Practical Pointers for Change Orders on Commercial Construction Contracts
December 31, 2014 —
John E. Bowerbank - Newmeyer & DillionConstruction projects pose unique challenges, including keeping costs within budget, meeting project deadlines, and coordinating the work of numerous contractors and subcontractors in the wake of inevitable design revisions and changes to the plans. Anticipating potential project challenges and negotiating contract provisions before commencing work on a project is critical for all parties. Careful planning should reduce the number of contract disputes. This, in turn, can facilitate the completion of a project within budget and on schedule.
“Changes” Clauses in Construction Contracts
Most commercial construction contracts have a clause addressing changes to the contract. A “changes” clause typically requires the mutual agreement of the parties on the scope of any modifications to the contract, as well as the effect on the contract price and timeframe for the work to be performed. This results in what is generally referred to as a “change order.” Many projects have a large number of change orders, which can result in significant cost overruns and delays to the project if the contract contains a complicated change order process. Therefore, in order to minimize cost overruns and project delays, it is crucial to keep the change order process as simplified and streamlined as possible.
In the most basic terms, change orders memorialize modifications to the original contract, and typically alter the contract's price, scope of work, and/or completion dates. A typical change order is a written document prepared by the owner or its design professional, and signed by the owner, design professional, and affected contractors and subcontractors. An executed change order indicates the parties’ agreement as to what changes are taking place, including approval for additional costs and schedule impacts.
While the reasons for change orders and the parties initiating them may vary, all change orders have one feature in common. Effective change orders alter the original contract and become part of the contract. Therefore, from a legal standpoint, change orders must be approached with the same caution and forethought as the original contract.
Practice Pointers for Change Orders
In light of the foregoing, some practice pointers for change orders in commercial construction contracts are as follows:
- Carefully Negotiate and Draft Change Order Provisions in the Original Contract.
A carefully negotiated and drafted “changes” clause that accounts for “unexpected circumstances” or “hidden conditions” can protect the parties from downstream costly disputes.
- Immediately Address Changes by Following the Change Order Process, Including Obtaining Necessary Signatures.
Regardless if you are an owner, general contractor or subcontractor, you should address any proposed change order immediately. Even if a decision maker gives “verbal” approval to go ahead with changed work, the work should not proceed without following the change order process in the original contract. This includes making sure to obtain any necessary signatures for the change order, if at all possible.
- Analyze the Plans and Specifications to Determine Whether “Changes” are Within the Scope of the Original Contract, or Whether They are Extra Work.
Prior to entering an original contract, it is imperative that the parties review the plans and specifications for ambiguities regarding work included in the original contract, versus potential extra work that would require a change order. This is important because a careful review of the plans and specifications sometimes reveals that work believed to be a change order is, in fact, original work, or vice versa.
- Make Sure Requests and Approvals for Change Orders are Done by an Authorized Representative.
When a party requests or gives its approval to a change order, it is important to confirm the request or approval came from an authorized representative.
- Avoid Vague and Open-Ended Change Orders.
Indeed, the vaguer a change order, the more likely it can lead to a dispute. Vague and open-ended change orders, including change orders that provide for payment on a time and materials basis, can be difficult for an owner to budget and schedule. This can lead to disputes as to cost and/or time extensions.
- Oral Assurances for Payment Without a Signed Change Order May Not Be Recoverable.
When a party provides verbal assurances to another party for extra work without following the change order process, there is a much higher likelihood that disputes will occur. Although there is case law that may allow a contractor to recover for extra work in private contracts based on oral promises, the parties should avoid placing themselves in such a legal position. Notably, in public contracts, a contractor may not be able to recover for any extra work without a signed changed order, even with verbal assurances of payment from the owner.
About the Author:
John E. Bowerbank, Newmeyer & Dillion
Mr. Bowerbank is a partner in the Newport Beach office and practices in the areas of business, insurance, real estate, and construction litigation. You can reach John at john.bowerbank@ndlf.com
Read the court decisionRead the full story...Reprinted courtesy of
SB 721 – California Multi-Family Buildings New Require Inspections of “EEEs”
December 19, 2018 —
Brenda Radmacher - Gordon & Rees Construction Law BlogMany in the construction industry and multi-family development field have been closely following Senate Bill 721, or the “Balcony Bill,” regarding new requirements for building owners associated with decks and balconies. After almost a dozen amendments, the “Balcony Bill” finally passed in the state legislature with an overwhelming majority and was signed into law September 17th, 2018, by Governor Jerry Brown.
