Construction Defect Claims are on the Rise Due to Pandemic-Related Issues
April 25, 2022 —
Beverley BevenFlorez – CDJ StaffAccording to a recent
New York Times article, pandemic-related issues such as “stop-and-start construction, global supply chain issues, pressure from lenders and yo-yoing housing prices” has caused an increase in construction defect suits for new apartment developments: “Complaints and legal claims are already emerging, signaling that a confluence of all factors amid the Covid crisis could continue to be a problem for new construction — from entry-level studios to top-tier penthouses — for years to come, according to lawyers and development consultants.”
A Times analysis of Department of Buildings data by Marketproof demonstrated an increase in complaints beginning March 1st, 2020: “During the first year of the pandemic, new residential buildings recorded an average of five complaints per building, a 46 percent jump from the same period the previous year.”
Steven D. Sladkus, a partner at Schwartz Sladkus Reich Greenberg Atlas told the Times that his “'phone’s been ringing off the hook' with complaints from homeowners in new condo buildings” regarding “heating problems, poor sound insulation, fire safety issues and faulty elevators.”
Developers have faced a variety of pandemic-related challenges including a disrupted supply chain, shut downs, shipping delays, labor shortages, and increased material prices. In 2020, the lack of availability of vaccines caused some construction to halt: “Suddenly one guy calls in sick and the whole crew of electricians can’t show up,” Steven Zirinsky, co-chair of the building codes committee at the New York chapter of the American Institute of Architects told the Times.
Read the court decisionRead the full story...Reprinted courtesy of
Designers George Yabu and Glenn Pushelberg Discuss One57’s Ultra-Luxury Park Hyatt
July 30, 2014 —
Jennifer Parker – BloombergOne57 might just be the hottest -- or at least the most expensive -- address in New York City.
The $375 million skyscraper currently piercing its blue-glass presence into Manhattan's midtown skyline is home not only to 94 private condos (two of which have already sold for $90 million); it also hosts a brand new Park Hyatt hotel, which opens this August.
Eight years in the making, this Hyatt is the first ultra-luxury hotel New York has seen since the Mandarin Oriental opened in 2003. It's intended to be a New York icon. So, naturally, Hyatt hired two Canadian guys to design it.
Meet George Yabu and Glenn Pushelberg, the dynamic couple who met as college students in Toronto in 1972, and decided to launch design firm YabuPushelberg. Now, they're earning millions per project to design luxury hotels, restaurants, and residences all over the world.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer Parker, Bloomberg
Construction of World's Tallest Building to Resume With New $1.9B Contract for Jeddah Tower
October 28, 2024 —
James Leggate - Engineering News-RecordConstruction of the Jeddah Tower in Jeddah, Saudi Arabia—which is planned to be the world’s tallest building—is set to resume with original contractor Saudi Binladin Group Co. after a years-long pause, owner Jeddah Economic Co.'s parent company, Kingdom Holding Co., announced Oct. 2.
Reprinted courtesy of
James Leggate, Engineering News-Record
Mr. Leggate may be contacted at leggatej@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
The ‘Sole Option’ Arbitration Provision in Construction Contracts
July 16, 2014 —
Beverley BevenFlorez-CDJ STAFFOn his Best Practices Construction Law blog, Matthew Devries discussed how the “at its sole option…has the right to demand arbitration” can “be a good provision if you are the party who has that option.”
For instance, Devries cites the case Archer Western Contractors, LLC v Holder Construction Company, where “the Georgia Court of Appeals recently affirmed the trial court’s decision to grant a contractor’s motion to compel arbitration with a ‘sole option’ provision.”
Devries stated that “it is important to review carefully the disputes clause in your construction contract to fully understand who has the right to demand arbitration and what rules will apply.”
Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Concludes Government’s CAA Legal Claims are Time-Barred But Injunctive-Relief Claims are Not
November 28, 2018 —
Anthony B. Cavender - Gravel2GavelIn another recent U.S. Court of Appeals for the Fifth Circuit decision, on October 1, 2018, the Fifth Circuit affirmed, in part, the District Court’s ruling that the general federal statute of limitations, 28 U.S.C. § 2462, required the dismissal of the government’s civil enforcement action in the case of U.S., et al., v. Luminant Generation Co., LLC, et al.
The Fifth Circuit agreed that the statute barred the imposition of any civil fine for the alleged unlawful construction operations regarding the modification of major emitting facilities contrary to Section 7475(a) of the Clean Air Act (CAA). But, the Fifth Circuit remanded the injunctive-relief claims to the District Court for further consideration.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
The Secret to Success Is Doing Things a Little Bit Differently
November 16, 2020 —
Charlie Kimmel - Construction ExecutiveThroughout the 1960s and 1970s, Rick Barry made his mark on the world of college and professional basketball. He was a skilled small forward who averaged 37.4 points per game during his senior year at the University of Miami, and he was the second overall pick in the 1965 NBA draft. But he’s best remembered as a prolific free-throw shooter: he led the NBA in free-throw percentage for several consecutive years. When he retired in 1980, his free-throw percentage (.900) was the highest in NBA history.
