Court Denies Insured's Motion to Dismiss Complaint Seeking to Compel Appraisal
March 13, 2023 —
Tred R. Eyerly - Insurance Law HawaiiThe court denied the insured's motion to dismiss after the insurer filed suit to compel an appraisal. Allied Trust Ins. Co. v. Tsang, 2023 U.S. Dist. LEXIS 352 (E.D. La. Jan. 3, 2023).
The insureds reported damage to their property arising from Hurricane Ida. The insurer, Allied Trust, investigated and determined that the covered damage was $1,978.18, which was less that the policy's deductible. The insureds estimated that the covered damage was $135,270.78.
Allied Trust invoked the appraisal provision. Allied Trust later filed suit alleging the insureds failed to comply and participate in the appraisal. The insureds moved to dismiss the complaint as moot. In their motion, the insureds argued that because they were now complying with the appraisal clause, all relief sought by Allied Trust had either already occurred or was currently underway.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Pending Home Sales in U.S. Increase Less Than Forecast
October 29, 2014 —
Michelle Jamrisko – BloombergThe number of contracts to buy existing homes rose less than forecast in September, signaling demand will probably plateau heading into the end of 2014.
The pending home sales index increased 0.3 percent after dropping 1 percent in August, the National Association of Realtors said today in Washington. The median projection in a Bloomberg survey of economists called for a 1 percent gain.
Home resales have yet to regain last year’s peak as still-tight credit and low inventories remain hurdles for the industry, which means residential real estate will make a limited contribution to the expansion. The recent drop in mortgage rates and pickup in hiring will probably help underpin demand, even as first-time buyers struggle to enter the market.
Read the court decisionRead the full story...Reprinted courtesy of
Michelle Jamrisko, BloombergMs. Jamrisko may be contacted at
mjamrisko@bloomberg.net
Contractor Side Deals Can Waive Rights
October 02, 2023 —
Christopher G. Hill - Construction Law MusingsHere at Construction Law Musings, we are quite fond of the Federal Miller Act and it’s Virginia counterpart, the “Little” Miller Act. Both of these statutes allow a subcontractor or supplier on a government construction project the security to perform their work with the knowledge that a bonding company will back their claim for payment. These acts are necessary because a construction company cannot file a mechanic’s lien on a government owned piece of property.
As a general rule the Miller Acts impose almost strict liability on a contractor and its surety to pay for work performed by a downstream supplier or subcontractor. However, as a recent case out of the Fourth Circuit Court of Appeals makes clear, this rule is not without exceptions.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Construction Mezzanine Financing
March 29, 2017 —
Tim Davis & Steven Coury - White and Williams LLPConstruction mezzanine lending is on the rise and more development deals are getting done with a capital stack that includes mezzanine debt in addition to the traditional components of sponsor equity and senior mortgage debt. Below are important issues and concepts to bear in mind when structuring the financing of a construction project that includes a mezzanine debt component.
Funding Sequence
Funding Sequence
When will the proceeds of the mezzanine loan be advanced? In some instances, the mezzanine loan proceeds will be advanced only after all of the borrower’s equity has been contributed to the construction of the project. In other instances, the borrower’s equity and the mezzanine loan proceeds go in either pari passu or simultaneously at another ratio. If the equity is not entirely contributed in advance, the mezzanine lender may require that the uncontributed equity be held by the mezzanine lender or held in a pledged account. The mezzanine lender may also further mitigate the risk of non-funding of the equity by requiring an equity funding guaranty (as discussed below).
Additionally, when will the mezzanine loan proceeds be advanced in relation to the senior mortgage loan proceeds? Will the entire mezzanine loan be advanced prior to any senior mortgage loan advance or will they be advanced pari passu? Depending on the business deal, the mezzanine loan agreement will need to reflect how and when the equity, the mezzanine debt, and the mortgage debt will be advanced.
