Court Holds That Trimming of Neighbor’s Trees is Not an Insured Accident or Occurrence
June 10, 2015 —
Christopher Kendrick and Valerie A. Moore – Haight Brown & Bonesteel LLPIn Albert v. Mid-Century Insurance Co. (No. B257792, filed 4/28/15, ord. pub. 5/20/15), a California Court of Appeal held that an insured’s trimming of a neighbor’s trees which allegedly damaged the trees was not an accident or occurrence covered by her homeowners insurance, despite a mistaken and good faith belief as to where the property line lay.
Ms. Albert was sued by her adjoining neighbor, who alleged damage to his property when she erected an encroaching fence and pruned nine mature olive trees on his property. The two parcels shared a reciprocal roadway easement providing for access to the main public road. At some point, Ms. Albert erected a fence that was subsequently determined to be on the neighbor’s land, and which enclosed a grove of nine mature olive trees. Ms. Albert claimed that the trees straddled the property line and were mutually owned. She pointed out that she had regularly been notified by the Los Angeles Fire Department to clear the area, and that she had been trimming the trees for years. Thus, she claimed a good faith belief that the trees were hers and that she was required to trim them.
Contending that her trimming had caused severe damage by reducing the aesthetic and monetary value of the trees, the neighbor sued alleging causes of action for trespass to real property and trees; abatement of private nuisance; declaratory relief; and for quiet title. He sought treble damages under Civil Code sections 733 and 3346, for injury to timber or trees.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com; Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Discussion of the Discovery Rule and Tolling Statute of Limitations
February 26, 2015 —
Beverley BevenFlorez-CDJ STAFFAttorney Clay Olson analyzed a recent South Carolina appeals case that “discussed the threshold for ‘notice’ as it pertains to statute(s) of limitations in construction defect cases. At the root of this action was a 2003 forensic report obtained by the HOA which was not acted upon until 2009.”
Olson presented the background of the case as well as the case progression. Olson concluded, “It is well settled that an expert’s findings, when presented to a claimant, trigger the statute of limitations as to the specific defective conditions and locale where defects are present. This case is interesting in its treatment of the initial report as a trigger of all defects in not only the main building which was subject of the 2003 report, but additional structures.”
Read the court decisionRead the full story...Reprinted courtesy of
Real Estate & Construction News Round-Up 05/04/22
May 23, 2022 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogConstruction payment apps are on the rise, the European Union proposes to block Russians from buying European real estate, warehouse vacancy rates hit a 27-year low, and more.
- The Metaverse Group has made itself one of the most prominent virtual land owners, having invested more than $10 million into digital real estate purchases. (Katie Canales, Business Insider)
- The European Union proposed to block Russians from buying European real estate in its six package of sanctions following Russia’s invasion of Ukraine. (Jorge Valero and Alberto Nardelli, Bloomberg)
- Although smart office buildings are able to easily identify viruses, they are susceptible to hacks, raising privacy and cybersecurity concerns in the market. (Konrad Putzier, The Wall Street Journal)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
Breach Of Duty of Good Faith And Fair Dealing Packaged With Contract Disputes Act Claim
March 27, 2023 —
David Adelstein - Florida Construction Legal UpdatesAn interesting opinion on a motion to dismiss came out of the United States Court of Federal Claims dealing with the claim that the government breached its duty of good faith and fair dealing in administering the prime contract. The contractor’s argument was that the government breached its duty of good faith and fair dealing by denying the contractor’s claim under the Contract Disputes Act (CDA). This was a creative claim and argument that deserves consideration because it tied in the contracting officer’s denial of the CDA claim for additional money with a breach of the duty of good faith and fair dealing.
In this case, Aries Construction Corp. v. U.S., 2023 WL 2146598 (Fed. Cl. 2023), a prime contractor was hired for a water pipeline construction project. The contractor encountered unexpected difficult site conditions that required additional equipment and labor. The contractor informed the contracting officer and alleged it was instructed to proceed with the additional equipment and labor. The contractor submitted a claim under the CDA but the contracting officer denied the claim. The contractor pursued the claim in the United States Court of Federal Claims arguing the government breached the contract and, of interest, breached its duty of good faith and fair dealing.
The government moved to dismiss the breach of good faith and fair dealing claim arguing that besides failing to state a cause of action the Court of Federal Claims had no jurisdiction because the breach of the duty of good faith and fair dealing was not properly presented to the contracting officer under the CDA. The Court of Federal Claims denied the government’s motion.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Wine without Cheese? (Why a construction contract needs an order of precedence clause)(Law Note)
August 11, 2011 —
Melissa Brumback, Construction Law in North CarolinaFor today’s law note, I’m addressing a comment that came to me last week from Dave O’Hern of Miller O’Hern Construction. Dave writes:
I am a general contractor doing a fuel tank replacement project for our county. In the specifications there is a spec for a UL 142 tank, on the plans the spec references UL 2085 ? a much more expensive tank. My subcontractor bid the UL 142 tank. The specifications state that the specs and plans are on the same level of precedence.
