Application of Set-Off When Determining Prevailing Party for Purposes of Attorney’s Fees
February 22, 2021 —
David Adelstein - Florida Construction Legal UpdatesThe recent opinion from the Second District Court of Appeal in Hayward Baker, Inc. v. Westfield Ins. Co., 2020 WL 7767859 (2nd DCA 2020) demonstrates that the significant issues test for determining the prevailing party for purposes of attorney’s fees applies to disputes involving payment bonds under Florida’s Lien Law (Florida Statutes Chapter 713). The
significant issues test is more or less a subjective test where the party that is deemed to have prevailed on the significant issues in the case is the prevailing party for purposes of attorney’s fees in the case. A trial court has discretion to determine the prevailing party which will not be disturbed absent an appellate court finding the trial court abused that discretion. This significant issues test is an important consideration so that parties understand just because money ends up going their way does not necessarily mean they prevailed on the significant issues in the case. It could mean that. But it may not based on the claims and moneys involved in the dispute.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Be Mindful Accepting Payment When Amounts Owed Are In Dispute
August 29, 2022 —
Nicholas Korst - Ahlers Cressman & Sleight PLLCAfter completing work on a project, or even during a project, it is not uncommon for some portion of the contract balance and/or a claim to be in dispute. As a contractor or subcontractor, it is important to be careful what is signed (or not signed) upon receipt of any payment both during and after completion of work on a project. One of the most common documents signed related to a receipt of payment is a lien/claim release document. This can be in the form of a conditional, unconditional, progress and/or final release. The language included in the release document is critically important, especially as it pertains to disputed amounts. As a contractor or subcontractor, if there are known disputes related to amounts owing, whether it be contract balance, disputed change order(s), a delay or inefficiency claim, or any other amounts believed to be owed, it is important to include language in the lien release that expressly carves out the disputed amounts. The same should be done for disputes related to extensions of time. This allows the contractor to accept the payment and release rights for the undisputed work, but continue to reserve its right to pursue the amounts in dispute later. If disputed amounts are not carved out, those amounts may effectively be waived and the subcontractor or contractor may lose all rights to recovery.
As a subcontractor in Alaska recently learned, there are potentially other ways a contractor may waive or lose its rights to recover amounts in dispute – without even signing a waiver or release document. In Smallwood Creek, Inc. v. Build Alaska General Contracting, LLC et al., the general contractor sent the subcontractor a check described as “final payment.” The subcontractor believed it was owed more than what the general contractor had sent and refused to accept the check. Months later, the subcontractor deposited the check. The subcontractor reversed course again and attempted to repay the general contractor the amount deposited. The general contractor refused, claiming the subcontractor’s acceptance of payment constituted satisfaction of all amounts owing to the subcontractor.
Read the court decisionRead the full story...Reprinted courtesy of
Nicholas Korst, Ahlers Cressman & Sleight PLLCMr. Korst may be contacted at
nicholas.korst@acslawyers.com
William Lyon to Acquire RSI Communities
February 22, 2018 —
Dave Suggs - CDJ STAFFAccording to the article “William Lyon Agrees to Buy RSI Communities $460 million deal plants Lyon in Texas and adds to Inland Empire land holdings” published on the website Builder, the Newport Beach home builder is purchasing the Southern California and Texas home builder. This will be Lyon Homes’ first venture in the state of Texas.
RSI Communities works within both San Antonio and Austin, Texas as well as Southern California and the Inland Empire. It was founded by Todd Palmaer, a home building expert and Ron Simon, a building products expert and Newport Beach businessman. First time home buyers have been RSI’s main target.
President and CEO of RSI, Tod Palmaer is optimistic about the acquisition “We are delighted to have our company join the William Lyon Homes organization. We have a great deal of confidence in the William Lyon Homes platform and its executive management team, and believe that its acquisition of RSI Communities will add to Lyon’s continued success in its current and new markets.”
Pat Donahue who has almost 30 years of experience in home building, will serve as President to the Inland Empire Division. John Bohnen, RSI’s present Chief Operating Officer, will be the regional president in Texas. Mr. Bohnen has previously held executive positions with numerous home builders. William Lyon’s president and CEO Mark R. Zaist is excited about adding RSI’s key players to their team, and had this to say about the purchase. “The acquisition of RSI represents our most significant acquisition since our entry into Portland and Seattle with the Polygon Northwest Homes acquisition in 2014 and furthers our strategy of building in the strongest markets in the Western U.S., while also strengthening our pipeline in Southern California, as we continue our mission of being the premier Western Regional home builder.”
