Federal Miller Act Payment Bond Claim: Who Gets Paid and Who Does Not? What Are the Deadlines?
September 16, 2019 —
William L. Porter - Porter Law GroupWhen working on federal public works construction projects there are no Stop Payment Notice or Mechanics Lien remedies available to protect subcontractors’ and suppliers’ right to payment. Instead, unpaid subcontractors and suppliers must resort to making a claim for payment under a federal law known as the AMiller Act@ (40 USCS 3131 et seq.). Many claimants however, do not realize that the right to make a Miller Act claim is not available to all subcontractors and suppliers. Before committing to performing work on a federal project it is important for subcontractors and suppliers to understand whether or not a Miller Act claim will be available. For those who have no Miller Act rights, careful consideration must be given to whether it is worth the risk to take on the project. For those who have valid Miller Act claim rights, important deadlines must be considered.
Who Gets Paid Under a Miller Act and Who Does Not
For federal projects in excess of $100,000, contractors who have a contract directly with the Federal Government must obtain Miller Act Payment Bond intended for the protection of Subcontractors, laborers and material suppliers to the project.
As a general rule, every subcontractor, laborer, or material supplier who deals directly with the prime contractor and is unpaid may bring a lawsuit for payment against the Miller Act Payment Bond. Further, every unpaid subcontractor, laborer, or material supplier who has a direct contractual relationship with a first-tier subcontractor may bring such an action. The deadlines for these claims are described below.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Settlement Conference May Not Be the End in Construction Defect Case
February 21, 2013 —
CDJ STAFFThe builder has been sentenced to jail for theft. The building has been condemned over construction defects. And the settlement conference probably won’t bring an end to the case. The building in question is a condominium complex, located at 770 Sandy Street in Norristown, Pennsylvania. Bruce Fazio took out a $2.5 million construction loan to build it. And when it was done, there were inspections over construction defects, the building was condemned, and then the court ordered repair work. The city of Norristown has sued Fazio to recover the more than $1.5 million it took to repair the building and allow at least some condominium owners to move back in.
The suit alleges that Norristown officials failed to properly inspect the construction work, and that inspectors were not properly certified. Further, it is alleged that secretaries and clerks signed off on inspection reports and certificates of occupancy.
Read the court decisionRead the full story...Reprinted courtesy of
Expect the Unexpected (Your Design Contracts in a Post-COVID World)
April 18, 2023 —
Melissa Dewey Brumback - Construction Law in North CarolinaHave you adapted your post-COVID practice to better plan for the “unexpected” ? In particular, have you looked at–and revised– your professional services contracts to give yourself a little more breathing room for unaccounted issues that may arise? If not, no time like the present.
Don’t like that saying? How about ” a stitch in time saves nine?” No? Still nothing? What about a picture of something so completely unexpected it shocks you– say, a fireman commuting home, in fire-fighting regalia, on a tricycle? Okay, here you go…
Now that I have your attention– you should make it a practice to regularly review and update your professional services agreements, and you should consider issues such as:
- Does your agreement provide for extra compensation if you have to spend more time or a longer period providing construction administration services for material delays or labor shortages? If not, it should.
- Does your agreement have a well-written “act of God” provision– one that includes pandemic/epidemics as part of the “act of God” conditions in which a term may become void? If not, add it now!
Read the court decisionRead the full story...Reprinted courtesy of
Melissa Dewey Brumback, Ragsdale LiggettMs. Brumback may be contacted at
mbrumback@rl-law.com
Georgia Supreme Court Addresses Anti-Indemnity Statute
October 21, 2019 —
David R. Cook - AHC Construction and Procurement BlogIn prior blog posts, we addressed Georgia’s anti-indemnity statute. One of the posts addressed the statute in the context of an electric utility easement near an airport. That case made its way to the Supreme Court Georgia, which provided some additional clarity to the statute. Milliken & Co. v. Georgia Power Co., — Ga. –, 829 S.E.2d 111 (2019).
When a plane crashed and several passengers and crew died or were injured, their representatives sued several defendants, including a nearby plant owner, Milliken & Company (“Milliken”), based on claims that transmission lines on Milliken’s property were too close to the runways, were too high, and encroached on the airport easements. Milliken cross claimed against Georgia Power Company (“GPC”). Milliken’s claim was based on an easement it granted to GPC, which required GPC to indemnify it for any claims arising out of GPC’s construction or maintenance of the transmission lines.