The county wants me to furnish the more expensive tank without compensation citing the clause that states the plans and specs are complementary and what is called for by one is binding as if called by all and the most stringent requirement will apply.
Read the full story…
Reprinted courtesy of Melissa Brumback of Ragsdale Liggett PLLC. Ms. Brumback can be contacted at mbrumback@rl-law.com.
Read the court decisionRead the full story...Reprinted courtesy of
Relief Bill's Highway Funds Could Help Construction Projects
January 04, 2021 —
Tom Ichniowski - Engineering News-RecordAmong the many provisions in the coronavirus relief bill, one key item is $10 billion to help state highway agencies make up for losses in state fuel taxes and other revenue due to the pandemic-caused falloff in traffic this year. Construction is one of a list of several eligible uses for the money—one of only a few construction funding provisions in the relief measure.
Reprinted courtesy of
Tom Ichniowski, Engineering News-Record
Mr. Ichniowski may be contacted at ichniowskit@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Top 10 Take-Aways: the ABA Forum's 2024 Mid-Winter Meeting
February 26, 2024 —
Marissa L. Downs - The Dispute ResolverThe Forum on Construction Law convened last week at Caesars Palace in sunny Las Vegas for its 2024 Mid-Winter Meeting. Carrie Okizaki and David Suchar (along with John Cook, Karen Erger, and countless others) put together a truly outstanding program on power projects. Here are my top 10 take-aways from this unique and insightful event:
10. The demand for power projects is steadily increasing. The increasing demand for power construction projects is being driven chiefly by the need to replace aging infrastructure as well as the desire to develop cleaner and more sustainable generation facilities. The constant demand for more and more electricity is not that surprising but, according to Jeff Richardson (Energy Solutions) and Eric S. Gould (Modus Strategic Solutions), the pipeline market size for power-generation projects in 2028 is expected to reach $10.6 trillion, i.e., double what it was just in 2022.
9. "Net Zero" is the new normal. In December 2021, President Biden issued an executive order proclaiming that, by 2050, the federal government will be a Net-Zero contributor to the climate crisis. To achieve this goal, the greenhouse gasses ("GHGs") released by government operations must be less than (or equal to) the GHGs absorbed/removed from the environment. Other government bodies and private companies alike are adopting similar Net-Zero goals. Because not all of these promises are created equal, Moody’s Investors Services has a tool to help consumers compare and evaluate companies' carbon transition plans. According to panelists, Amanda Schermer MacVey (Venable), Brendan Hennessey (Pillsbury), and Laszlo von Lazar (Black & Veatch), these Net-Zero commitments are likely to result in more rigorous supplier codes of conduct and heightened carbon tracing efforts on construction projects.
Read the court decisionRead the full story...Reprinted courtesy of
Marissa L. Downs, Laurie & Brennan, LLPMs. Downs may be contacted at
mdowns@lauriebrennan.com
Construction Contract’s Scope of Work Should Be Written With Clarity
March 06, 2023 —
David Adelstein - Florida Construction Legal UpdatesThe scope of work section in your construction contract should never be overlooked. In numerous instances, it is overlooked which leads to a dispute as to the precise nature of the scope of work. This dispute could be the result of an ambiguity in the scope of work section. Or it could be the result of an omission. Or it could be the result of a lack of clarification. Or it could be the result of not properly reviewing and vetting the scope of work section. This is a section—whether included in the body of your contract or attached as an exhibit—you absolutely, positively want clarity. Otherwise, you are potentially setting yourself up for a future dispute that could include (i) an additional work / change order dispute, (ii) an incomplete work dispute, or (iii) a failure to properly perform your work dispute. These are all disputes you want to avoid, and many times can avoid, by going through and negotiating the scope of work section to bring clarity to this section. Remember, clarity is a positive. Ambiguity or uncertainty is a negative.
An example of such an avoidable scope of work dispute can be found in All Year Cooling and Heating, Inc. v. Burkett Properties, Inc., 2023 WL 2000991 (Fla. 4th DCA 2023). Here, an air conditioning contractor was hired to install six new split air conditioning systems. The scope of work provided that there were currently “two split systems that are currently existing, working perfectly and are not to be replaced as part of this contract.” The property manager claimed the air conditioning contractor was required to bring these two existing split air conditioning systems up to code as the contract provided that notwithstanding anything to the contrary, the contractor “will certify and shall ensure that all split systems in the building, upon completion of all the work, will be fully compliant with all codes and regulations and shall be responsible for any costs relates to the implementation and/or remediation of same.”
Read the court decisionRead the full story...Reprinted courtesy of