Court Rules in Favor of Treasure Island Developers in Environmental Case
July 09, 2014 —
Beverley BevenFlorez-CDJ STAFFA California court ruled that the Environmental Impact Report (EIR) that had been approved by the city of San Francisco was adequate for the proposed 8,000-home development on Treasure Island, according to the San Francisco Business Times.
The suit had been brought by Citizens for a Sustainable Treasure Island back in 2011. However, in December of 2012, “a lower court affirmed the EIR and the citizens’ group appealed that decision.”
The project was proposed by partners Lennar Corp. and Wilson Meany. The development would “add thousands of new housing units along with retail, hotel and office space in addition to renovating historic buildings and creating 300 acres of open space.”
Read the court decisionRead the full story...Reprinted courtesy of
Construction Delays: Which Method Should Be Used to Calculate Delay?
July 25, 2021 —
David Adelstein - Florida Construction Legal UpdatesIf you need to prove and allocate construction project delays, you should engage a scheduling consultant qualified with CPM (critical path method) analysis. You should also engage counsel to assist in preserving your rights, as well as presenting and maximing your arguments for delay.
There are numerous methodologies used to quantify and allocate delay. You want to discuss the most effective analysis for your case and facts including whether you want/should use a forward-looking prospective analysis or a backward-looking retrospective analysis that factors in as-built data. In doing so, you want to make sure you understand the pros and cons of each methodology including the bases to attack the methodology that will be subject to cross-examination. The five primary CPM methodologies are as follows:
- As-Planned Versus As-Built. This methodology compares the as-planned baseline schedule to an as-built schedule reflecting progress to assign delay. An as-built schedule that reflects progress includes actual start dates, finish dates, and durations. The actual dates and durations are compared with the as-planned dates and durations on the baseline schedule to determine delay. Under this methodology, the delay impact is determined retrospectively.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
“For What It’s Worth”
October 21, 2024 —
Daniel Lund III - LexologyThe legal doctrine of quantum meruit is essentially referring to recovering “for what it’s worth,” incorporating the Latin phrase for “as much as one has deserved.”
Quantum meruit recovery occurs when there is no contract between parties for the particular item for which recovery is sought. Hence, quantum meruit recovery is generally a means of last resort to endeavor to make oneself whole.
So, it was for a subcontractor seeking nearly $14,000,000 for work it performed on a construction project in Portsmouth, New Hampshire. The subcontractor sued on contract as well as quantum meruit/unjust enrichment. The court initially dismissed the quantum meruit/unjust enrichment claims – because there was a contract claim – whereupon the contract claim was dismissed on summary judgment: the subcontractor failed to timely submit change proposals and, consequently, “lost contract remedies available to recover amounts it sought in the change proposals.”
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Colorado Requires Builders to Accommodate High-Efficiency Devices in New Homes
December 14, 2020 —
David M. McLain – Colorado Construction LitigationStarting in 2009, the Colorado Legislature began adding requirements that builders offer certain options to accommodate high-efficiency devices. These requirements started with solar prewire options in 2009, then water-smart home options in 2010. In 2020, the Legislature added requirements for electric vehicle charging and heating systems. These sections apply to unoccupied homes serving as sales inventory or a model home or manufactured homes, as defined by Colorado law. While the Legislature has only required builders to include options to accommodate these devices, it may be just a matter of time until builders must install the prescribed devices themselves.
In 2009, the Legislature passed C.R.S. 38-35.7-106, which was amended this year by HB 20-1155. As it now reads, Colorado law requires every builder of single-family detached residences to offer to have the home’s electrical or plumbing system, or both, include:
- A residential photovoltaic solar generation system or a residential thermal system, or both;
- Upgrades of wiring or plumbing, or both, planned by the builder to accommodate future installation of such systems; and
- A chase or conduit, or both, constructed to allow ease of future installation of the necessary wiring or plumbing for such systems.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & RoswellMr. McLain may be contacted at
mclain@hhmrlaw.com
Options When there is a Construction Lien on Your Property
June 02, 2016 —
David Adelstein – Florida Construction Legal UpdatesThere is a construction lien on my property. What are my best options? I hear this question quite a bit…so here it goes…
(1) Do nothing. That’s right – do nothing. If you are not looking to sell your house or refinance in the next year or so, you can do nothing and see whether the lienor files a construction lien foreclosure lawsuit. The lienor has one year from the recording of the lien to file the lawsuit.
