Denial of Motion to Dissolve Lis Pendens Does Not Automatically Create Basis for Certiorari Relief
November 16, 2023 —
David Adelstein - Florida Construction Legal UpdatesA recent appellate decision out of Florida’s Sixth District Court of Appeal holds that a trial court’s denial of motion to dissolve a lis pendens does NOT automatically give a basis for a petition for a writ of certiorari. Generalized allegations of “irreparable harm” to support the basis for the petition for writ of certiorari are insufficient. Rather, the party moving for the petition MUST clearly demonstrate the irreparable harm; otherwise, the petition for writ of certiorari will fail.
A lis pendens has legal significance. It is a recorded document that notifies the world that there is a pending lawsuit dealing with the real property at issue. This is important because who wants to buy a piece of property that is subject to litigation – that would be a risky transaction!
In CPPB, LLC v. Taurus Apopka City Center, LLC, 48 Fla.L.Weekly D1837a (Fla. 6th DCA 2023), a dispute arose as to a real estate transaction. The owner sold a parcel to a buyer. The owner also owned three adjacent parcels. As part of the transaction, the buyer agreed to perform certain improvements to all of the parcels including those adjacent parcels owned by the owner. The owner deposited funds in escrow for purposes of its share of the improvements. A payment dispute arose regarding the improvements and the buyer sued the seller. The seller filed a counterclaim to rescind the transaction along with a recorded lis pendens on the parcel purchased by the buyer. The buyer moved to dissolve the lis pendens which the trial court denied. This prompted the appeal – a petition for a write of certiorari based on the trial court’s denial of the motion to dissolve the lis pendens.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Attorney-Client Privilege in the Age of Cyber Breaches
October 18, 2021 —
Shaia Araghi - Newmeyer DillionInvestigations and forensic reports relating to a cybersecurity breach may not always be protected by the attorney-client privilege or work product protection. Companies seeking such reports after a data breach must take caution to protect them from a possible waiver of privilege in the event of subsequent litigation relating to a data breach. The following recent cases highlight the potential waiver of privilege in light of the preparation of a forensic report.
- In re Capital One Consumer Data Security Breach Litigation, 2020 WL 3470261 (E.D. Va. June 25, 2020)
- After a data breach occurred, Capital One retained a law firm that later entered into an agreement with Mandiant for various cyber-related services (including incident remediation), which required that Mandiant provide deliverables to the firm, rather than to Capitol One. In re Capital One Consumer Data Security Breach Litigation, 2020 WL 2731238, at *1 (E.D. Va. June 25, 2020). Plaintiffs sought release of the report created by Mandiant (regarding the factors leading to the breach), arguing that it was prepared for business and regulatory purposes and therefore was not privileged, while Capital One argued that the report was privileged because it was prepared in anticipation of litigation. Ibid. The Court determined that Capital One did not carry its burden of establishing that the report was protected by the attorney work-product doctrine and ordered that Capital One produce the report. Id. at *7. In its reasoning, the Court stated that the fact that there is litigation does not, by itself, provide prepared materials with work-product protection. Ibid. The work-product protection applies when a party faces a claim following an event that may result in litigation, and the work product would not have been prepared in a substantially similar form but for the prospect of that litigation. Ibid.
Read the court decisionRead the full story...Reprinted courtesy of
Shaia Araghi, Newmeyer DillionMs. Araghi may be contacted at
shaia.araghi@ndlf.com
Colorado Nearly Triples Damages Caps for Cases Filed in 2025, Allows Siblings to File Wrongful Death Claims
July 22, 2024 —
Amy Johnson - Lewis BrisboisDenver, Colo. (June 13, 2024) - On June 3, 2024, Colorado Governor Jared Polis signed HB24-1472 to increase the damages caps for personal injury and wrongful death claims. The law nearly triples the amounts available to plaintiffs, which will continue to increase for inflationary adjustments beginning in 2028 and every two years thereafter. These new damages caps affect not only claims that accrue in 2025 and beyond, but they also change the caps for any civil cases filed on or after January 1, 2025. This law was enacted as a compromise to a ballot measure that would have removed any cap on damages. The new caps are as follows:
- The cap on noneconomic damages for personal injuries will be $1.5 million.
