Filing Motion to Increase Lien Transfer Bond (Before Trial Court Loses Jurisdiction Over Final Judgment)
May 15, 2023 —
David Adelstein - Florida Construction Legal UpdatesIf a construction lien is recorded against real property, the lien can be transferred to a lien transfer bond. This transfers the security or collateral of the construction lien from the real property to the lien transfer bond. The lien transfer bond can be a bond posted by a surety company or it can be cash. This is governed by Florida Statute s. 713.24. The amount of the lien does not dictate the amount of the lien transfer bond. Rather, the lien transfer bond needs to be in the amount of the lien, plus interest on that amount for three years, plus $1,000 or 25% of the amount of the lien (whichever is greater so factor in the 25%) to cover attorney’s fees. Fla. Stat. 713.24(1).
If you are looking to transfer a construction lien to a lien transfer bond, make sure to consult with counsel.
Keep in mind there is a statutory mechanism for a lienor to increase the lien transfer bond to cover attorney’s fees and costs and notice the word “must” in the statute below. Pursuant to Florida Statute s. 713.24(3):
Any party having an interest in such security or the property from which the lien was transferred may at any time, and any number of times, file a complaint in chancery in the circuit court of the county where such security is deposited, or file a motion in a pending action to enforce a lien, for an order to require additional security, reduction of security, change or substitution of sureties, payment of discharge thereof, or any other matter affecting said security. If the court finds that the amount of the deposit or bond in excess of the amount claimed in the claim of lien is insufficient to pay the lienor’s attorney’s fees and court costs incurred in the action to enforce the lien, the court must increase the amount of the cash deposit or lien transfer bond. Nothing in this section shall be construed to vest exclusive jurisdiction in the circuit courts over transfer bond claims for nonpayment of an amount within the monetary jurisdiction of the county courts.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Partner Bradley T. Guldalian Secures Summary Judgment Win for National Hotel Chain
August 26, 2019 —
Bradley T. Guldalian - Traub LiebermanOn June 26, 2019, Traub Lieberman Straus & Shrewsberry LLP Partner Bradley T. Guldalian secured summary judgment on behalf of a national hotel chain in a slip and fall accident filed in Osceola County Circuit Court in Kissimmee, Florida. The underlying loss occurred when the Plaintiff slipped and fell in a puddle of water allegedly existing in the hotel’s laundry room and suffered a partial thickness rotator cuff tear involving the distal infraspinatus tendon for which he underwent surgery and incurred over $70,000 in medical bills. The Plaintiff filed a premises liability action against the hotel claiming the hotel had failed to maintain its premises in a reasonably safe condition proximately causing the Plaintiff’s fall and resulting injuries.
After discovery closed, Mr. Guldalian filed a motion for summary judgment on behalf of the hotel arguing that to prevail in a negligence claim involving a “transitory foreign substance”, such as water on a floor, an injured party must plead and prove pursuant to Florida Statute 768.0755 that the business establishment had actual or constructive knowledge of the dangerous condition and should have taken action to remedy it prior to the time of the alleged fall. Constructive knowledge may be proven by circumstantial evidence showing that (1) the dangerous condition existed for such a length of time that, in the exercise of ordinary care, the business establishment should have known of the condition or (2) that the condition occurred with such regularity that it was foreseeable that the condition would be present on the day the injury occurred.
Read the court decisionRead the full story...Reprinted courtesy of
Bradley T. Guldalian, Traub LiebermanMr. Guldalian may be contacted at
bguldalian@tlsslaw.com
Retroactive Application of a Construction Subcontract Containing a Merger Clause? Florida’s Fifth District Court of Appeal Answers in the Affirmative
September 07, 2017 —
Sanjo S. Shatley - Florida Construction Law NewsFlorida’s Fifth District Court of Appeal recently addressed the issue of retroactive application of a construction subcontract on the basis of a merger clause in Don Facciobene, Inc. v. Hough Roofing, Inc.[1]
In the case, in late 2010, Don Facciobene, Inc. (“DFI”), a licensed general contractor, contracted with Digiacinto Holdings, LLC, an owner of a home built in 1905 in Melbourne, Florida, known as the Nannie Lee House or the Strawberry Mansion, to perform various renovations in preparation for a restaurant to be opened on the premises. One of the renovations included a new roof. DFI subcontracted the roofing work to Hough Roofing, Inc. (“HRI”), a licensed roofing subcontractor. In mid-March 2011, HRI submitted an estimate and proposed statement of work to DFI. DFI’s project manager signed HRI’s proposal on April 5, 2011, as well as an additional expanded proposal six days later. According to the proposals, payment was due on completion. HRI began work on the roof on April 15, 2011, without a signed subcontract. However, DFI and HRI ultimately executed a subcontract on June 8, 2011, even though HRI had mostly finished its work by the end of May.
Read the court decisionRead the full story...Reprinted courtesy of
Sanjo S. Shatley, Cole, Scott & Kissane, P.A.Mr. Shatley may be contacted at
sanjo.shatley@csklegal.com
World’s Biggest Crane Lifts Huge Steel Ring at U.K. Nuclear Site
January 25, 2021 —
Rachel Morison - BloombergThe world’s largest crane hoisted the first of three massive steel rings that will encase one of the reactors at Electricite de France SA’s nuclear construction site in the U.K., a key milestone in getting the project completed on time.
