Illinois Court Determines Duty to Defend Construction Defect Claims
March 22, 2021 —
Tred R. Eyerly - Insurance Law HawaiiGiven the underlying allegations of damage to personal property, the court determined the insurer had a duty to defend. Certain Underwriters at Lloyd's London v. Metropolitan Builders, Inc., 2019 Ill. App. LEXIS 979 (Ill. Ct. App. Dec. 18, 2019).
Metropolitan was hired as the general contractor for construction, renovation and demolition at contiguous properties - the 1907 Property, 1909 Property, and 1911 Property. During construction activities, the structures on the 1907 Property and 1909 Property collapsed. The existing structures on the properties were later deemed unsafe and were demolished by the city of Chicago.
AIG insured the owner of the buildings and paid over $1.8 million for repairs and associated expenses arising from the collapse. AIG then invoked its rights of subrogation against Metropolitan by filing suit. Metropolitan tendered the suit to its insurer, Lloyd's, who denied coverage and filed for a declaratory judgment. The trial court found the underlying complaint alleged property damage, but not an occurrence. Summary judgment was awarded to Lloyd's.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Surviving the Construction Law Backlog: Nontraditional Approaches to Resolution
June 07, 2021 —
Jeffrey Kozek - Construction ExecutiveAcross the construction industry, COVID-19’s impact has caused a range of problems for contractors and projects—prolonged or intermittent work shutdowns, supply chain delays, pricing increases on materials and funding shortfalls. It has also led to court closures. The legal backlog for claims and disputes means that owners and contractors are facing the option of waiting until the courts are functioning the way they were previously or utilizing alternative approaches to resolution to keep projects and businesses running.
Though courts across the country reopened to some extent in the latter half of 2020, many state and federal facilities were shut down or working with a limited capability for weeks or months. The closures not only froze the progress of numerous disputes already underway, but caused new schedule, cost and COVID-19-related claims to also be held up in the same backlog that is slowly being addressed under current restricted operations. New safety measures to reduce viral transmission, including reduced usage of courtrooms, restrictions on personnel and increased cleaning and sanitizing measures, have limited the number of cases courts can handle on a daily basis and lengthened legal timelines in ways many parties had not anticipated and cannot afford.
Reprinted courtesy of
Jeffrey Kozek, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Lockton Expands Construction and Design Team
July 19, 2011 —
CDJ STAFFLockton Companies, LLC, the largest privately held independent insurance broker, has announced that it is expanding its construction and design team with the hiring of Karen Erger and Tom Miller.
Ms. Erger will provide professional liability practice management, loss prevention, contract and complex claims management consulting services to Lockton's architectural, engineering and construction clients in her role as Vice President, Director of Practice Management. Her background includes construction litigation at a leading construction law firm, professional liability claims defense and claims consulting for major professional liability underwriters.
Miller joins Lockton as a Senior Vice President within the Design and Construction Unit. His role will be dedicated to serving the needs of engineering, architecture and construction firms performing services around the globe. He has spent more than 15 years concentrating on professional liability for design professionals and contractors in multiple roles. He previously managed the professional liability underwriting of one of the largest construction insurers and has developed numerous manuscript insurance products as well as focused on strategic planning to enhance business unit opportunities.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Congratulations to Partner John O’Meara for Being Named as One of America’s Top 100 Civil Defense Litigators for Three Consecutive Years!
September 20, 2021 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPPlease join Bremer Whyte Brown & O’Meara, LLP in congratulating Woodland Hills Partner John O’Meara for being selected as one of America’s Top 100 Civil Defense Litigators for the third year in a row!
Membership among America’s Top 100 Civil Defense Litigators highlights the accomplishments of the nation’s most esteemed and skilled Civil Defense attorneys. Only 100 attorneys in each state receive this honor and candidates for membership are identified through third-party research or peer nominations by America’s Top 100 or elite attorneys in the community. Candidates are judged by the attorney’s lifetime legal achievements, professional experience, significant case results, peer reputation, client satisfaction, other notable honors, media notoriety, and community impact.
Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Policy Sublimit Does Not Apply to Business Interruption Loss
December 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiRefusing to give the sublimit in a flood policy an expansive reading, the court found that the sublimit did not apply to business interruption loss. Federal-Mogul Corp. v. Ins. Co. of Pa., 2015 U.S. Dist. LEXIS 137394 (E.D. Mich. Oct. 8, 2015).