Balconies and decks, called “Exterior Elevated Elements” (“EEE”) in the statute, are common features in most multi-family buildings in California – where better to enjoy the California sun? However, many of the structures have proven to be problematic at best due to complex intersections of construction trades and design issues as well as limited understanding and effectuation of maintenance. Indeed, the “Balcony Bill” arose largely out of an outcry following the 2015 balcony collapse in Berkeley in 2015, which left six young people dead and another seven injured.
Read the court decisionRead the full story...Reprinted courtesy of
Brenda Radmacher, Gordon & Rees Scully MansukhaniMs. Radmacher may be contacted at
bradmacher@grsm.com
Potential Construction Liabilities Contractors Need to Know
September 21, 2020 —
Manipal Dhariwal - Construction ExecutiveThe outbreak of COVID-19 started in early December 2019, gradually expanding to the other countries of the world. The spread of the pandemic did not just affect the world in terms of health, but also made industries suffer across all verticals—leading to a few unique challenges for construction contractors.
From financial imbalance to trouble retaining cash flow, the circumstances have turned to be completely unfavorable for the contractors that rely on banks for essential surety credits to sustain. To prevent loss of liquidity, the contractors are leaning toward construction accounting software and other technology to keep their accounting data in place and avoid risks with project deliveries.
But still, there are many other factors that must be considered to maintain cash flow for potential credit availability such as debt agreements and lines of credit, which involve financing of equipment and vehicles.
Nevertheless, it is completely the responsibility of the contractors to stick with the guidelines related to the line of credit and debt agreements which in most cases are covenant ratios.
Reprinted courtesy of
Manipal Dhariwal, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Revamp to Nationwide Permits Impacting Oil and Gas Pipeline, Utility and Telecom Line Work
March 29, 2021 —
Alex P. Prochaska, Jones Walker LLP - ConsensusDocsTo avoid delay costs and penalties, contractors involved in pipeline and utilities construction maintenance, repair and removal need to understand how the 43 year old Nationwide Permit (NWP) regime has changed specific to the NWP 12 and what is now required for compliance. This change is important for contractors who construct, maintain, or repair pipelines that cross or impact waters of the United States, including wetlands. NWPs are a useful tool to streamline construction of a pipeline project, but it is important for contractors to know when certain terms and conditions still apply to the particular NWP and those that have been eliminated.
On January 13, 2021, the United States Army Corps of Engineers (the Corps) published a final rule that reissued and modified twelve existing NWPs and issued four new NWPs that will take effect on March 15, 2021.1 The remaining 40 NWPs that were not reissued or modified under this rule will continue under the general conditions and definitions of the January 6, 2017 final rule.
Read the court decisionRead the full story...Reprinted courtesy of
Alex P. Prochaska, Jones Walker LLPMr. Prochaska may be contacted at
aprochaska@joneswalker.com
Colorado House Bill 1279 Stalls over 120-day Unit Owner Election Period
April 20, 2017 —
Luke Mecklenburg - Snell & Wilmer Real Estate Litigation BlogWith the session more than halfway through, the Colorado Legislature’s 2017 attempts at meaningful construction defect reform may fail again. This year, the Legislature did not attempt a single-bill construction defect overhaul like those that have failed over the last half-decade. Rather, it has sought to enact reforms on a piecemeal basis, with several smaller bills addressing specific issues that have been affecting condominium construction along Colorado’s booming Front Range.
This new approach appears to be headed towards much the same outcome as the failed efforts of the past. House Bill 1169 would have given developers a statutory right to repair before being sued by homeowners, and Senate Bill 156 would mandate arbitration or mediation. Both have been assigned to the House State, Veterans, and Military Affairs Committee (often viewed as the “bill-kill committee”), and have little chance of being resuscitated this session.
