Preserving your Rights to Secure Payment on Construction Projects (with Examples)
March 22, 2017 —
David Adelstein – Florida Construction Legal UpdatesAll participants across the construction industry should understand what efforts they should take to maximize and collateralize payment. No one wants to work for free and, certainly, no one in the construction industry wants to work without ensuring there is some mechanism to recover payment in the event they remain unpaid. Being proactive and knowledgeable can go a long way when it comes to recovering your money.
Your Contract – It starts with the contract. You should understand those risks that are allocated to you and those that are allocated to another party. And, you should understand the contractual mechanism to resolve claims and disputes and whether your contract has a prevailing party attorney’s fees provision. In addition to contractual rights, there are tools for you to maximize your collection efforts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at
dadelstein@gmail.com
Policing Those Subcontractors: It Might Take Extra Effort To Be An Additional Insured
June 14, 2011 —
Douglas Reiser, Builders Council BlogI just came across a case that I think truly paints the insurance dilemma for contractors. Thanks to this recent Illinois case, I don’t have to make up any factual scenarios—so kudos to Attorney Robert Boylan for posting it.
In reading over my RSS feeds this weekend, I noticed a great writeup on long-time blogger Josh Glazov’s Construction Law Today. Attorney Robert Boylan’s post describes a recent Illinois case where a general contractor was denied its additional insured status on a second-tier subcontractor’s insurance. The reason for the denial: the general contractor failed to procure an agreement in writing with the second-tier subcontractor, requiring it to be listed as an additional insured.
Read the full story…
Reprinted courtesy of Douglas Reiser of Reiser Legal LLC. Mr. Reiser can be contacted at info@reiserlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
You Can Take This Job and Shove It!
June 10, 2015 —
Garret Murai – California Construction Law BlogThat’s it.
You’ve had it.
They can take their job and shove it!
But can you really tell an owner on a construction project to proverbially shove it where the sun don’t shine?
Well, far be it for me to tread on your First Amendment Rights or stick my nose into the subsequently brought public disturbance charges against you. But can you legally tell an owner to shove it, and that you’re no longer going to perform work on their [insert expletive] project? Well, indeed you can, in limited circumstances, and it’s called a “Stop Work Notice.”
Note: A stop work notice is different from a stop payment notice.
What is a stop work notice?
A stop work notice is a notice given by a direct contractor to a project owner that the contractor will stop work if an amount owed to the contract is not paid within 10 days after notice is given.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
Emerging Trends in Shortened Statutes of Limitations and Statutes of Repose
January 02, 2024 —
Ivette Kincaid & Thomas McCarrick - Kahana FeldIntroduction
A growing trend in construction defect legislation around the country has seen the shortening of statutes of limitation and statutes of repose for a plaintiff to bring claims related to construction defects. Over the past ten years, several states, notably Florida and Texas, have shortened their statutes of repose. This is generally positive news for developers and contractors; however, the specifics and ramifications of these legislative and judicial updates are still unknown.
Statute of Limitations
A statute of limitations sets forth the time that a plaintiff has to sue or allege a particular cause of action against a defendant. These time limitations are codified into law and vary depending on the State and the cause of action. A statute of limitations starts at the occurrence of an injury or damage or at the time the injury or damage is discovered. The statute of limitations may be subject to some exceptions such as tolling for reasons such as the injured party being a minor in which case depending on the particular statute, the statute does not begin to run until after the minor reaches the age of majority.
Reprinted courtesy of
Ivette Kincaid, Kahana Feld and
Thomas McCarrick, Kahana Feld
Ms. Kincaid may be contacted at ikincaid@kahanafeld.com
Mr. McCarrick may be contacted at tmccarrick@kahanafeld.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Client Advisory: What The Recent Beacon Decision Means For Developers And General Contractors
August 20, 2014 —
Steven M. Cvitanovic and Whitney L. Stefko - Haight Brown & Bonesteel LLPOn July 3, 2014, the California Supreme Court (the “Court”) came out with its decision in Beacon Residential Community Association v. Skidmore, Owings & Merrill, et al. The Beacon decision settled a long-standing dispute in California about whether design professionals such as architects and engineers owe a duty to non-client third parties. In finding that the plaintiffs in Beacon could state a claim against the architects of the Beacon project, the Court also sowed the seeds of change in the way contracts are structured between developers, architects, engineers, and even general contractors.
So, how will Beacon change the landscape for developers and general contractors? It is important to understand the factual background in Beacon to predict how the decision may alter the playing field. For a detailed analysis of the Amicus briefs in the Beacon matter from the AIA, the CBIA, and the Consumer Attorneys of California, please click here.
The Beacon case arose from a common development model in California: a developer conceives a multi-unit project, maps the project as a condo development but rents as apartments. Shortly after completion of the Beacon project, the developer sold the entire project and the new owner finalized the existing condominium map and placed the units on the market as condominiums. Although the architects always knew they had designed a residential structure, the project ultimately became a condominium development. The newly formed homeowners’ association filed a construction defect suit against the developers, general contractor, the subcontractors and the architects for design and construction defects.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court Addresses Newly Amended Statute of Repose for Construction Claims
June 26, 2023 —
David R. Cook Jr. - Autry, Hall & Cook, LLPWe have been following the protracted legal battle concerning
Southern States Chemical, Inc. v. Tampa Tank & Welding, Inc. This case had been litigated at the Supreme Court and resulted in legislation. In the latest round, the Supreme Court answered whether Georgia’s statute of repose for construction claims applies to claims arising or brought before the statute was amendment in 2020.
What is a Georgia’s statute of repose? Under the statute, “[n]o action to recover damages: (1) For any deficiency in the survey or plat, planning, design, specifications, supervision or observation of construction, or construction of an improvement to real property; (2) For injury to property, real or personal, arising out of any such deficiency; or (3) For injury to the person or for wrongful death arising out of any such deficiency shall be brought against any person performing or furnishing the survey or plat, design, planning, supervision or observation of construction, or construction of such an improvement more than eight years after substantial completion of such an improvement.”
The case began ten years ago when Southern States suited Tampa Tank and Corrosion Control for alleged defects in renovating a 24-foot tall, 130-foot wide storage tank. The tank renovation was completed in 2002, and in 2011, the tank was found to leak sulfuric acid.
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook Jr., Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
Second Circuit Affirms Win for General Contractor on No Damages for Delay Provision
September 02, 2024 —
Bill Wilson - Construction Law ZoneIn NASDI, LLC v. Skanska Koch Inc. Kiewit Infrastructure Co. (JV), 2024 WL 1270188 (2d Cir. Mar. 26, 2024), the U.S. Court of Appeals for the Second Circuit affirmed the District Court’s grant of summary judgment dismissing a subcontractor’s delay claim against a general contractor on a public project in New York state. The Court enforced a typical no-damages-for-delay provision to bar the subcontractor’s breach of contract claim. The no-damages-for-delay provision in the subcontract at issue provided:
NO DAMAGE FOR DELAY. Except as otherwise provided …, Subcontractor agrees that it shall have no Claim against Contractor for any loss or damage it may sustain through delay, disruption, suspension, stoppage, interference, interruption, compression, or acceleration of Subcontractor’s Work (‘Delay Damages’) caused or directed by Contractor for any reason, and that all such Claims shall be fully compensated for by Contractor’s granting Subcontractor such time extensions as it is entitled to as a result of any of the foregoing.
Read the court decisionRead the full story...Reprinted courtesy of