Harrisburg Sought Support Before Ruinous Incinerator Retrofit
September 20, 2017 —
Jonathan Barnes & Richard Korman - Engineering News-RecordWhen former Harrisburg, Pa., Mayor Stephen Reed (D) and his aides set out to retrofit the city’s aging incinerator in late 2000, the project spun out of control over the coming years, enlarging the debt the city owed on the facility to $300 million and sinking Harrisburg into financial ruin.
Reprinted courtesy of
Jonathan Barnes, ENR and
Richard Korman, ENR
ENR staff may be contacted at ENR.com@bnpmedia.com
Read the court decisionRead the full story...Reprinted courtesy of
Boilerplate Contract Language on Permits could cause Problems for Contractors
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFCraig Martin on his blog Construction Contractor Advisor discusses the potential problems for a contractor that a “boilerplate contract” could cause: “A recent case revealed the problems a contractor had with permits when the contractor’s estimate contemplated an easy permitting process and compliance, but in actuality it was much, much more difficult.”
Martin cites the case Bell/Heery v. United States, where a contractor discovered that the permit process would be much more time-consuming and expensive than originally planned. When Bell/Heery asked for additional funds to cover the additional costs, the “contracting officer rejected the request, finding that Bell/Heery had assumed the risk of the permitting process and it was liable for any costs associated with the permitting process and construction methods required by the permitting process.”
“Bell/Heery appealed to the Court of Claims,” but lost the battle. The contractor had to absorb $7 million in costs to comply with the required permits.
Read the court decisionRead the full story...Reprinted courtesy of
2017 California Employment Law Update
January 13, 2017 —
Evelin Y. Bailey - California Construction Law BlogBelow are some of the new laws going into effect this year that affect the construction industry. Unless otherwise noted, the laws go into effect on January 1, 2017.
Public Works and Prevailing Wages
You can read more about the new laws—AB 326, AB 1926 and SB 954—relating to public works and prevailing wages in an earlier blog post.
Employment Contracts
Choice of Forum and Choice of Law. Under SB 1241, an employer cannot require an employee who primarily works and resides in California to agree to file a lawsuit or bring a claim in another state when the claim arises in California. This is usually referred to as the choice of forum clause.
Read the court decisionRead the full story...Reprinted courtesy of
Evelin Y. Bailey, Wendel Rosen Black & Dean LLP Ms. Bailey may be contacted at
ebailey@wendel.com
Complying With Data Breach Regulations in the Construction Industry
November 24, 2019 —
Ryan Bilbrey - Construction ExecutiveRecent data breach incidents—like the massive Capital One cyberattack, where a former employee accessed more than 100 million customer accounts and credit card applications—have left many users questioning how safe their information really is in the hands of companies.
There is reason to be concerned. More than 4.1 billion records were exposed in nearly 4,000 data breaches reported in the first half of 2019 alone, according to the 2019 MidYear QuickView Data Breach Report. Construction companies are not immune.
As the industry becomes more reliant on technology—using augmented reality, Building Information Modeling and drones on construction sites, for example—construction companies are becoming greater targets for hackers looking to gain a financial or strategic advantage.
Instead of assuming a company will never experience a breach (or rather, denying that it will ever happen), it’s important to be aware of possible threats and establish data breach response policies to minimize potentially catastrophic fallout.
Reprinted courtesy of
Ryan Bilbrey, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Bilbrey may be contacted at
rbilbrey@biaprotect.com
Top 10 Insurance Cases of 2024
January 21, 2025 —
Jeffrey J. Vita & Michelle A. Grieco - Saxe Doernberger & Vita, P.C.Federal and state courts tackled a myriad of interesting insurance-related issues this past year. The U.S. Supreme Court also surprisingly addressed coverage issues in 2024, in not one—but two—decisions. It is rare for the Supreme Court to confront insurance coverage issues which usually involve matters of state law. The highest court’s assessment of the nuances of insurance to resolve maritime choice of law issues and interpret an insurer’s role in bankruptcy proceedings is indicative of the significant role that insurance coverage plays in resolving commercial disputes.