(2) Record a
Notice of Contest of Lien. The
Notice of Contest of Lien shortens the lienor’s statue of limitations to foreclose on the lien from one year to 60 days. If the lienor fails to foreclose on the lien within 60 days, the lien is extinguished by operation of law. This is the route I tend to prefer. If the lienor is going to file a lien foreclosure lawsuit, I tend to think it is better forcing the issue on the front end as opposed to waiting a year. But every situation is different.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Gillotti v. Stewart (2017) 2017 WL 1488711 Rejects Liberty Mutual, Holding Once Again that the Right to Repair Act is the Exclusive Remedy for Construction Defect Claims
June 05, 2017 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. - Chapman Glucksman Dean Roeb & Barger BulletinBackground
In Gillotti v. Stewart (April 26, 2017) 2017 WL 1488711, which was ordered to be published on May 18, 2017, the defendant grading subcontractor added soil over tree roots to level the driveway on the plaintiff homeowner’s sloped lot. The homeowner sued the grading subcontractor under the California Right to Repair Act (Civil Code §§ 895, et seq.) claiming that the subcontractor’s work damaged the trees.
After the jury found the subcontractor was not negligent, the trial court entered judgment in favor of the subcontractor. The homeowner appealed, arguing that the trial court improperly construed the Right to Repair Act as barring a common law negligence theory against the subcontractor and erred in failing to follow Liberty Mutual Insurance Co. v. Brookfield Crystal Cove LLC (2013) 219 Cal.App.4th 98. The Third District Court of Appeal disagreed and affirmed the trial court’s judgment in favor of the subcontractor.
Impact
This is the second time the Third District Court of Appeal has held that Liberty Mutual (discussed below) was wrongly decided and held that the Right to Repair Act is the exclusive remedy for construction defect claims. The decision follows its holding in Elliott Homes, Inc. v. Superior Court (Hicks) (2016) 6 Cal.App.5th 333, in which the Court of Appeal held that the Right to Repair Act’s pre-litigation procedures apply when homeowners plead construction defect claims based on common law causes of action, as opposed to violations of the building standards set forth in the Right to Repair Act. Elliott is currently on hold at the California Supreme Court, pending the decision in McMillin Albany, LLC v. Superior Court (2015) 239 Cal.App.4th 1132, wherein Liberty Mutual was rejected for the first time by the Fifth District. CGDRB continues to follow developments regarding the much anticipated McMillin decision closely, as well as all related matters.
Discussion
The Right to Repair Act makes contractors and subcontractors not involved in home sales liable for construction defects only if the homeowner proves they negligently cause the violation in whole or part (Civil Code §§ 911(b), 936). As such, the trial court in Gillotti instructed the jury on negligence with respect to the grading subcontractor. The jury found that while the construction did violate some of the Right to Repair’s building standards alleged by the homeowner, the subcontractor was not negligent in anyway. After the jury verdict, the trial court found in favor of the grading subcontractor.
The homeowner moved for a judgment notwithstanding the verdict or a new trial on the grounds that the trial court improperly barred a common law negligence theory against the grading subcontractor. The trial court denied the motions on the grounds that “[t]he Right to Repair Act specifically provides that no other causes of action are allowed. See Civil Code § 943.” The trial court specifically noted that its decision conflicted with Liberty Mutual, in which the Fourth District Court of Appeal held that the Right to Repair Act does not eliminate common law rights and remedies where actual damage has occurred, stating that Liberty Mutual was wrongly decided and that the Liberty Mutual court was naïve in its assumptions regarding the legislative history of the Right to Repair Act.
In Gillotti, the Third District Court of Appeal stated that the Liberty Mutual court failed to analyze the language of Civil Code § 896, which “clearly and unequivocally expresses the legislative intent that the Act apply to all action seeking recovery of damages arising out of, or related to deficiencies in, residential construction, except as specifically set forth in the Act. The Act does not specifically except actions arising from actual damages. To the contrary, it authorizes recovery of damages, e.g., for ‘the reasonable cost of repairing and rectifying any damages resulting from the failure of the home to meet the standards....’ ([Civil Code] § 944).”
