said, banks could stop writing 30-year mortgages for coastal homes, shrinking the pool of able buyers and sending prices lower still. Those properties make up a quarter of the city’s tax base; if that revenue fell, the city would struggle to provide the services that make it such a desirable place to live, causing more sales and another drop in revenue.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher Flavelle, Bloomberg
Nuclear Energy Gets a Much-Needed Boost
August 05, 2024 —
The Editorial Board - BloombergPresident Joe Biden, as you’ve no doubt heard, has had a rough few weeks. Yet on Tuesday, he signed a bill into law that could well prove transformative for America’s energy future. Here’s hoping — whatever happens in November’s election — that more progress lies ahead.
Known as the Advance Act, the bill seeks to remedy some long-standing flaws in nuclear-energy regulation. To reach net zero, the world will need to roughly double its nuclear capacity by 2050, according to the International Energy Agency. Yet constructing new nuclear plants in the US is expensive, time-consuming and encumbered by red tape. Partly as a result, the industry has stagnated: The share of electricity generated by nuclear is projected to decline to about 12% by 2050, from about 18% today.
The Advance Act should help reverse that trend. As a start, it makes useful reforms to the Nuclear Regulatory Commission, allowing the agency to hire more staff, reduce licensing fees, speed application processing and ease the burden of environmental reviews. It also makes a small but consequential change to the commission’s mission, requiring it — after decades of focusing on potential threats — to also consider the vast public benefits of nuclear energy when making regulatory decisions.
Read the court decisionRead the full story...Reprinted courtesy of
The Editorial Board, Bloomberg
Florida Court of Appeals Holds Underlying Tort Case Must Resolve Before Third-Party Spoliation Action Can Be Litigated
December 04, 2018 —
Lian Skaf - The Subrogation StrategistIn Amerisure Ins. Co. v. Rodriguez, 43 Fla. L. Weekly 2225 (Fla. Dist. Ct. App., Sept. 26, 2018), the Third District Court of Appeals of Florida addressed whether a third-party spoliation claim should be litigated and tried at the same time as the plaintiff’s underlying tort case. The court held that since the third-party spoliation claim did not accrue until the underlying claim was resolved, the spoliation cause of action could not proceed until the plaintiff resolved his underlying claim.
The underlying matter in Amerisure involved a personal injury claim by plaintiff Lazaro Rodriguez. While working as an employee for BV Oil, Inc. (BV), Mr. Rodriguez was knocked from the top of a gasoline tanker he was fueling at a gasoline storage warehouse owned by Cosme Investment (Cosme). Mr. Rodriguez filed a personal injury lawsuit against Cosme. He also collected worker’s compensation benefits from Amerisure Insurance Company (Amerisure), BV’s worker’s compensation carrier, while his lawsuit was pending.
Read the court decisionRead the full story...Reprinted courtesy of
Lian Skaf, White & Williams LLPMr. Skaf may be contacted at