Additionally, 2024 included a pivotal opinion from the 5th Circuit, which welcomed the principle that negligent construction can constitute “property damage” under a CGL policy if it causes a harmful change to the property. Elsewhere in the country, the Hawaii Supreme Court ruled that reckless conduct can qualify as an “accident” under a CGL policy’s definition of “occurrence”; however, the court simultaneously ruled that greenhouse gases fall within the scope of “pollutants” under the policy’s pollution exclusion. Cyber coverage decisions were also prominent, and the 5th Circuit chimed in with an interesting decision interpreting the scope of coverage afforded under a “system failure” provision. These decisions represent a mere sampling of the multitude of insurance issues courts nationwide have grappled with in 2024.
Reprinted courtesy of
Jeffrey J. Vita, Saxe Doernberger & Vita, P.C. and
Michelle A. Grieco, Saxe Doernberger & Vita, P.C.
Mr. Vita may be contacted at JVita@sdvlaw.com
Ms. Grieco may be contacted at MGrieco@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Failing to Release A Mechanics Lien Can Destroy Your Construction Business
May 01, 2023 —
William L. Porter - Porter Law GroupIs the title to this article possibly true? Yes, absolutely! I have seen it happen. Let me tell you how it happens so you can avoid such a result.
When contractors, subcontractors or suppliers in California construction projects are not paid they often record a mechanics lien on the property on which they worked. This is a customary accepted legal process for the claimant to secure its right to payment. The mechanics lien enables the claimant to eventually sell the property and obtain payment from the proceeds to the extent they remain unpaid. California Civil Code Section 8460 generally requires that a lawsuit to foreclose on a mechanics’ lien must be filed in court within ninety (90) days after the mechanics’ lien is recorded. If no lawsuit has been filed in court within this 90-day period, then the lien generally becomes unenforceable. Because the mechanics lien remains a cloud on the title to the property if not released, the lien claimant usually releases the mechanics lien if they have failed to meet the lawsuit deadline. Lien claimants will also release a lien and/or dismiss the foreclosure lawsuit in exchange for payment. It is rare that the property is actually sold to obtain payment. This is a brief description of the pathway to payment through the use of a mechanics lien.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Texas Jury Finds Presence of SARS-CoV-2 Virus Causes “Physical Loss or Damage” to Property, Awards Over $48 Million to Baylor College of Medicine
September 26, 2022 —
Michael S. Levine & Kevin V. Small - Hunton Insurance Recovery BlogA Texas jury has found that the presence of SARS-CoV-2 virus on the property of Baylor College of Medicine (BCM) caused “physical loss or damage” and resulting economic loss, triggering coverage under BCM’s commercial property insurance program. The jury awarded BCM over $48 million following a three-day trial; the award consisted of $42.8 million in business interruption, $3.3 million in extra expense, and $2.3 million in damage to research projects.
The verdict came after the court denied the insurers’ pre-trial motion for summary judgment, rejecting the insurers’ contention that a virus cannot—as a matter of law—cause physical loss or damage to property. In denying the motion, the court held that whether the presence of the virus causes physical loss or damage presents a question of fact for the jury to resolve; a copy of the order rejecting the insurers’ summary judgment argument can be found
here.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Kevin V. Small, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Small may be contacted at ksmall@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Hirer Liable for Injury to Subcontractor’s Employee Due to Failure to Act, Not Just Affirmative Acts, Holds Court of Appeal
December 11, 2018 —
Garret Murai - California Construction Law BlogThe Privette doctrine, named after the court case Privette v. Superior Court (1993) 5 Cal.4th 689, provides that a higher-tiered party such as an owner or general contractor is not liable for injuries sustained by employees of a lower-tiered party such as a subcontractor on a construction project. There are, however, exceptions to the Privette doctrine. One of these exceptions is known as the “retained control doctrine.”
Under the retained control doctrine, a higher-tiered party cannot avoid liability under the Privette doctrine if the higher-tiered party: (1) retains control over the conditions of the work; (2) negligently exercises control over such conditions; and (3) its negligent exercise of control contributes to the injuries sustained by the employee of the lower-tiered party.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel, Rosen, Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com