Construction Law Alert: Concrete Supplier Botches Concrete Mix, Gets Thrashed By Court of Appeal for Trying to Blame Third Party
January 21, 2015 —
Steven M. Cvitanovic and Whitney L. Stefko – Haight Brown & Bonesteel LLPOn January 8, 2015, the Second Appellate district affirmed judgment of the lower court in State Ready Mix Inc. v. Moffatt & Nichol, and barred a concrete supplier from blaming a third party consultant for the concrete supplier's failure to deliver concrete that met project specifications.
In 2012, Major Engineering Marine, Inc. was hired by a project manager to construct a harbor pier in the Channel Islands Harbor. Major hired State Ready Mix, Inc. to supply the concrete for the project. State wrote and submitted a concrete mix design and, at the request of Major, civil engineer Moffatt & Nichol reviewed and approved State's mix design at no charge.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel LLP and
Whitney L. Stefko, Haight Brown & Bonesteel LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Stefko may be contacted at wstefko@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Insurer Not Bound by Decision in Underlying Case Where No Collateral Estoppel
February 25, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe Eleventh Circuit determined that the trial court did not err by refusing to give preclusive effect to findings made in the underlying state-court action because there was no collateral estoppel. Nationwide Mut. Ins. Co. v. Sharif, 2014 U.S. App. LEXIS 2114 (11th Cir. Feb. 4, 2014).
Bashir's owned a grocery and was insured by Nationwide. The decedent was accidentally killed by a pistol stored under the cash register. The decedent's personal representative sued Bashir in state court. Nationwide declined to defend because it maintained that the employment exclusion applied to bar coverage.
The personal representative argued two alternative claims, the first assuming the decedent was not an employee of Bashir's and the second assuming that he was. The state court granted a motion to dismiss the second claim that the decedent was an employee. In a subsequent trial, judgment was awarded against Bashir and another defendant in the amount of $950,000.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
The Business of Engineering: An Interview with Matthew Loos
July 15, 2019 —
Aarni Heiskanen - AEC BusinessMatthew Loos is an experienced project manager in the civil engineering industry. He works as a project engineer at Jones|Carter in Fort Worth, Texas. In this interview, we discuss Matt’s new book, The Business of Engineering.
It is not very common that an engineer writes a non-technical book. What inspired you to do so?
Have you ever gotten an idea stuck in your head that you just couldn’t let go of? A time when you couldn’t go to sleep because the idea was consistently begging for your attention?
That’s what happened to me. The idea for this book hits me right before bed, as most good ideas do. I couldn’t go to sleep after the idea struck me. I spent half of the night writing the chapters of this book in my mind. I had been thinking about the idea of engineering and how it relates to other career fields, even the non-technical ones. I was disenchanted with the trifling number of classes I took that prepared me for the business world. These were the initial thoughts that eventually led me down the road into thinking about engineering as a profession going forward.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Revisiting Termination For Convenience Clauses In Uncertain And Ever-Changing Economic Times
February 27, 2023 —
Adam M. Tuckman & Brittney M. Wiesner - ConsensusDocsIn these times of persistent inflationary forces and efforts to tame the consequences through rising interest rates, economic uncertainty abounds in the United States and around the world. As an approximately $1 trillion contributor to the economy in the United States (4.2% of GDP in 2021) alone according to the Associated General Contractors of America, the health and the growth of the construction industry is certainly susceptible to these rapidly changing macroeconomic conditions.
Presently, an unanswered question is how project developers will react to unpredictable fluctuations in project costs and interest rates. Although it seems unlikely to be a prevalent response, it is possible that substantial increases in borrowing, labor, or material costs would cause owners to pull the plug on projects that are in the advanced stages of construction. For projects in the nascent stages of development or construction, however, the calculous for owners becomes more tenuous. Both public and private owners may find it more prudent to indefinitely suspend or cancel pending or ongoing projects due to any, or a combination of, forecasted increases in project costs, shrinking funding, higher borrowing costs, or macro-economic uncertainty. Facing this quandary, how would an owner already under contract with a constructor and design team suspend or cancel its project? One potential approach is to invoke a termination for convenience clause found in the parties’ contract.
