“Wait! Do You Have All Your Ducks in a Row?” Filing of a Certificate of Merit in Conjunction With a Complaint
January 13, 2020 —
Rahul Gogineni - The Subrogation StrategistIn Barrett v. Berry Contr. L.P., No. 13-18-00498-CV, 2019 Tex. LEXIS 8811, the Thirteenth District Court of Appeals of Texas considered, among other things, the procedural timing requirements of filing a certificate of merit in conjunction with a complaint. The court concluded that the proper reading of the statute requires a plaintiff to file a certificate of merit with the first complaint naming the defendant as a party.
In Barrett, after sustaining injuries while working at a refinery, David Barrett (Barrett) filed suit against Berry Contracting, LP and Elite Piping & Civil, Ltd. on July 6, 2016. In Barrett’s first amended complaint, which he filed on August 23, 2016, Barrett added Govind Development, LLC (Govind) as another defendant. Barrett subsequently filed a second amended complaint (omitting Govind) and, on December 27, 2017, shortly before the statute of limitations ran, a third amended complaint (reasserting claims against Govind). On January 28, 2018, after the statute of limitations period ran, Barrett filed a certificate of merit. Govind filed a motion to dismiss the claim, asserting that Barrett violated the statute that required a certificate of merit to be filed with the complaint, Tex. Civ. Prac & Rem. Code §150.002.
Tex. Civ. Prac. & Rem. Code §150.002(a) states,
In any action or arbitration proceeding for damages arising out of the provision of professional services by a licensed or registered professional, a claimant shall be required to file with the complaint an affidavit of a third-party licensed architect, licensed professional engineer, registered landscape architect or registered professional land surveyor…
Read the court decisionRead the full story...Reprinted courtesy of
Rahul Gogineni, White and Williams LLPMr. Gogineni may be contacted at
goginenir@whiteandwilliams.com
Motion for Reconsideration Challenging Appraisal Determining Cause of Loss Denied
November 16, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court rejected the insurer's motion for reconsideration attempting to set aside the appraisal award that determined the cause of loss. Mesco Mfg., LLC v. Motorists Mut. Ins. Co., 2023 WL 5334659 (S.D. Ind. Aug. 18, 2023).
Mesco suffered a loss to the roofs of its facilities due to hail damage. Mesco sued Motorists alleging it breached the policy by failing to pay the full amount of the claim. The claim went to appraisal. The policy's appraisal provision reserved Motorists' right to deny the claim despite an appraisal going forward. The appraisal award noted that the loss was caused by hail.
Cross-motions for summary judgment were filed. The court found that Motorists had breached the policy by failing to pay the arbitration award and granted summary judgment to the insured. The "right to deny" clause did not give Motorists the unfetterd right to disregard the umpire's award if it disgreed about the amount of loss caused by hail. The only dispute was whether the damage was caused by hail, and the umpire found that it was.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
2018 Super Lawyers and Rising Stars!
July 18, 2018 —
Wilke, Fleury, Hoffelt, Gould & Birney, LLPWilke Fleury is thrilled to announce our 2018 Super Lawyers and Rising Stars! Twelve of our talented attorneys have been honored with the Super Lawyers and Rising Stars distinctions.
Super Lawyers® is a service of the Thomson Reuters, Legal Division. Each year, the research team at Super Lawyers® undertakes a rigorous multi-phase selection process that includes a statewide survey of lawyers, independent evaluation of candidates by the attorney-led research staff, a peer review of candidates by practice area and a good-standing and disciplinary check. The Super Lawyers list represents only five percent of lawyers in California and Rising Stars reflects 2.5% of the state’s up-and-coming lawyers.
Congratulations to Wilke Fleury’s 2018 Super Lawyers and Rising Stars!
Read the court decisionRead the full story...Reprinted courtesy of
Wilke, Fleury, Hoffelt, Gould & Birney, LLP
A Vision and Strategy for the Adoption of Open International Standards
November 18, 2019 —
Aarni Heiskanen - AEC BusinessThe final report of RASTI is now available in English. The project outlined a national vision and strategy for the adoption of open international standards in the real estate and construction industries. The Finnish version includes several appendices.
One of the frameworks that RASTI devised was a built environment life-cycle process map. It is derived from the model of Antti Autio of the Ministry of the Environment.
The map presents the processes of the four “lanes”: the customer’s/users value creation processes, public sector processes, information work, and production. Ideally, data and information flow across the processes, using open standards.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
New York Developer gets Reprieve in Leasehold Battle
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to The Real Deal, a “Manhattan Supreme Court judge granted an injunction in favor of Tribeca Mews developer Thurcon Properties, which is fighting to keep the leasehold on several adjacent parcels in connection with a certificate of occupancy.”