On appeal, the Supreme Court considered whether the clause was unenforceable under O.C.G.A. § 13-8-2(b). In general, “a party may contract away liability to the other party for the consequences of his own negligence without contravening public policy, except when such agreement it prohibited by statute.” Id. at 113 citing Lanier at McEver v. Planners & Eng’rs Collaborative, 284 Ga. 204, 205 (2008). As one such statute, O.C.G.A. § 13-8-2(b) applies when an indemnification provision (i) “relates in some way to a contract for construction, alteration, repair, or maintenance of certain property” and (ii) “promises to indemnify a party for damages arising from that own party’s sole negligence.” Id. at 114 (internal punctuation omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David R. Cook, Autry, Hall & Cook, LLPMr. Cook may be contacted at
cook@ahclaw.com
New EPA Regulation for Phase I Environmental Site Assessments
January 27, 2014 —
Beverley BevenFlorez-CDJ STAFFThe EPA recently amended the “’All Appropriate Inquiries Rule’ concerning environmental site assessments of potentially contaminated sites,” reports the Schinnerer Risk Management Blog. Engineers will need to be aware that “Phase I assessments should now reference ASTM International’s E1527-13 “Standard Practice for Environmental Site Assessments: Phase I Environmental Site Assessment Process” in order to comply with the All Appropriate Inquiries Rule.”
Read the court decisionRead the full story...Reprinted courtesy of
Evolving Climate Patterns and Extreme Weather Demand New Building Methods
May 22, 2023 —
Annette Rubin - Construction ExecutiveCompared to the rest of the world, most buildings in the United States are relatively young. But most residential and commercial properties could use a makeover. Buildings constructed over twenty, fifty and one hundred years ago are, unsurprisingly, not as energy-efficient or as safe as new builds following modern methods—especially when considering the effects of climate change and more frequent extreme weather events on the integrity of that infrastructure.
According to the National Association of Home Builders, over 90% of new homes built in the United States today are wood-framed. These homes are incapable of withstanding a tornado or hurricane, yet they are still being built directly in the path of storms. Even buildings constructed in some of the most earthquake-prone areas of the U.S. may contain design flaws that make them susceptible to damage because they are built using a non-ductile concrete method, which experts say has an inadequate configuration of steel reinforcing bars—making the building vulnerable when shaken. While this building method was banned for new construction, it is not yet required to retrofit older construction to improve safety and structural integrity.
Reprinted courtesy of
Annette Rubin, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Additional Insured Not Entitled to Indemnity Coverage For Damage Caused by Named Insured
February 23, 2017 —
Tred R. Eyerly – Insurance Law HawaiiThe additional insured unsuccessfully sought to recover damages to its building caused by the named insured. Brit UW, Ltd. v. Tripar, Inc., 2017 U.S. Dist. LEXIS 2462 (N.D. Ill. Jan. 6, 2017).
Davis Russell Real Estate and Management LLC hired Tripar, Inc., a general contractor, to renovate a 12-unit apartment building. The entire roof was to be replaced by a roofing subcontractor. Davis Russell drafted a Professional Services Agreement (PSA) that governed the project. Tripar was to obtain a CGL policy and provide a certificate of insurance evidencing the coverage. Davis Russell was to be named as an additional insured.
Tripar's insurance broker prepared a certificate of insurance reflecting that a CGL policy was issued to Tripar by Brit UW, Ltd. But the certificate clearly stated that it was not issued by the insurer and that it did not alter coverage. The certificate of insurance further stated that it conferred no rights upon the holder.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Unqualified Threat to Picket a Neutral is Unfair Labor Practice
January 08, 2019 —
Wally Zimolong - Supplemental ConditionsOn December 27, 2018, the National Labor Relations Board enforced a decades old policy that a union’s unqualified threat to picket a neutral employer at a “common situs” a/k/a a construction site is a violation of the National Labor Relations Act.
Background
The case involved area standards picketing by the IBEW of a project owned by the Las Vegas Convention and Visitors Authority (LVCVA). The IBEW sent a letter to various affiliated unions who were working on the project advising them of its intent to engage in area standards picketing at the project directed to the merit shop electrical subcontractor performing work there. The IBEW also sent a copy of the letter to the LVCVA.
Read the court decisionRead the full story...Reprinted courtesy of
Wally Zimolong, Zimolong LLCMr. Zimolong may be contacted at
wally@zimolonglaw.com