- The cap on noneconomic damages for wrongful death will be $2.125 million.
Plaintiffs are likely to delay filing new actions through the rest of 2024 as long as they are not up against a statute of limitations deadline.
Read the court decisionRead the full story...Reprinted courtesy of
Amy Johnson, Lewis BrisboisMs. Johnson may be contacted at
Amy.Johnson@lewisbrisbois.com
California Court Invokes Equity to Stretch Anti-Subrogation Rule Principles
June 18, 2019 —
Gus Sara & William L. Doerler - The Subrogation StrategistIn Western Heritage Ins. Co. v. Frances Todd, Inc. 2019 Cal. App. Lexis 299, the Court of Appeals of California, First Appellate District, addressed whether a commercial condominium association’s carrier could subrogate against the tenants (aka lessees) of one of its member unit owners. After examining the condominium association’s declarations, as well as the lease terms between the owner and the lessees, the court held that the association’s carrier could not subrogate against the lessees because they were implied co-insureds on the policy. To reach its decision, the court explained that an insurer steps into the shoes of its insured, not the party with whom it is in privity. Although the first-party property portion of the association’s insurance policy did not, as required by the association’s declarations, have the owner listed as an additional named insured, the court held that it would be inequitable to treat the association as the sole insured for purposes of determining Western Heritage’s right to bring a subrogation action.
In Western Heritage, William R. de Carion d/b/a Surfwood Properties (de Carion or Lessor), owned a commercial unit within a multi-unit commercial building. The building was managed by the East Shore Commercial Condominiums Owners’ Association (the Association). As a unit owner, de Carion was a member of the Association. The Association’s Declarations of Codes, Covenants and Restrictions (CC&Rs) required the Association to procure fire insurance for the commercial units by adding the unit owners as additional named insureds. The CC&Rs also prohibited owners and their “tenants” from procuring their own fire insurance policies for the premises. In 2013, de Carion leased his commercial space to Frances Todd, Inc. d/b/a The Wooden Duck, Eric Todd Gellerman and Amy Frances Feber (Lessees).
Reprinted courtesy of
Gus Sara, White and Williams LLP and
William L. Doerler, White and Williams LLP
Mr. Sara may be contacted at sarag@whiteandwilliams.com
Mr. Doerler may be contacted at doerlerw@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
With VA Mechanic’s Liens Sometimes “Substantial Compliance” is Enough (but don’t count on it) [UPDATE]
October 14, 2019 —
Christopher G. Hill - Construction Law MusingsVirginia mechanic’s liens are a powerful and tricky beast that in most cases require absolute precision in their preparation. However, an interesting opinion recently came out of the Virginia Supreme Court that may provide a bit of a “safe harbor” from the total form over function nature of a mechanic’s lien.
In Desai, Executrix v. A.R. Design Group Inc., the Court considered a lien memorandum that had what could be described as technical flaws in the preparation of the mechanic’s lien by A. R. Design Group. The basic facts are that A. R. Design Group used the form of lien found in Va. Code Sec. 43-5 (also found as Form CC-1512 at the Virginia Judiciary website) when it recorded two lien memoranda for two pieces of property owned by a trust. Relating to one of the two properties, the memorandum failed to identify the “Owner” as the trustee of the trust. On the memoranda relating to both properties the affidavit verifying the amounts claimed did not identify the signatory as agent for A. R. Design Group, instead listing the agent as the claimant and further failed to state a date from which interest is claimed or a date on which the debt was due.