Reprinted courtesy of
Tim Davis, White and Williams LLP and
Steven Coury, White and Williams LLP
Mr. Davis may be contacted at davist@whiteandwilliams.com
Mr. Coury may be contacted at courys@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
Reasonableness of Liquidated Damages Determined at Time of Contract (or, You Can’t Look Back Again)
October 05, 2020 —
Christopher G. Hill - Construction Law MusingsI’ve discussed the continuing litigation between White Oak Power Constructors v. Mitsubishi Hitachi Power Systems Americas, Inc. previously here at Construction Law Musings because the case was another reminder that your construction contract terms matter and will be interpreted strictly here in the Commonwealth of Virginia. The prior opinion in this case from the Eastern District of Virginia court the Court considered the applicability of a liquidated damages provision. In the latest opinion from the Court (PDF) the Court looked at when and how any liquidated damages would be calculated. In its June 22, 2020 opinion, the Court put the issue as follows:
White Oak’s motion for partial summary judgment presents a narrow issue: whether courts may consider the damages actually sustained by a party as a result of a contract breach when deciding if liquidated damages required by a contract “grossly exceed” a party’s actual damages.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Subcontractor Strikes Out in its Claims Against Federal Government
July 08, 2024 —
David Adelstein - Florida Construction Legal UpdatesIs it a good idea for a subcontractor to sue the federal government? A recent case would suggest NO–way too many huge hurdles for the subcontractor to overcome. No matter how creative the arguments may be, it’s a high mountain to climb.
In Fox Logistics & Construction Co. v. U.S., 2024 WL 2807677 (Fed.Cl. 2024), a subcontractor sued the federal government when it was not paid by the prime contractor. The subcontractor claimed it was a third-party beneficiary under the government’s modifications to the prime contractor’s payment procedure, or alternatively it had an implied-in-fact contract with the government. The Court of Federal Claims granted summary judgment in favor of the government. The subcontractor, while creative, struck out in its claims based on the hurdles in a subcontractor suing the federal government.
This case involved upgrading an air force base. The subcontractor performed most of the work. The prime contractor had cash flow problems and did not pay the subcontractor. The government got involved to enforce provisions of its contract to force the prime contractor to pay subcontractors and even modified the payment procedure by having future payments to the prime contractor deposited into a new bank account that government could monitor. This ultimately did not work, and the prime contractor filed for bankruptcy. The subcontractor claimed it was owed millions–apparently, it was not able to recover the money through the prime contractor’s bankruptcy—and pursued claims against the federal government in an effort to recover money it was owed.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Resumes after Defects
June 28, 2013 —
CDJ STAFFWhen inspectors found defective bolts in the construction of the Media Arts Center at L. A. Mission College, the contractor walked off the job. The project had been underway for about eighteen months. After problems were found with welds and bolts, the contractor informed the school that it could not complete the job. The California Division of the State Architect then required inspection of every weld and joint, leading to a dispute as to who was going to pay for it.
At this point, only the first story has been inspected. Although the other two stories must be inspected, the new contractor is about to begin work on the building. James O’Reilly, the executive director for facilities, planning and development, said that “the main focus is on fixing the defective issues and getting construction completed so we can serve the Mission campus.” Still at question is how much SMC Construction received before they walked off the job.
Read the court decisionRead the full story...Reprinted courtesy of
The Future of Construction Tech Is Decision Tech
August 06, 2019 —
Bassem Hamdy - Construction ExecutiveIt doesn’t take much to be catastrophically wrong in construction; some bad information, a touch of misleading intel, a few biased opinions mixed with human error and perhaps a little bad luck to top it off. A poor decision early in a project plants itself like a weed—it grows benignly at first, and becomes gravely pervasive at the end.
Being wrong in construction is dangerous. Error leads to leaning towers and broken buildings. Poorly-built structures can hinder economic growth and deprive communities of good infrastructure. For the enterprise, bad decisions can lead to massive financial loss and—worse—human loss on a jobsite.
Despite knowing all the dangers, it seems that flawed data, misleading intel and human error have become traits the industry can’t shake. To be clear, construction is one of—if not the most—complex industry in today’s economy. Companies walk a tight rope between a 2% margin on one side and ruinous loss on the other. Under such conditions, it’s easy to see why sustained good judgement is difficult.
Reprinted courtesy of
Bassem Hamdy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of