Dump Site Provider Has Valid Little Miller Act Claim
October 19, 2020 —
Christopher G. Hill - Construction Law MusingsYou may have thought that a Virginia “Little Miller Act” bond claim, like a mechanic’s lien, could only be brought by those that provide materials and labor incorporated into the construction project. If you did, you aren’t alone.
In fact, Safeco Insurance Co. of America, a surety, made exactly the above argument in Yard Works LLC v. GroundDown Constructors LLC. In that case, a debris hauling company failed to pay Yard Works, the company that provided the dumping site for the debris. Yard Works sued pursuant to the Little Miller Act to get paid. In response, the surety sought to have the claim against the payment bond dismissed and argued that because Yard Works did not actually improve the property or provide improvements and that Yard Works only passively provided a dump site, Yard Works could not claim under the payment bond.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Eyerly may be contacted at
te@hawaiilawyer.com
Reminder: In Court (as in life) the Worst Thing You Can Do Is Not Show Up
September 28, 2017 —
Christopher G. Hill - Construction Law MusingsAs long time (and possibly recent) readers of Construction Law Musings know, I am a Virginia Supreme Court Certified Mediator. In that capacity, I spend quite a bit of time sitting in general district court courtrooms in places like Goochland and Caroline Counties “court sitting” awaiting a referral from the judge of a case with parties ready and willing to take advantage of the mediation process.
As I sit there wearing my mediator “hat,” I see case after case be called for the first return date. Without fail, several cases are called where the defendant fails to appear after being served with process. There are even a case or two where the plaintiff (the party that picked the return date in the first place) fails to appear. In the first instance, where the defendant doesn’t appear, the judge almost inevitably enters a judgment for the amount sued for by the plaintiff. In the latter instance, the case is dismissed without prejudice to the plaintiff with a shake of the head by the judge at the wasted time and filing fee. This post focuses on the first case.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Offices of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Be Careful with Good Faith Payments
February 24, 2020 —
Christopher G. Hill - Construction Law MusingsSometimes doing the expedient thing and what looks good at the time can come back to bite you. Just ask 3M Company.
In Faneuil, Inc. v. 3M Co., the Virginia Supreme Court considered a customer services subcontract between Faneuil and 3M relating to a toll collection contract 3M entered into with ERC. The subcontract had a “pay if paid” clause in it requiring payment to 3M from ERC before ERC was required to pay Faneuil, a written change order provision and a base monthly payment to Faneuil for the services that could be reduced in the event of less than expected toll collections. Further, the subcontract stated that if either party settled 3rd party claims, that settlement would not bind the other party to the subcontract absent consent or Court order.
Faneuil was then alleged to have been required to provide “Special Services” relating to manual identification of license plates and other information necessary for toll billing due to 3M’s alleged failure to provide adequate imaging services. Faneuil requested (without written change order) and 3M promised to pay extra for these services. When 3M was slow to pay for the special services, Faneuil did what you would expect and threatened to stop providing them. Instead of contesting the right to the work, 3m made sporadic “good faith” payments to induce continued Special Services from Faneuil. Eventually 3M’s issues caused ERC to stop payments and thus 3M stopped paying Faneuil. 3M then settled the payment claims with ERC and still failed to pay Faneuil.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
The Need for Situational Awareness in Construction
January 27, 2020 —
Aarni Heiskanen - AEC BusinessRecent research backs up what we already know from practice: construction work is suboptimal. What happens on a construction site has not kept up with the demands of an increasingly complex work environment. Situational awareness could give on-site employees the necessary means to finally reap the productivity benefits of digitalization.
Under the guidance of Professor Olli Seppänen, research teams at the Finnish Aalto University have delved into everyday conditions at a construction site. With the workers’ permission, they used video cameras, sensors, and surveys to locate the bottlenecks in productivity. The researchers also monitored the movement of products and materials on a construction site. The results are eye-opening.
According to Aalto’s data, digitalization has not improved the productivity of construction foremen and workers. A typical worker still spends up to 70% of their time on activities that add no value: searching for information, unnecessary movement, and waiting. Construction materials are moved from place to place six times on the site before being consumed. In addition, especially on large construction sites, machinery often goes missing or is displaced.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Equitable Subrogation Part Deux: Mechanic’s Lien vs. Later Bank Deed of Trust
September 15, 2016 —
Kevin J. Parker – Snell & Wilmer Real Estate Litigation BlogThis post follows, almost two years to the day, Rick Erickson’s post of August 29, 2014. As noted by Rick Erickson in his August 29, 2014 post, the Arizona Supreme Court in the Weitz case (2014) had determined that equitable subrogation principles were applicable to enable an earlier-recorded mechanic’s lien to be trumped by a later-recorded bank deed of trust, if the loan secured by the later deed of trust paid off a lien that had been ahead of the mechanic’s lien. In a decision filed August 9, 2016, the Arizona Court of Appeals further clarified the scope of such equitable subrogation.
