Why Insurers and Their Attorneys Need to Pay Close Attention to Their Discovery Burden in Washington
March 28, 2018 —
Neal Philip – Insurance Law BlogAs previously reported in this blog, Washington case law generally affords insureds a broad right to the discovery of claim file materials, including information that should be protected from disclosure by attorney/client privilege or the work product doctrine.
Cedell v. Farmers Ins. Co. of Washington, 176 Wn.2d 686, 295 P. 3d 239 (2013). The discovery pitfalls created by
Cedell were on full display in a recent Western District of Washington decision that granted an insured’s motion to compel production of work product and attorney/client communications from an insurer’s claims file.
Westridge Townhomes Owners Ass’n v. Great American Assur. Co., 2018 U.S. Dist. LEXIS 27960 (W.D. Wash. February 21, 2018)
The background facts are somewhat unclear, but it appears that the insured in this case made a claim for coverage under two insurance policies and there was an allegedly inadequate response from the insurers. The insured sued its insurers for coverage in 2016 before the insurers issued a declination of coverage letter. The two insurers retained the same attorney to represent them, and that attorney subsequently wrote a declination letter on behalf of the insurers, which was sent to the insured on April 12, 2017. The insured ultimately sought production of the entire claim file, which had not been split between the claim investigation and the coverage litigation. The insurers argued, among other things, that the insured was not entitled to anything after the litigation commenced in 2016 on work product grounds, and certainly was not entitled to communications with their attorney.
Read the court decisionRead the full story...Reprinted courtesy of
Neal Philip, Gordon, Reese, Scully, & MansukhaniMr. Philip may be contacted at
nphilip@grsm.com
Burlingame Construction Defect Case Heading to Trial
December 30, 2013 —
CDJ STAFFA condominium association in the Aspen, Colorado area will likely go to trial over its claims of construction defects, reports Aspen Daily News Online. According to the suit, siding and trim were improperly manufactured and installed. The homeowners engaged experts to determine the appropriate remedy, and then sought bids from contractors. Shaw Construction, which built the condos, responded with a counteroffer. Chris Rhody, the lawyer for the homeowners, said there was “a big difference” between the association’s request and the builder’s counteroffer.
According to Mr. Rhody, settlement is still possible, but seems unlikely. A date for the trial is yet to be set.
Read the court decisionRead the full story...Reprinted courtesy of
Maximizing Contractual Indemnity Rights: Components of an Effective Provision
December 02, 2015 —
William Kennedy – White and Williams LLPTort law is aimed at providing compensation to the victims of negligence. Tort law encourages plaintiffs to cast a wide net, pursuing claims or suits against not only those whose fault seems manifestly primary, but also against defendants whose causal exposure is minimal, against those whose exposure is purely by operation of law. As discussed in the first installment of this series, "Maximizing Contractual Indemnity: Problems with Common Law," three common law principles – vicarious liability, joint and several liability, and common law indemnity – cause some parties to pay in excess of their actual degree of causal fault. Contractual indemnity can remedy that harsh result.
Part Two: Components of an Effective Provision
Properly composed, “broad form” contractual indemnity provisions permit an Indemnitee to shift the full range of financial consequences from tort exposure, including civil damages, defense fees, expert fees, and litigation expenses. Such contracts permit indemnity even where the underlying damage was incurred due to a degree of negligence or fault on the part of the Indemnitee. Such contracts can also allow an Indemnitee to shift to the Indemnitor the risk of loss for someone from whom the Indemnitor would otherwise be immune from suit (e.g., the Indemnitor’s employees). A well-written contract can even convert an entity which is an Indemnitor as to one party (e.g., a general contractor which has to indemnify a property owner) into an Indemnitee as to another party (e.g., a subcontractor) for the very same risk.
Read the court decisionRead the full story...Reprinted courtesy of
William Kennedy, White and Williams LLPMr. Kennedy may be contacted at
kennedyw@whiteandwilliams.com
Don’t Kick the Claim Until the End of the Project: Timely Give Notice and Preserve Your Claims on Construction Projects
December 10, 2015 —
Christopher G. Hill – Construction Law MusingsFor this week’s Guest Post Friday, we welcome
Tara L. Chadbourn. Tara is an attorney with
ReavesColey PLLC in Chesapeake, VA, where she concentrates her practice on construction law, litigation and commercial litigation. Tara counsels owners, contractors, subcontractors and materials suppliers in various government and commercial construction matters. Tara can be reached at tara.chadbourn@reavescoley.com.
You may have experienced and have certainly heard of the scenario in which a contractor waits to address a claim as part of project closeout, only to realize the applicable deadline has already passed. While there may have been discussions about claims during the course of the project, contractors cannot rely upon oral conversations about outstanding claims. Instead, contractors must be vigilant in satisfying notice requirements and preserving claims. While entitlement must still be proven, a contractor’s chances of recovery increase greatly if the contractor abides by notice requirements and consciously preserves claims in the following ways.
