Approaching Design-Build Projects to Avoid (or Win) Disputes
August 07, 2023 —
Stuart Eisler - Construction ExecutiveStakeholders engage in design-build projects believing the collaborative nature better aligns parties' interests and reduces overall risk exposure. Each of the lead parties bases this belief on different factors—the owner sees an opportunity to reduce change-order exposure and improve delivery times, the design-builder (or contractor) aims to control design volatility by ensuring project components match budgeted projections, and the designer intends to benefit by greater constructability review from the design-builder team and often additional time to detail designs. Rarely do design-build parties contemplate claims arising while initiating a project.
This being said, design-build projects carry unique, inherent risks due to the award of often fixed-price contracts utilizing incomplete, preliminary designs. As scopes creep and costs balloon, previously harmonious parties experience discord and lurking claims. While the majority of design-build projects are completed without major dispute, there are strategies available to further avoid disputes and prevail in those that are unavoidable.
Reprinted courtesy of
Stuart Eisler, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Meet the Forum's In-House Counsel: J. PAUL ALLEN
May 28, 2024 —
Jessica Knox - The Dispute ResolverCompany: Fischer Homes
Email: paul@jpaulallen.com
Law School: Chase College of Law at Northern Kentucky University (JD 1992)
States Where Company Operates/Does Business: Kentucky, Ohio, Indiana, Georgia, Missouri, Florida
Q: Describe your background and the path you took to becoming in-house counsel.
A: I started at a large Cincinnati firm straight out of law school. I moved in-house for a client of the firm after about 8 years and have remained in-house ever since. The in-house experience has been rewarding and varied over the last 24 years. I have worked for a Fortune 500, publicly traded steel company, a private equity led construction products company, and, finally, a family-owned residential homebuilder. I had the good fortune to be General Counsel at the last 2 in-house companies and was able to establish a legal department from scratch at Fischer Homes. As time went on and I gained experience, I stayed in-house because of the ability to work for a single client and have a greater impact on the business side of things.
Read the court decisionRead the full story...Reprinted courtesy of
Jessica Knox, Stinson LLPMs. Knox may be contacted at
jessica.knox@stinson.com
Another Colorado Construction Defect Reform Bill Dies
May 07, 2014 —
Beverley BevenFlorez-CDJ STAFFColorado construction defects reform Senate Bill 220 died when “Senate President Morgan Carroll, D-Aurora, declined to call a second committee to hear” the bill, according to Ed Sealover writing for the Denver Business Journal. Sen. Carroll declared that the “bill backers” did not incorporate any of the “suggestions she or House Speaker Mark Ferrandino had given them.”
“SB 220 would have required condo-unit owners to submit to alternative-dispute resolution such as arbitration or mediation if the unit developer required it,” Sealover reported. “And it would have required that a majority of members of a homeowners association agree to file a lawsuit, a standard significantly larger than the two-person bar that now must be met.”
Bill Cosponsor Sen. Mark Scheffel, R-Castle Rock, “believes litigation reform” will become “an election issue and” that it “has strong momentum heading into the 2015 session.”
Read the court decisionRead the full story...Reprinted courtesy of
40 Year Anniversary – Congratulations Ed Doernberger
November 23, 2016 —
Tracy Alan Saxe - Saxe Doernberger & Vita, P.C.Forty years ago, on the Big Island of Hawaii,
Edwin L. Doernberger was sworn in as an attorney. Fifteen years ago, Ed rejoined two former partners to help build an exciting new boutique insurance policyholder practice. Today, Saxe Doernberger & Vita is pleased to celebrate the 40th anniversary of its most distinguished partner.
“Ed’s energy and enthusiasm are undiminished,” said co-founder and Managing Partner, Tracy Alan Saxe. “He’s still one of the firm’s most active litigators.” Ed has extensive appellate experience, having argued before the Connecticut and Hawaii Supreme and Appellate Courts, New York Appellate Courts, and the Second and Ninth Circuits.
