Unwrapped Pipes Lead to Flooding and Construction Defect Lawsuit
July 31, 2013 —
CDJ STAFFHomeowners in New Jersey have filed a lawsuit over unwrapped pipes in exterior walls. During the cold winter weather, the pipes froze, leading one homeowner to experience a “massive leak.” A plumber was able to end the flooding by shutting off water to the house. He then told the homeowner, Robert Long, that he had been doing the same at other homes in the community.
The Longs are now party to a class-action lawsuit which seeks that the homebuilder, Ryan Homes, tell those who have purchased homes about the defect. Further, the suit seeks compensation for those whose home have been damaged, and repairs to assure that additional homes do not have their pipes burst.
Stephen P. DeNittis, who is representing the Longs, said that “the code violation alleged in this case is particularly troublesome because it involves unprotected pipes hidden inside an exterior wall.”
Read the court decisionRead the full story...Reprinted courtesy of
Payment Bond Surety Entitled to Award of Attorneys’ Fees Although Defended by Principal
February 01, 2023 —
Garret Murai - California Construction Law BlogFor contractors involved in California public works projects the scenario is not uncommon: The general contractor awarded the public works project is required to obtain a payment bond for the benefit of subcontractors and suppliers and the payment bond surety issuing the payment bond requires the general contractor to defend and indemnify the surety from and against any claims against the payment bond.
In
Cell-Crete Corporation v. Federal Insurance Company, 82 Cal.App.5th 1090 (2022), the 4th District Court of Appeal examined whether a payment bond surety, who prevails in a claim against the payment bond, is entitled to statutory attorneys’ fees when the party actually incurring the attorneys’ fees was the general contractor, pursuant to its defense and indemnity obligations, as opposed to the surety itself.
The Cell-Crete Case
General contractor Granite Construction Company was awarded a public works contract issued by the City of Thermal known as the Airport Boulevard at Grapefruit Boulevard and Union Pacific Railroad Grade Separation Project. We’ll just call it the “Project.” Subcontractor Cell-Crete Corporation entered into a subcontract with Granite for lightweight concrete and related work.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Colorado Rejects Bill to Shorten Statute of Repose
May 07, 2015 —
Jesse Howard Witt – Acerbic WittThe House State, Veterans, and Military Affairs committee voted today to postpone Senate Bill 15-091 indefinitely, effectively killing the bill for the 2015 session.
As originally drafted, the bill would have given Colorado the shortest statute of repose in the United States. Senate amendments softened the impact of the bill somewhat, but it still would have reduced the amount of time that the owners of single-family homes would have to discover construction defects. Proponents argued that this was necessary because Colorado’s harsh weather conditions make it difficult for construction to last longer than five years. Opponents countered that construction defect laws only provide relief when a builder has violated a code or standard, which is unrelated to the expected lifespan of a product.
One of the Representatives noted that states like Alaska have much harsher weather patterns yet allow homeowners to bring claims up to ten years after construction is complete. Another questioned whether the bill would do anything to encourage affordable housing, a topic that has generated substantial media attention in recent months.
Read the court decisionRead the full story...Reprinted courtesy of
Jesse Howard Witt, Acerbic WittMr. Witt welcomes comments at www.wittlawfirm.net
Impaired Property Exclusion Bars Coverage When Loose Bolt Interferes with MRI Unit Operation
May 16, 2018 —
Christopher Kendrick & Valerie A. Moore - Haight Brown & Bonesteel, LLPIn All Green Electric v. Security National Ins. Co. (No. B279456, filed 3/19/18, ord. pub. 4/17/18), a California appeals court ruled that the impaired property exclusion barred coverage for a claim based on the insured’s failure to tighten a loose bolt that resulted in stray magnetic fields interfering with operation of an MRI machine and allegedly threatening the health of personnel.
All Green was an electrical contractor hired to perform wiring for an MRI unit installation. Stray magnetic fields interfered with the unit’s operation. Efforts to remediate the problem included installing shielding and ultimately relocating the unit to another room. An expert finally determined that a bolt left loose by All Green was causing the magnetic field, which disappeared when the bolt was properly tightened. The facility sought damages for negligence, including costs for unnecessary modifications and repairs, payments to outside sources for substitute mammography testing, operational costs and expenses, damage to reputation, lost profits, and the loss of an HMO contract.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
How the New Dropped Object Standard Is Changing Jobsite Safety
January 02, 2019 —
Derek Rose - Construction ExecutiveIn the United States, a dropped object injures a worker every 11 minutes—equating to nearly 50,000 cases every year. For those who seek medical treatment for these types of injuries, it can cost an average of $42,000. In fact, 5 percent of all fatalities on jobsites are due to falling objects, according to the Bureau of Labor Statistics.