The Court also disagreed with Liberty Mutual’s view that because Civil Code §§ 931 and 943 acknowledge exceptions to the Right to Repair Act’s statutory remedies, the Act does not preclude common law claims for damages due to defects identified in the Act. The Court stated: “Neither list of exceptions, in section 943 or in section 931, includes common law causes of action such as negligence. If the Legislature had intended to make such a wide-ranging exception to the restrictive language of the first sentence of section 943, we would have expected it to do so expressly.”
Additionally, the Court of Appeal rejected the argument that Civil Code § 897 preserves a common law negligence claims for violation of standards not listed in Civil Code § 986. It explained that the section of Civil Code § 897, which provides, “The standards set forth in this chapter are intended to address every function or component of a structure,” expresses the legislative intent that the Right to Repair Act be all-encompassing. Anything inadvertently omitted is actionable under the Act if it causes damage. Any exceptions to the Act are made expressly through Civil Code §§ 931 and 934. The Court concluded in no uncertain terms that the Right to Repair Act precludes common law claims in cases for damages covered by the Act.
The homeowner further argued that she was not precluded from bringing a common law claim because a tree is not a “structure,” and therefore the alleged tree damage did not fall within the realm of the Right to Repair. The Court of Appeal also rejected this argument, holding that while the tree damage itself was not expressly covered, the act of adding soil to make the driveway level (which caused the damage) implicated the standards covered by the Right to Repair Act. The Court explained that since under the Act a “structure” includes “improvement located upon a lot or within a common area” (Civil Code § 895(a)), as the driveway was an improvement upon the lot, the claim was within the purview of the Right to Repair Act. As the soil, a component of the driveway, caused damage (to the trees), it was actionable under the Act.
Reprinted courtesy of
Richard H. Glucksman, Chapman Glucksman Dean Roeb & Barger and
Chelsea L. Zwart, Chapman Glucksman Dean Roeb & Barger
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Ms. Zwart may be contacted at czwart@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida Issues Emergency Fraud Prevention Rule to Protect Policyholders in Wake of Catastrophic Storms
November 05, 2024 —
Geoffrey B. Fehling & Olivia G. Bushman - Hunton Insurance Recovery BlogLast week, just before Hurricane Milton made landfall, Florida state officials issued an emergency decree to all licensed insurance adjusters in the state to protect homeowners against “unfair and deceptive acts” and “post-storm fraud” by insurance carriers. According to The Washington Post, the Florida Department of Financial Services is requiring that all claim adjusters provide an explanation for each change they make to a consumer’s loss estimate, document those changes, and retain all versions of the estimate and identify who made those revisions. When processing claims, adjusters must also use an electronic estimating system that provides an itemized report of all damage, as well as labor, materials, equipment and supplies. Those costs should be consistent with what a contractor or a repair company in that particular area would charge.
“Property damage from Hurricane Milton will be catastrophic and may result in billions of dollars in property losses,” the emergency rule states. “Fair and transparent loss estimates and claims adjustments will be crucial to ensure Floridians are properly and fairly compensated under the terms of their property insurance contracts, while also ensuring ongoing insurer solvency after potentially momentous financial losses.”
Reprinted courtesy of
Geoffrey B. Fehling, Hunton Andrews Kurth and
Olivia G. Bushman, Hunton Andrews Kurth
Mr. Fehling may be contacted at gfehling@HuntonAK.com
Ms. Bushman may be contacted at obushman@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Couple Gets $79,000 on $10 Million Construction Defect Claim
September 24, 2013 —
CDJ STAFFA Florida couple who sought more than $10 million in damages in a construction defect suit, has received a jury verdict of only $79,000. Leo and Kathryn Vecellio bought the 25,000 square-foot home in 2008, after which they discovered water intrusion issues. They sued both the builder and couple from whom they had bought the house.
Although the Vecellios spent more than $11 million to repair their home, the jury concluded that the builder did not know about the construction defects. The jury did determine that the builder, Dan E. Swanson, did either lie about or conceal certain facts about the construction. He was ordered to pay the $79,000 in damages to the Vecellios.
Lawyers for the defendants argued that the leaks were not from the original construction of the home, but were instead caused by the renovations made by the Vecellios. The Vecellios are pursuing whether they are entitled to money from home warranties. “There will be more evidence to be considered. I’m determined to see this through,” said Leo Vecellio.
Read the court decisionRead the full story...Reprinted courtesy of