Reprinted courtesy of
Adam M. Tuckman, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs) and Brittney M. Wiesner, Watt, Tieder, Hoffar, & Fitzgerald, LLP (ConsensusDocs)
Mr. Tuckman may be contacted at atuckman@watttieder.com
Read the court decisionRead the full story...Reprinted courtesy of
Emergency Paid Sick Leave and FMLA Leave Updates in Response to COVID-19
April 06, 2020 —
Yvette Davis & Kyle R. DiNicola - Haight Brown & BonesteelThe Families First Coronavirus Response Act (“FFCRA”) was signed by the President on March 18, 2020 and will become effective no later than April 2, 2020. The law contains numerous updates to the country’s employment regulations in response to the Coronavirus pandemic of which employers should be familiar.
Of particular note, the FFCRA makes limited amendments to the Family and Medical Leave Act. Now, pursuant to the Emergency Family and Medical Leave Expansion Act (“EFMLEA”) employees may take up to 12 weeks of family and medical leave after having worked with the employer for 30 calendar days if the employee is unable to work (or telework) due to the employee’s need to care for a son or daughter under 18 years of age due to the child’s school closure or unavailability of a childcare provider due to a public health emergency, i.e., COVID-19. Unlike the FMLA, which does not apply to many small employers, this requirement applies to any employers with 500 or fewer employees. No mileage radius requirement exists under the EFMLEA.
When an employee utilizes leave pursuant to EFMLEA, the first 10 days of that leave may consist of unpaid leave, but the employee may elect to substitute any accrued paid vacation leave, personal leave, or medical or sick leave, including the Emergency Paid Sick Leave provided for by the Act and described below). All subsequent days of leave taken by the employee after the tenth day must be paid by the employer at a rate of not less than two thirds of the employee’s regular rate of pay and the number of hours the employee would otherwise normally be scheduled to work. The cap is $200 per day or $10,000 in the aggregate.
Reprinted courtesy of
Yvette Davis, Haight Brown & Bonesteel and
Kyle R. DiNicola, Haight Brown & Bonesteel
Ms. Davis may be contacted at ydavis@hbblaw.com
Mr. DiNicola may be contacted at kdinicola@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Defects and Second Buyers in Pennsylvania
February 07, 2013 —
CDJ STAFFThe ability to sue over construction defects has typically been limited to the initial purchaser of a home. But as Kevin F. McKeegan writes in the Pittsburgh Post-Gazette, the Pennsylvania Superior Court recently expanded that to subsequent purchasers. As Mr. Keegan notes, "not only can the first buyer of a new home bring a lawsuit against a builder, but now any subsequent buyer within 12 years of the home's construction can file a claim."
Mr. Keegan, a lawyer with Meyer, Unkovic & Scott, notes that in the underlying case, the second owners of a home in Jamison, Pennsylvania filed a claim that the water infiltration violated the "implied warranty of habitability."
There are still limitations on construction defects in Pennsylvania. The suit must be filed within twelve years of completion of the construction, and a breach of implied warranty must be proven. Mr. Keegan notes that "the homeowner must show that a defect is hidden and non-obvious, that it is the result of the builder's design or construction, and that it affects the habitability of the residence."
Read the court decisionRead the full story...Reprinted courtesy of
BIM Meets Reality on the Construction Site
September 25, 2018 —
Aarni Heiskanen - AEC BusinessBIM models are mostly used by foremen on construction sites. But what if they could be made available for workers at the press of a button? This question was what the Finnish government-funded KIRA pilot project set out to answer. As a by-product, the project also produced augmented reality (AR) solutions for construction sites.
The research project was called ”Digitalization of a construction project based on role and location information” (RoPa). It was conducted by construction company Fira and engineering consultancy Sweco.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Risky Business: Contractual Versus Equitable Rights of Subrogation
December 16, 2023 —
Kyle Rice - The Subrogation StrategistIn Zurich Am. Ins. Co. v. Infrastructure Eng’g. Inc., 2023 Ill. App. LEXIS 383, the insurer, Zurich American Insurance Company (Insurer) proceeded as subrogee of Community College District No. 508 d/b/a City Colleges of Chicago and CMO, a Joint Venture. The Appellate Court of Illinois, First District (Appellate Court) addressed whether Insurer – who issued a builder’s risk policy to insure a building during construction – could subrogate on behalf of the building owner, City Colleges of Chicago (City Colleges), who was part of the joint venture and an additional named insured, but who had not been directly paid for the underlying loss. The Appellate Court determined that the policy language established that the carrier was contractually permitted to subrogate on behalf of all additional named insureds on the policy, including the building owner.
Read the court decisionRead the full story...Reprinted courtesy of
Kyle Rice, White and WilliamsMr. Rice may be contacted at
ricek@whiteandwilliams.com