These statistics highlight the overwhelming importance of dropped object prevention. OSHA already identifies dropped object incidents under the category of “Struck by Object” in its widely recognized “Fatal Four” list of the four leading causes of fatalities in the construction industry.
Reprinted courtesy of
Derek Rose, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Arkansas Federal Court Fans the Product Liability Flames Utilizing the Malfunction Theory
September 14, 2020 —
Michael J. Ciamaichelo - The Subrogation StrategistTo establish a product liability claim in Arkansas, the plaintiff must prove that the product was supplied in a defective condition, which rendered it unreasonably dangerous and that the defective condition was the proximate cause of the claimed damage or injury. Ordinarily, a plaintiff relies upon direct evidence of a product defect to establish its product liability claim. However, in some cases, the product sustains so much damage that it is impossible for a plaintiff to obtain direct evidence of a defect.
The malfunction theory allows a plaintiff in a product liability action to establish a defect through circumstantial evidence, when direct evidence of a defect no longer exists. In order to utilize the malfunction theory, a plaintiff must present evidence that an unspecified product defect was the most likely cause of the damage/accident and rule out all other possible causes of the damage/accident. In Am. Nat’l Prop. & Cas. Co. v. Broan-Nutone, No. 5:18-CV-5250, 2020 U.S. Dist. LEXIS 117116, the United States District Court for the Western District of Arkansas ruled that the plaintiff offered sufficient evidence under “the malfunction theory” to defeat a summary judgment motion in a product liability action involving a bathroom fan that was destroyed in a fire.
Read the court decisionRead the full story...Reprinted courtesy of
Michael J. Ciamaichelo, White and Williams LLPMr. Ciamaichelo may be contacted at
ciamaichelom@whiteandwilliams.com
Snooze You Lose? Enforcement of Notice and Timing Provisions
November 11, 2024 —
Cornelius F. "Lee" Banta, Jr. - ConsensusDocsDeadlines are an inescapable part of the construction industry. Bid deadlines. Submittal deadlines. Material delivery deadlines. Substantial completion. Final completion. And so, inevitably, fighting about deadlines becomes a necessary byproduct. Was the deadline really a deadline? Was the schedule slippage on the critical path? Should there be an equitable extension to the date of substantial completion? Given the amount of attention and concern conferred on deadlines, those drafting construction contracts naturally seek to clarify which deadlines really matter with the inclusion of notice and timing provisions.
A contract’s change order and claims procedures are often a key friction point for those drafting and administering the contract. Should there be a requirement for prior written notice of a claim for cost/time relief? How much advance notice? Who should the request be sent to? Is a specific form of notice required? What are the consequences of failing to provide timely notice? A practitioner should pay careful attention to negotiating these terms on the front end, because rest assured, these contract provisions will garner scrutiny when a change order dispute boils over.
Read the court decisionRead the full story...Reprinted courtesy of
Cornelius F. "Lee" Banta, Jr., Peckar & Abramson, P.C.Mr. Banta may be contacted at
lbanta@pecklaw.com
How to Defend Stucco Allegations
February 07, 2014 —
Beverley BevenFlorez-CDJ STAFFManaging partner Paul McBride discusses how to defend stucco defect allegations in his article in Kring & Chung, LLP’s online publication. According to McBride, about “80% of construction defect lawsuits which [Kring & Chung] defend involve stucco-clad houses.” In the article, McBride addresses “improper building paper installation and stucco cracks.”
“If you are defending the stucco subcontractor,” McBride advises to look “first, at the windows section of the plaintiffs’ defect report and cost of repair estimate.” He explains that “this is the section where the plaintiffs’ expert will allege water intrusion that will be allocation to your stucco subcontractor.”
McBride declares that the “most important thing to understand about stucco cracks is that stucco cracking is common. This is both a common sense observation and a perfectly valid legal defense.”
Read the court decisionRead the full story...Reprinted courtesy of