So what was the secret to his success? He did things a little bit differently. While the vast majority of basketball players shoot overhand free throws, Barry was famous for his unorthodox underhanded shots. This technique was not only incredibly effective, but it also set him apart as a player and contributed to his popularity.
Construction companies can learn a lot from Barry’s strategy of doing things a little bit differently to achieve success. Most companies don’t need to worry about their employees’ free-throw techniques. But all of them need to set themselves apart from their competition and establish strong reputations in today’s highly competitive market.
Reprinted courtesy of
Charlie Kimmel, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Finding an "Occurrence," Appellate Court Rules Insurer Must Defend
March 11, 2024 —
Tred R. Eyerly - Insurance Law HawaiiReversing the trial court, the Wisconsin Court of Appeals found the insurer must defend a cross-claim against the insured owner of a building after an explosion occurred. LBC, LLC v Spectrum Brands, Inc., 2023 Wis. App. LEXIS 1251 (Wis. Ct. App, Nov. 30, 2023).
LBC leased commercial property to Spectrum. Spectrum stored lithium on the property. The lithium exploded when it came into contact with water that entered the premises during historic flooding in August 2018. Spectrum remediated the premises, vacated the premises prior to the lease's termination date, and stopped paying rent.
LBC sued Spectrum, alleging that Spectrum negligently stored the lithium and that Spectrum breached the lease. Spectrum counterclaimed, alleging that LCB breached the lease in various respects, that LCB negligent allowed water to infiltrate the premises, and that Spectrum was constructively evicted. LCB tendered the counterclaim to its insurer, General Casualty. The tender was denied and LCB sued.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Badly Constructed Masonry Walls Not an Occurrence in Arkansas Law
May 10, 2012 —
CDJ STAFFThe US District Court for Maryland has granted a summary judgment in the case Konover Construction Corp. v. ATC Associates to Massachusetts Bay Insurance Company and denied a request for dismissal from ACT. Konover (KBE) was contracted by Wal-Mart to build a Wal-Mart store and a Sam’s Club in Port Covington, Maryland. Superus, Inc. was hired by KBE to build the masonry walls. Superus purchased a policy from Massachusetts Bay Insurance which named KBE as an additional insured. Wal-Mart hired ATC Associates to independently test and inspect the concrete structural steel, and masonry.
After the building was in use, a large crack appeared which was attributed a latent construction defect. Other cracks were discovered. Upon investigation, it was discovered that there were “voids or foam in the concrete block surrounding the reinforcing steel that should have been filled with grout,” and in some cases, “reinforcing steel was missing or not installed in accordance with the specifications.” KBE paid for the repair and remediation and Wal-Mart assigned all rights and interests against ATC to KBE.
KBE filed suit against ATC. ATC called for dismissal on the grounds that Wal-Mart had no claims as the problems had been remediated. Wal-Mart then provided KBE with additional agreements to give them enforceable rights against ATC and Superus. KBE filed a fourteen claims against ATC, Superus, and Massachusetts Bay. In the current case, Massachusetts Bay sought summary judgment and ATC sought dismissal of all claims against it.
Massachusetts Bay claims that they need not indemnify Superus, as “there is no evidence adequate to establish that Superus’ defective work caused any collateral and/or resulting damage that was not subject to an Impaired Property exclusion, and that, in any event, no damage occurred during the policy period.”
As Wal-Mart is headquarted in Arkansas, certain contracts were under Arkansas law. Under the Arkansas courts, “defective workmanship, standing alone and resulting in damages only to the work product itself, is not an ‘occurrence.’” The court determined that collateral or resultant damage would be covered. The court found that “it is clear under Arkansas law, and the parties appear to agree, that Massachusetts Bay is not obligated to indemnify KBE for any repairs to the masonry walls themselves, including any cracks or gaps in the walls.” The court also found that “there is no evidence adequate to prove that any allegedly resultant property damage was caused by Superus’ faulty construction of the walls.” The court also noted that “if the building code violation and structural integrity problem were ‘property damage,’ insurance coverage would be barred by the Impaired Property Exclusion.” Based on these findings, the court concluded that Massachusetts Bay is entitled to summary judgment.
While the court dismissed the case against Massachusetts Bay, the court declined ATC’s motion to dismiss. The court noted that ACT’s alleged negligence in conducting inspections “created only a risk of economic loss for KBE.” Although hired by Wal-Mart, ATC “transmitted its daily testing and inspection reports of the Wal-Mart and Sam’s Club projects directly to KBE.” The court found that “KBE has made a plausible claim.”
ATC also claimed that KBE contributed to the negligence due to the negligence of its subcontractor. The court concluded that it was plausible that “ATC will not be able to carry its burden of proving KBE was contributorily negligent.” The court was less sanguine about KBE’s fraud claim, but though it “may not now appear likely to have merit, it is above the ‘plausibility’ line.”
In conclusion, KBE may not continue its case against Massachusetts Bay. However, the judge allowed the other proceedings to continue.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of