Read the court decisionRead the full story...Reprinted courtesy of
Tracy Alan Saxe, Saxe Doernberger & Vita, P.C.Mr. Saxe may be contacted at
tas@sdvlaw.com
Luxury Homes Push City’s Building Permits Past $7.5 Million
December 30, 2013 —
CDJ STAFFThe city of Ardmore, Oklahoma is seeing a building boom with the total value of building permits issued by the city in November slightly exceeded $7.5 million, reports Ardmoreite.com. Most of that total comes from residential construction, with the bulk of it coming from just three homes. While Lance Windel Construction plans on building 46 homes, the top value of those homes will be $153,000. The total value for the homes being built by three other firms is more $6.4 million, and those contractors are building just one home each.
Read the court decisionRead the full story...Reprinted courtesy of
Liquidated Damages: Too High and It’s a Penalty. Too Low and You’re Out of Luck.
November 21, 2022 —
Christian Fernandez - Snell & Wilmer Real Estate Litigation BlogLiquidated damages provisions in commercial and residential real estate contracts play a vital role when a transaction goes south, and should be given careful consideration when negotiating a real estate contract. Liquidated damages may be referred to in a variety of ways, such as “earnest money,” a “good-faith deposit,” or a “non-refundable deposit,” but each typically denote a negotiated amount of money that a seller is entitled to retain should a buyer breach a purchase and sale agreement. The purpose of liquidated damages is to provide the parties with certainty when actual damages arising from a breach of contract may be difficult to calculate. Accordingly, liquidated damages provisions alleviate the need for potentially expensive litigation associated with proving damages.
While parties are free to negotiate the amount of liquidated damages, the amount must approximate the loss anticipated at the time of contracting, or the loss that actually occurs as a result of a breach. Arizona courts have held that where the amount of liquidated damages is unreasonably large when compared to the anticipated loss or actual loss, the liquidated damages provision is unenforceable as a penalty. A breaching party faced with high liquidated damages will often seek to invalidate the provision as a penalty. If a court agrees, the non-breaching party may still recover damages, but must go through the process of proving such damages. Therefore, when negotiating a real estate contract, consideration should be given as to whether a liquidated damages amount is arbitrarily high when compared to an anticipated loss in the event of a breach.
Read the court decisionRead the full story...Reprinted courtesy of
Christian Fernandez, Snell & WilmerMr. Fernandez may be contacted at
cfernandez@swlaw.com
Attorney's Erroneous Conclusion that Limitations Period Had Not Expired Was Not Grounds For Relief Under C.C.P. § 473(b)
February 27, 2019 —
David W. Evans & Stephen J. SquillarioIn Jackson v. Kaiser Foundation Hospitals, Inc. (2/8/19 No. A150833), the First District Court of Appeal affirmed the trial court’s denial of a motion for relief from a voluntary dismissal, without prejudice, filed by the plaintiff based on the erroneous conclusion of an attorney who she had consulted (but who had not yet appeared as counsel in her case) that the applicable statute of limitations had not yet expired. In reality, the limitations period had expired on the same date plaintiff had filed her complaint in propria persona. The plaintiff later retained the attorney on a limited basis to present the motion for relief pursuant to Code of Civil Procedure § 473(b) based on the attorney’s affidavit of fault. Therein, the attorney testified that he had advised the plaintiff to dismiss her action voluntarily based on a misinterpretation of the applicable limitations period, which the attorney characterized as having been based on his “mistake, inadvertence, surprise, or neglect.”
Section 473 provides two distinct provisions for relief from default or dismissal – one is discretionary, while the other is mandatory. Discretionary relief is available in the case of an attorney’s mistake, inadvertence, surprise, or excusable neglect. In contrast, mandatory relief is available where the resulting dismissal was caused by an attorney’s mistake, whether or not excusable. In denying the plaintiff’s motion, the trial court reasoned that the plaintiff could not rely upon Section 473(b) because (1) the attorney did not represent the plaintiff at the time and (2) this provision did not apply to the voluntary dismissal of an action without prejudice.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Six-Month Prison Term for Role in HOA Scam
January 28, 2013 —
CDJ STAFFBen Kim, the former police lieutenant whose wife is one of the figures in the scheme to take over Las Vegas homeowner associations in order to profit from construction defect settlements, might face a six-month sentence in a bank fraud scheme. Mr. Kim has plead guilty in the charges that he submitted false financial documents. Others who were involved in the homeowner scandal, including Mr. Kim's wife, were also involved in this case.
Read the court decisionRead the full story...Reprinted courtesy of