The insured's facility in Thailand was damaged by flood. The parties stipulated that the insured suffered a loss of $64,500,000, which included $39,406,467 in property damage and $25,093,533 in time element loss (i.e., economic loss due to an inability to operate normally). The insurer paid $30 million, stating that the High Hazard flood zone provision in the policy limited the amount owed under the policy.
The insured argued the High Hazard sublimit applied only to physical loss or damage caused by the flood, and not to time element loss. Therefore, the insured was entitled to judgment on its time element loss claim for $29,093,533. The insurer argued it was entitled to judgment as a matter of law because the High Hazard sublimit applied to all loss caused by flood, including time element loss.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
What You Should Know About Liquidated Damages and Liability Caps for Delay and Performance Liquidated Damages
May 06, 2024 —
Chris Cazenave - ConsensusDocsLiquidated damage clauses are omnipresent in today’s construction contracts—often considered in early negotiations to provide a degree of certainty and limit financial liability.
There are two principal types of LDs appearing in construction contracts—(i.) damages for delay when a contractor fails to deliver a project by a certain milestone; and (ii.) performance damages when a contractor fails to meet specific performance requirements. Differentiating between LDs for delay and LDs for performance—especially when both LD types are combined in the same contract—is key to risk awareness and allocation during contract negotiations and throughout performance.
This article briefly outlines what you should know about LDs for delay and LDs for failing to meet certain performance requirements. The article also covers how contractors can allocate and cap risks based on risks each party can either manage, insure, or otherwise limit.
Read the court decisionRead the full story...Reprinted courtesy of
Chris Cazenave, Jones Walker LLPMr. Cazenave may be contacted at
ccazenave@joneswalker.com
FEMA Fire Management Assistance Granted for the French Fire
July 08, 2024 —
The Federal Emergency Management AgencyOAKLAND, Calif. – The Federal Emergency Management Agency's (FEMA) Region 9 Administrator authorized the use of federal funds on July 4 at 11:37 p.m. PDT / 2:37 a.m. EDT to assist the state of California to combat the French Fire burning in Mariposa County.
On July 4, the state of California submitted a request for a Fire Management Assistance Grant (FMAG). At the time of the request, the fire threatened approximately 1,019 homes in and around Mariposa, CA, population 1,300. 95% of the threatened homes are primary residences and 5% are secondary residences.
The fire started on July 4, 2024 and had burned more than 790 acres of State and private land. The fire was 0% contained. There are five large fires burning uncontrolled within the State.
FMAGs provide federal funding for up to 75 percent of eligible firefighting costs. The Disaster Relief Fund provides allowances for FMAGs through FEMA to assist in fighting fires that threaten to become a greater incident.
Eligible costs covered by FMAGs can include expenses for field camps, equipment use, materials, supplies and mobilization, and demobilization activities attributed to fighting the fire.
For more information on FMAGs, visit https://www.fema.gov/assistance/public/fire-management-assistance.
Read the court decisionRead the full story...Reprinted courtesy of
New Highway for Olympics Cuts off Village near Sochi, Russia
February 07, 2014 —
Beverley BevenFlorez-CDJ STAFFA new highway costing $635 million was built in Sochi, Russia to support this month’s Winter Olympic Games—but the “shining” highway has cut off residents of the Village of Akhtyr, according to The Spokesman-Review. The online publication reports that while the Olympics will showcase the “luxury malls, sleek stadiums and high-speed train links, thousands of ordinary people in the Sochi area put up with squalor and environmental waste: villagers living next to an illegal dump filled with Olympic construction waste, families whose homes are sinking into the earth, city dwellers suffering chronic power cuts despite promises to improve electricity.”
One of the Sochi residents told KPAX News that what was once a “15-minute walk to get the bus to work has become a two-hour, cross-country trek. Military guards block their way to the rickety footbridge they used to use.” Furthermore, KPAX News claimed, “Heavy construction and traffic have chewed up the road through town and turned it into a dust bowl.”
Read the full story at The Spokesman-Review...
Read the full story at KPAX News... Read the court decisionRead the full story...Reprinted courtesy of