In Markham Contracting Co., Inc. v. FDIC, No. 1 CA-CV 14-0752 (August 9, 2016), the Arizona Court of Appeals addressed a situation where a first-recorded deed of trust was followed by a second-recorded mechanic’s lien; and then, after the mechanic’s lien was recorded, a new lender made a secured construction loan that was used, in part, to pay off the loan that was secured by the first-position deed of trust. The key being “in part.” The subsequent lender loaned $4.8 million, but only $2.9 million went to pay off the balance owing on the first-position deed of trust.
Read the court decisionRead the full story...Reprinted courtesy of
Kevin J. Parker – Snell & WilmerMr. Parker may be contacted at
kparker@swlaw.com
Oregon Courthouse Reopening after Four Years Repairing Defects
April 01, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Courthouse Square in Marion County, Oregon is due to reopen after four years and nearly $23 million of repair costs to fix structural defects, according to the Statesman Journal. The square includes a courthouse building and bus mall, and is jointly owned by the county and transit district.
Two years after the Courthouse Square had been built, cracks were observed “in the building’s walls” and “paving stones on the bus mall shifted and settled.” A construction defect suit was filed in 2006.
However, the situation worsened in July of 2010 when “engineers determined that the entire complex was dangerous,” according to the Statesman Journal. “Building safety officials gave Courthouse Square’s occupants 60 days to move out, forcing county and transit district operations into temporary leased space.”
Now that the structural repairs have been completed, Dave Clark, project manager with Structural Preservation Systems LLC (the company awarded the repair contract), stated that the building’s structure is now stronger than most buildings. “If there’s an earthquake, come to this building,” Clark said.
Read the court decisionRead the full story...Reprinted courtesy of
Executive Insights 2024: Leaders in Construction Law
August 05, 2024 —
Construction ExecutiveThe key risks that should always be taken into account when a contract is signed are risks associated with uncompensated delays and cost increases. Provisions relating to the scope of work deserve significant attention to help minimize these risks. Defining the scope of work is often put on the backburner while parties focus on negotiating the rest of the terms and conditions of the contract. And when these scopes are inserted, they are often not closely reviewed by attorneys who tend to defer to project personnel on scope. These situations can lead to costly disputes.
Instead, make sure: (1) the correct plans and specifications have been referenced in the contract; (2) an attorney or his/her business counterpart is familiar with relevant specifications; (3) the exhibit containing the assumptions and clarifications is clearly written, has been coordinated with language in the body of the contract and can be clearly understood by attorneys and business people beyond the preconstruction personnel who drafted them; and (4) the contract addresses the order of precedence in the event of a conflict between or among contract provisions (including exhibits). With regard to specifications referenced above, an attorney review is advised because many specification sections, including submittal sections, change order sections, payment provisions and construction progress documentation sections, regularly vary from the negotiated sections of the actual contract. Contractors also unwittingly accept design risk through performance specifications, and the accompanying obligations and risks are underestimated by those tasked with the initial review of those documents. In sum, a clear scope is as important as clear terms and conditions.
Reprinted courtesy of
Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Insurance Policy’s “No Voluntary Payment” Clauses Lose Some Bite in Colorado
October 22, 2013 —
Brady Iandiorio — Higgins, Hopkins, McLain & Roswell, LLC.The Colorado Court of Appeals recently handed down an opinion dulling the teeth of the “no voluntary payment” clauses found in many contractors’ insurance policies. In the case of Stresscon Corporation v. Travelers Property Casualty Company of America, 2013 WL 4874352 (Colo. App. 2013), the Court of Appeals found that an insured’s breach of the “no voluntary payment” clause does not always bar the insured from receiving benefits from its insurance company.
In July 2007, at a construction project run by Mortenson (the “GC”), a partially erected building collapsed, killing one worker and gravely injuring another. The collapse was caused by a crane hook pulling a concrete component off of its supports. The GC contracted with Stresscon Corporation (“Stresscon”) to build pre-cast concrete components for the project, and in turn Stresscon hired two sub-subcontractors, RMS and Hardrock (the “Crane Team”) to work together to erect those concrete components. Stresscon and the Crane Team had liability insurance, and Stresscon was insured by Travelers Property Casualty Company of America (“Travelers”).
The accident led to three separate lawsuits: 1) one brought by the deceased worker; 2) one brought by the injured worker; and 3) one brought by the GC against Stresscon claiming it was entitled to contract damages incurred because the project was delayed.
Read the court decisionRead the full story...Reprinted courtesy of
Brady IandiorioBrady Iandiorio can be contacted at