Read the court decisionRead the full story...Reprinted courtesy of
Mich. AG Says Straits of Mackinac Tunnel Deal Unconstitutional
June 03, 2019 —
Jeff Yoders - Engineering News-RecordMichigan Attorney General Dana Nessel (D) has declared unconstitutional a late-2018 law that would create an authority to oversee construction of a key tunnel. The tunnel would house an oil-and-gas pipeline under the Straits of Mackinac.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Yoders, ENRMr. Yoders may be contacted at
yodersj@enr.com
Not So Fast, My Friend: Pacing and Concurrent Delay
April 25, 2022 —
William E. Underwood - ConsensusDocsWhen critical path activities are delayed by the owner (or another party), contractors will sometimes “pace,” or slow down, other activities to match the owner-caused delay. After all, why should the contractor hurry up and wait? But paced activities can often appear as concurrent delays on a project’s overall schedule. And all too often, contractors fail to contemporaneously document their efforts to pace work. Not only can this create avoidable disputes with owners and other contractors, but it can also create future roadblocks to the recovery of delay damages. This article examines the interplay between pacing and concurrent delay[1] and what contractors should do to minimize risk and preserve their rights to obtain more than a simple time extension for project delays.
Pacing versus Concurrent Delay
As a basic matter, most contracts allocate responsibility/liability for a schedule delay to the party that caused the delay. For example, if an owner is contractually required to provide equipment for a contractor to install, then the owner likely bears responsibility for any delays caused if the equipment is delivered late. If, however, the contractor was also behind schedule on other activities during this time and the project would have been delayed regardless of the owner’s late deliveries, then the delay is probably concurrent. And the contractor will generally be entitled to only an extension of time, and no other monetary relief.
Read the court decisionRead the full story...Reprinted courtesy of
William E. Underwood, Jones Walker LLP (ConsensusDocs)Mr. Underwood may be contacted at
wunderwood@joneswalker.com
Orange County Home Builder Dead at 93
April 25, 2012 —
CDJ STAFFRandall E. Presley was a homebuilder in Southern California for more than thirty years, acting as head of Presley Development Company from 1956 until selling the firm to Lyon Homes in 1987. The two companies merged in 1991 as the Presley Cos. Mr. Presley saw the need in the 1950s to provide people in Southern California with low- to medium-priced quality homes.
His firm built more than 160 communities and was among the ten largest homebuilding firms in the country, expanding beyond California. Mr. Presley was 93 when he succumbed to pneumonia. He is survived by a wife, three children, seven grandchildren, and 11 great-grandchildren.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Vermont Supreme Court Reverses, Finding No Coverage for Collapse
May 18, 2020 —
Tred R. Eyerly - Insurance Law HawaiiThe Vermont Supreme Court reversed the trial court's decision for collapse coverage. Commercial Constr. Endeavors, Inc. v. Ohio Sec. Ins. Co., 2019 Vt. LEXIS 173 (Vt. Sup. Ct. Dec. 13,2019).
Commercial Construction Endeavors, Inc. (CCE) built a livestock barn. By late December 2014, the barn was partially complete, with the foundation laid, wood framing erected, and roof trusses installed. In late December, strong winds caused the structure to collapse. CCE started clearing debris and rebuilding the barn, incurring additional labor and material costs.
CCE reported the collapse to Ohio Security. The policy covered loss to "Covered Property." Ohio Security determined that the loss was covered for "Off-Premises Property Damage Including Care, Custody or Control." This endorsement provided coverage for damage to real property upon which CCE was performing operations where the damage resulted from those operations. Ohio Security paid CCE $24,750, the full amount available under the endorsement, less a $250 deductible.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
How Are You Dealing with Material Delays / Supply Chain Impacts?
June 07, 2021 —
David Adelstein - Florida Construction Legal UpdatesIn a prior article I discussed a material escalation provision in your construction contract to account for the volatility of the material price market. While including such a provision may not have been much of a forethought before, it is now!
What about concerns with the actual supply chain that impacts the availability of and the lead time of materials? How are you addressing this concern in your construction contract?
The pandemic has raised awareness to this issue as certain material availability has been impacted by the pandemic. As a result, parties in construction have tried to forecast those materials where delivery issues may occur including those materials with longer than expected lead times. But equally important is how this issue is being addressed in your construction contract including how you want to negotiate this risk in future construction contracts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com