In 2013, Thurcon Properties was sued by the condo board, who claimed “the certificate of occupancy was pushed back at the building due to a number of construction defects.” The Real Deal further reported that the condo board “claimed the developers sold about 10 units to an outside buyer, and took some of the proceeds for themselves.”
Recently, a judge “ordered Feldman Heritage, owner of the ground lease at 125 Church and several adjacent sites, to appear in court on April 30,” because he wants the lease owner “to show why Thurcon should not be given the chance to cure the alleged lease default.”
Read the court decisionRead the full story...Reprinted courtesy of
Delays Caused When Government (Owner) Pushes Contractor’s Work Into Rainy / Adverse Weather Season
January 13, 2020 —
David Adelstein - Florida Construction Legal UpdatesThere are a number of horizontal construction projects where a contractor’s sequence of work and schedule is predicated on avoiding the rainy season (or certain force majeure events). The reason is that the rainy season will result in delays due to the inability to work (and work efficiently) during the adverse weather (including flooding caused by the weather). If the work is pushed into the rainy season, is such delay compensable if the government (or owner) delayed the project that pushed work out into the rainy season? It very well can be.
For example, in Meridian Engineering Co. v. U.S., 2019 WL 4594233 (Fed. Cl. 2019), a contractor was hired by the Army Corps of Engineers to construct a flood control project for a channel in Arizona. Due to delays, including those caused by the government, the project was pushed into the monsoon season, which caused additional delays largely due to flooding caused by the heavy rain. One issue was whether such delays were compensable to the contractor – the government raised the argument that the contractor assumed the risk of potential flooding from the rainy season. The Court found this argument unconvincing:
[The contractor’s] initial construction schedule planned for a completion of the channel invert work, a necessary step in protecting the site from flooding, to be completed by late June 2008…[M]any issues arose in the project’s early stages that led to cumulative substantial delay, including those caused by the government’s failure….The government cannot now claim that [the contractor] assumed the risk of flooding from monsoon season when the government was largely responsible for [the contractor’s] inability to complete the project prior to the beginning of the monsoon season. Simply put, the government cannot escape liability for flood damages when the government is responsible for causing the contractor to be working during the flood-prone season.
Meridian Engineering, 2019 WL at *7 (internal citations omitted)
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Traub Lieberman Partner Michael K. Kiernan and Associate Brandon Christian Obtain Dismissal with Prejudice in Favor of Defendant
November 27, 2023 —
Michael K. Kiernan & Brandon Christian - Traub LiebermanIn a 14-count breach of contract action brought in the Fifteenth Judicial Circuit in Palm Beach County, Florida, Partner Michael K. Kiernan and Associate Brandon Christian obtained dismissal with prejudice in favor of Defendant St. Joseph’s Episcopal Church of Boynton Beach, Florida (“Church”).
Plaintiffs, St. Joseph’s Episcopal School (“School”) and its benefactor, William Swaney, filed suit to enforce an alleged 99-year oral lease agreement which Swaney asserted had been made to him by a prior rector of the Church in exchange for his contributions to the School. Plaintiffs also sought emergency injunctive relief to allow the School to continue to operate on Church property. The Church maintained in part that the only lease in effect was a written lease, approved by the Church Vestry and the Diocese of Southeast Florida, and which the Church Vestry unanimously voted not to renew in 2022.
Reprinted courtesy of
Michael K. Kiernan, Traub Lieberman and
Brandon Christian, Traub Lieberman
Mr. Kiernan may be contacted at mkiernan@tlsslaw.com
Mr. Christian may be contacted at bchristian@tlsslaw.com
Read the court decisionRead the full story...Reprinted courtesy of
U.S. Supreme Court Allows Climate Change Lawsuits to Proceed in State Court
May 01, 2023 —
George Leahy - Lewis BrisboisWashington, D.C. (April 25, 2023) - On Monday, April 24, the U.S. Supreme Court refused to hear appeals by several major energy companies that sought to remove lawsuits filed by state and local governments from state court into federal court. The Court’s
certiorari denials reject companies’ appeals in five separate cases, which involved claims brought by municipalities in Colorado, Maryland, California, Hawaii, and Rhode Island. Each municipality claims that it has been harmed by the effects of climate change, allegedly attributed to the companies’ carbon emissions.
The Court’s denials effectively allow the lawsuits to continue in state court, often seen as favorable for plaintiffs due to a greater potential for jury trials and associated damages awards than might be available in federal court. Following a
2021 Supreme Court ruling in a related case that granted the companies an additional chance to argue that their cases should be heard in federal court, the lower federal appeals courts in each of the five cases concluded that the companies had not established sufficient grounds to establish proper venue and jurisdiction in federal court. The Supreme Court’s April 24 denial leaves those decisions unaltered, allowing the lawsuits to continue in state court for further consideration.
Read the court decisionRead the full story...Reprinted courtesy of
George Leahy, Lewis Brisbois