Contractors Must Acquaint Themselves with Contractual Notice Provisions:
Many prime and subcontract agreements contain stringent notice provisions that require the contractor to give notice within a certain time period or else the claim is expressly waived. The deadline for notice is often only a few days after the occurrence giving rise to the claim or the contractor becoming aware of the claim. To avoid waiver, contractors must carefully review their contracts for provisions requiring notice of a claims for adjustment for a variety of situations to include unforeseen site conditions, trade sequencing changes, project delay or scope of work changes.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
The (Jurisdictional) Rebranding of The CDA’s Sum Certain Requirement
April 15, 2024 —
Jordan A. Hutcheson and Stephanie Rolfsness - Watt TiederThe Contract Disputes Act (the “CDA”), 41 U.S.C.A. §§ 7101 et seq., which has provided the statutory framework for resolution of most contract disputes between the federal government and its contractors since 1978, has recently been the subject of changes in judicial interpretation, despite no corresponding statutory changes. The CDA’s implementing provisions in the Federal Acquisition Regulations (FAR), require that contractors submit a claim to the government in the form of written demand to a contracting officer requesting a final decision and seeking the payment of money in a sum certain prior to pursuing resolution via board or court. However, with respect to the sum certain requirement, the United States Court of Appeals for the Federal Circuit issued an opinion in late 2023 determining that this requirement “should not be given the jurisdictional brand” as it has categorically received in the past. Rather, the court concluded that the sum certain requirement is merely an element of a claim for relief under the CDA that a contractor must satisfy to recover. This rebranding does not debase the sum certain requirement, but it does indicate a renewed focus on what constitutes “jurisdictional” in government contracts litigation.
Reprinted courtesy of
Jordan A. Hutcheson, Watt Tieder and
Stephanie Rolfsness, Watt Tieder
Ms. Hutcheson may be contacted at jhutcheson@watttieder.com
Ms. Rolfsness may be contacted at srolfsness@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
The Condo Conundrum: 10 Reasons Why There's a 'For Sale' Shortage in Seattle
December 20, 2017 —
Dave Suggs - CDJ STAFFSeattle Washington is experiencing a shortage of in-city condos. Of the 27,000 units of new housing being built in downtown Seattle, 94 percent will be rentals. As housing prices are rising in the US’s fastest-growing large city, the median home price is $660,000. Dean Jones of the Seattle Magazine reports on why consumers consider condos, but home developers don’t in his article “The Condo Conundrum: 10 Reasons Why There's a 'For Sale' Shortage in Seattle.”
Reason 1, condominiums don’t always offer high returns and can be riskier for the home developer. Reason 2, the Washington State Condo Act “overprotects” buyers of condos with over-the-top warranties that makes everyone in the industry afraid to work with condos. Reason 3, the cost of condo building is increased because of the risk of defect litigation. Reason 4, condo presale buyers are not required to deposit a percentage to invest in a new development and before closing could decide to walk away. Reason 5, there is a lot of interest in apartment buildings from investment groups.
Reason 6, investors whose goal is to own “trophy” assets in rising markets can’t wait the years it takes developers to plan and construct a new multistory community. Reason 7, since rent prices have risen 50 percent on average in the last 7 years, it’s profitable to be a landlord. Reason 8, the millennials who live and work in this tech oriented region prefer to rent because of living through the rise and fall of the housing market. Reason 9, the costs is rising each year to deliver new projects. Reason 10, high-rise zoning was adopted 2 years before the recession, so just as condo development was gearing up, apartment building took over.
Read the court decisionRead the full story...Reprinted courtesy of
New OSHA Rule Creates Electronic Reporting Requirement
June 22, 2016 —
John K. Baker & Kevin Conrad – White and Williams LLPThe United States Occupational Safety and Health Administration (OSHA) issued a
Final Rule revising portions of its Recording and Reporting Occupational Injuries and Illnesses regulations (Recording and Reporting Regulations). The revisions take effect August 10, 2016.
Employers subject to the new requirements have until July 1, 2017 to submit electronically the required information for calendar year 2016. OSHA will make electronically-submitted workplace-safety data for each reporting employer available publicly in an online database.
Reprinted courtesy of
John K. Baker, White and Williams LLP and
Kevin Conrad, White and Williams LLP
Mr. Baker may be contacted at bakerj@whiteandwilliams.com
Mr. Conrad may be contacted at conradk@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Non-compliance With Endorsement Means No Indemnity Coverage
January 15, 2019 —
Tred R. Eyerly - Insurance Law HawaiiThe insured's failure to verify that subcontractors had CGL policies and to provide a contract stating that the subcontractors would indemnify the insured as required by the policy's endorsement meant there was no coverage for the insured. Cincinnati Spec. Underwriters Ins. Co. v. Milionis Constr., Inc., 2018 U.S. Dist. LEXIS 199658 (E.D. Wash. Nov. 26, 2018).
The homeowners filed suit against Milionis, the general contractor for construction of a home. The underlying suit alleged that Milionis breached the parties' agreement by leaving the home unfinished. Cincinnati defended Milionis under a reservation of rights.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com