This was also the fate of House Bill 1279, but bipartisan support had many believing that it still had a chance of passing—at least until last week. House Bill 1279 would require an executive board of a homeowners association to satisfy several prerequisites before suing a developer or builder, namely to (1) notify all unit owners and the developer or builder against whom the lawsuit is being considered; (2) call an association meeting where the builder or developer could present relevant facts and arguments; and (3) get approval from the majority of the unit owners after providing detailed disclosures about the lawsuit, including the potential costs and benefits thereof.
Read the court decisionRead the full story...Reprinted courtesy of
Luke Mecklenburg, Snell & WilmerMr. Mecklenburg may be contacted at
lmecklenburg@swlaw.com
Contractor Owed a Defense
November 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe Illinois Appellate Court reversed the lower court and found that the insured contractor was entitled to a defense for alleged construction defects. Acuity v. M/I Homes of Chicago, LLC, 2022 Ill. App. LEXIS 393 (Ill. Ct. App. Sept. 9, 2022).
The owners association (AOAO) sued M/I Homes for breach of contract and the implied warranty of habitability due to alleged defects. The AOAO alleged that the defects caused physical injury to the townhomes. There was resulting property damage such as damage to other building materials, windows and patio doors, and water damage to the interior of units. M/I Homes requested a defense from Acuity, but the request was denied.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Former UN General Assembly President Charged in Bribe Scheme
October 21, 2015 —
Patricia Hurtado & Greg Farrell – BloombergA former president of the United Nations General Assembly and a billionaire Macau developer were accused of taking part in a four-year corruption scheme that included bribes to help fund a campaign for the post at the organization in exchange for the promotion of Chinese businesses.
John Ashe, president of the UN General Assembly from September 2013 to September 2014, accepted more than $1 million in payoffs from developer Ng Lap Seng and an associate to help persuade the international body to build a multibillion-dollar conference center in Macau and promote Chinese businesses, including a bank, in Antigua, according to the U.S.
The new charges, announced Tuesday, relate to an earlier case against Ng, 68, who has a personal net worth of about $1.8 billion. He’s been held in a federal jail in Manhattan since he was arrested Sept. 19, accused of bringing $4.5 million into the country and lying about its purpose to U.S. authorities.
Reprinted courtesy of
Patricia Hurtado, Bloomberg and
Greg Farrell, Bloomberg
Read the court decisionRead the full story...Reprinted courtesy of
Court of Appeal Shines Light on Collusive Settlement Agreements
October 21, 2015 —
Kristian B. Moriarty & R. Bryan Martin – Haight Brown & Bonesteel LLPIn Diamond v. Reshko, (filed 8/20/2015, No. A139251) the California Court of Appeal, First District, held that a defendant was entitled to introduce evidence at trial reflecting amounts paid by co-defendants in settlement of a plaintiff’s claim.
Plaintiff, Christine Diamond, was injured during an automobile accident that occurred while she was a passenger in a taxi driven by Amir Mansouri. Christine, and her husband Andrew, filed suit against Mr. Mansouri, the Yellow Cab Collective (“Yellow Cab”), and the driver of the vehicle that collided with the taxi, Serge Reshko. Before trial, Mansouri and the Yellow Cab Collective settled with Plaintiffs, but agreed to appear and participate as defendants at the jury trial of the action. Mansouri and Yellow Cab paid a total of $400,000 to Plaintiffs in settlement.
Reshko filed a pre-trial motion seeking an order permitting Reshko to admit evidence of the settlement between Plaintiffs and the other defendants. The trial court refused to rule on the motion before trial. Ultimately, evidence of the settlement between Plaintiffs, Mansouri and Yellow Cab was excluded during trial. The jury returned a verdict in favor of Plaintiffs in the total amount of $745,778, finding Mansouri 40 percent at fault, and Reshko 60 percent at fault. The Trial Court entered judgment against Reshko in the sum of $406,698.
Reshko appealed the judgment. The First District Court of Appeal reversed, holding that evidence of the settlement should have been admitted at trial because the settling defendant’s position should be revealed to the court and jury to avoid committing a fraud on the court, and in order to permit the trier of fact to properly weigh the settling defendant’s testimony.
Reprinted courtesy of
Kristian B. Moriarty, Haight Brown & Bonesteel LLP and
R. Bryan Martin, Haight Brown & Bonesteel LLP
Mr. Moriarty may be contacted at kmoriarty@hbblaw.com
Mr. Martin may be contacted at bmartin@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of