Operators of the 250-meter (820-foot) tall crane, affectionately known as “Big Carl,” lifted the ring that weighs as much as a jumbo jet overnight to take advantage of windless conditions.
Hinkley Point C is the U.K.’s first new nuclear power plant in more than two decades. Once up and running the reactor will generate electricity for six million homes by 2025.
It’s the largest and most advanced infrastructure project in the country and, when finished, will contain 3 million tons of concrete and 50,000 tons of structural steel, enough to build a railway line between London and Rome.
Read the court decisionRead the full story...Reprinted courtesy of
Rachel Morison, Bloomberg
Time to Repair Nevada’s Construction Defect Laws?
February 10, 2012 —
CDJ STAFFThe Builders Magazine writes that during the previous session of the Nevada legislature, reforms sought by the building industry were stopped by the Speaker of the Nevada Assembly. The new session brings a new speaker and new hope for construction defect reform in Nevada.
Pat Hickey, a member of the Assembly and a small business owner told The Builders Magazine that “we need to apply pressure on the legislators to fix the law.” He also recommended that people “go to Governor Sandoval and ask for his help.” Builders seeks legislation that will include right to repair and it should “define construction defect in such a way that it allows for a fair process.”
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Green Energy Can Complicate Real Estate Foreclosures
November 30, 2016 —
Bob L. Olson – Snell & Wilmer Real Estate Litigation BlogA quick drive through almost any newer residential community in the Southwest will show that a lot of residents are embracing “Green Energy” or renewable energy by placing solar panels on their properties. While most people would agree that increasing the use of alternative energy is socially responsible, there are a number of real estate investors that may view it as an opportunity to make additional profits by purchasing distressed properties with solar panels and then reselling those properties for more than they would be worth without solar panels. The theory is relatively straight forward as many believe that foreclosure of a deed of trust that was recorded before the solar panels were installed would extinguish any liens in favor of the vendor that sold or financed the sale of the solar panels. After all, it is generally held that “a valid foreclosure of a mortgage terminates all interest in the foreclosed real estate that are junior to the mortgage being foreclosed.” See SFR Investments Pool 1, LLC v. U.S. Bank, N.A., 130 Nev. Adv. Op. 75, 334 P.3d 408, 412 (2014) (quoting Restatement (Third) of Property, Mortgages §7.1 (1997)).
NOT SO FAST! While the general rule is that foreclosure of a senior lien terminates junior liens, most purveyors of solar panels do not encumber the property with mortgages or deeds of trust to secure payment of amounts they are owed. Rather, they typically either lease the solar panels to the property owner or secure repayment of the purchase price of the solar panels with a fixture filing under the Uniform Commercial Code (the “UCC”).
Read the court decisionRead the full story...Reprinted courtesy of
Bob L. Olson, Snell & WilmerMr. Olson may be contacted at
bolson@swlaw.com
As Laura Wreaks Havoc Along The Gulf, Is Your Insurance Ready to Respond?
October 19, 2020 —
Walter J. Andrews, Michael S. Levine, Andrea DeField & Meagan R. Cyrus - Hunton Insurance Recovery BlogAs Texas and Louisiana brace for Hurricane Laura to make landfall, policyholders in the affected regions should be making last minute preparations to ensure their properties are covered in the storm’s wake.
Hurricane Laura is expected to make landfall as a Category 4 storm tonight, or early Thursday morning between Houston, Texas and Lake Charles, Louisiana. With wind speeds reaching over 120 mph, Laura has the potential for catastrophic damage to life and property and long-term disruption of normal business operations. The following three steps are crucial to ensuring that you protect your property and business and maximize insurance proceeds should your property fall in the path of this storm:
- Locate a copy of your policy.
Having your policy on hand prior to a loss will aid in starting your claim as soon as possible, as it may be more difficult to get in touch with your broker following a storm where thousands of claims are taking place simultaneously.
Reprinted courtesy of
Walter J. Andrews, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth,
Andrea DeField, Hunton Andrews Kurth and
Meagan R. Cyrus, Hunton Andrews Kurth
Mr. Andrews may be contacted at wandrews@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. DeField may be contacted at adefield@HuntonAK.com
Ms. Cyrus may be contacted at mcyrus@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Increase in Single-Family New Home Sales Year-Over-Year in January
February 26, 2015 —
Beverley BevenFlorez-CDJ STAFFBuilder magazine reported, “Sales of new single-family houses in January 2015 were at a seasonally adjusted annual rate of 481,000, according to estimates released today by the U.S. Census Bureau. This is 0.2% (±22.2%)* below the revised December rate of 482,000, but is 5.3% (±22.1%)* above the January 2014 estimate of 457,000.”
According to Metrostudy (as reported by Builder), builders seem to be getting ready for increased production this year: “An excellent leading indicator for housing starts is the number of lots reaching development (ready for the builder to start building). Our in-field research shows that lot development has doubled in the last two to three years in many markets.”
Read the court decisionRead the full story...Reprinted courtesy of