Needless to say, the owner argued that each of these technical defects invalidated the memoranda and therefore they should have been released. Somewhat surprisingly the Fairfax, Virginia Circuit Court disagreed and held the liens to be valid. On appeal, the Virginia Supreme Court affirmed the lower court. The held that the failure to add the word “Trustee” after Ulka Desai’s name did not invalidate the lien because the trustee had all of the rights of ownership and furthermore that naming Desai in the memorandum served the purpose of putting third parties on notice of the lien.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
When is a “Notice of Completion” on a California Private Works Construction Project Valid? Why Does It Matter for My Collection Rights?
January 27, 2020 —
William L. Porter - Porter Law GroupWhat is a Notice of Completion?
A “notice of completion” is a document recorded by the owner of property where construction work was performed. Specifically, it is recorded at the Office of the County Recorder in the County where the work was performed. The notice of completion tells the world at large that the construction project is complete. It also triggers the deadlines for those who have not been paid to make their claims for payment.
Is an Owner of a California Private Works Project Required to Record a Notice of Completion?
No, there is no requirement that an owner of a California private works construction project record a Notice of Completion. However, there are consequences which depend on whether an Owner elects to record the notice or not.
For My Collection Rights, Why Does it Matter Whether a Notice of Completion Has Been Recorded?
The date of recording of a valid notice of completion sets the deadline for those who have not been paid for work performed and materials supplied to a California construction project to pursue such important collection remedies as the “mechanics lien”, the “stop payment notice” and the “payment bond claim.” These are very powerful collection remedies for those who have not been paid. If the deadline to pursue these remedies is missed by a claimant, then the claimant’s right to pursue these remedies is also missed. One of these remedies, the mechanics lien, will enable the claimant to sell the owner’s property where the work was performed in order to get paid.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Charles Carter v. Pulte Home Corporation
October 12, 2020 —
Michael Velladao - Lewis BrisboisIn Carter v. Pulte Home Corp., __Cal.App.5th__(July 23, 2020), the California Court of Appeal affirmed the entry of judgment in favor of subcontractors in connection with a Complaint for Intervention based on equitable subrogation filed by Travelers Property Casualty Company of America (“Travelers”) seeking to recover defense costs incurred in defending Pulte Home Corporation (“Pulte”) in an underlying construction defect lawsuit. The parties’ dispute arose out of Travelers’ defense of Pulte as an additional insured under policies issued to four subcontractors involved in the underlying construction defect lawsuit. Several subcontractors involved in the underlying construction defect lawsuit refused to defend Pulte based on the indemnity clauses in their subcontracts. Such clauses promised to indemnify Pulte as follows:
“all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (“Claims”) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte. . . .”
Pulte eventually settled the construction defect lawsuit and its claims against all of the subcontractors. Travelers ultimately paid $320,491.82 for Pulte’s defense and recovered $164,400 from some of the subcontractors. Travelers’ intervention in the underlying lawsuit was intended to recover the remaining $156,091.82 from the subcontractors that refused to indemnify Pulte for the defense of the construction defect lawsuit. In the underlying trial, Travelers argued that the subcontractors were obligated to pay defense costs on a joint and several basis (minus what Travelers had already recovered). The trial court did not agree and held that Travelers was not entitled to equitable subrogation for the remaining defense costs.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Doctrine of Avoidable Consequences as Affirmative Defense
January 31, 2018 —
David Adelstein - Florida Construction Legal UpdatesThe doctrine of avoidable consequences is an affirmative defense that can be used in certain property damage lawsuits. This is a defense that does not go to liability, but it goes to damages. This doctrine of avoidable consequences defense holds that a plaintiff cannot recover damages caused by a defendant that the plaintiff could have reasonably avoided . See Media Holdings, LLC v. Orange County, Florida, 43 Fla.L.Weekly D237c (Fla. 5th DCA 2018). Stated differently, if the plaintiff could have reasonably avoided the consequences of the damages caused by the defendant then the plaintiff cannot recover those damages. However, the defendant needs to prove this defense — the burden is on the defendant to establish this defense (ideally through expert testimony).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Florida Construction Legal UpdatesMr. Adelstein may be contacted at