Texas Supreme Court Holds Stipulated Extrinsic Evidence May Be Considered in Determining Duty to Defend
May 10, 2022 —
Tred R. Eyerly - Insurance Law HawaiiResponding to certified questions from the Fifth Circuit, the Texas Supreme Court held that in limited circumstances, extrinsic evidence may be considered in determining the duty to defend. Monroe Guar. Ins. Co. v. Bitco Gen. Ins. Corp., 2022 Tex. LEXIS 148 (Tex. Feb. 11, 2022).
The two insurers each provided CGL coverage to the insured, 5D Drilling & Pump Service, Inc., at different times. BIitco provided two consecutive one-year CGL policies covering October 2013 to October 2015. Monroe's CGL policy covered 5D from October 2015 to October 2016.
5D was sued by David Jones for breach of contract and negligence, seeking damage allegedly resulting from 5D's drilling operations on Jones's property. Jones contracted with 5D in the summer of 2014 to drill a 3600-foot irrigation well on his farmland. The complaint did not detail when 5D's purportedly negligent acts occurred or even when 5D began or stopped the work.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Exploring Architects’ Perspectives on AI: A Survey of Fears and Hopes
March 19, 2024 —
Aarni Heiskanen - AEC BusinessRIBA, the Royal Institute of British Architects, ran a survey in late 2023 with 500 respondents on the impact of AI on their profession. The study also explored the near-term outlook for AI adoption and use. The results reveal divided opinions among architects. A popular view is that AI threatens the profession, even though a larger portion sees tools like AI as necessary in the coming years.
The Present Use of AI
The respondents were asked, for the projects they are currently working on, how often their practice used AI in any way.
In all, 41% said that they use AI to some degree. Of those, 43% agree that AI has improved efficiency in the architectural design processes, while 24% disagree.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
aec-business@aepartners.fi
Harvey's Aftermath Will Rattle Construction Supply Chain, Economists Say
September 07, 2017 —
Tim Grogan - Engineering News-RecordHurricane Harvey’s immediate impact on the construction sector will be a disruption in the supply chain for key materials, along with scheduling problems for projects that were under construction. As the cleanup and eventual rebuilding proceed, increased demand for materials and labor will push costs upward and contractors will be scrambling to secure supplies and workers.
Read the court decisionRead the full story...Reprinted courtesy of
Tim Grogan, ENRENR may be contacted at
ENR.com@bnpmedia.com
Construction Defect Headaches Can Be Avoided
February 21, 2013 —
CDJ STAFFConstruction defect claims can be an avoidable headache, if builders apply some forethought. Mark J. Peschel of Johnson & Lindberg, a Bloomington, Minnesota law firm, points out that simply says that windows should be weatherproofed by appropriate flashing, without any guidance on accomplishing that. He notes that “builders tend not to know the weatherproofing code provisions as well as they should.” Another lawyer, Eric S. Hayes of Brown and Carlson in St. Louis Park extends this, “it’s not just the building codes that need to be followed, but also the standards in the industry.”
Hayes notes that another way builders can avoid headaches is by being proactive. “I often hear, once things have gone sour and moved toward litigation, that the homeowner contacted the contractor a dozen times about a leaking basement and nothing was done, so they were forced to sue.” His advice for builders: “Don’t let it fester.”
Read the court decisionRead the full story...Reprinted courtesy of
Express Warranty Trumping Spearin’s Implied Warranty
March 06, 2022 —
David Adelstein - Florida Construction Legal UpdatesBe mindful of that express warranty provision in your contract. It could result in an outcome that you did not consider or factor when submitting your proposal or agreeing to your contract amount.
An express warranty could have the effect of eviscerating the argument that you performed your scope of work pursuant to the plans and specifications. In other words, the applicability of the Spearin doctrine could be rendered moot based on express warranty language in your contract that is fully within your control because you do not have to agree to that language.
Under the Spearin doctrine:
[W]hen a ‘contractor is bound to build according to plans and specifications prepared by the owner, the contractor will not be responsible for the consequences of defects in the plans and specification.’ Spearin and its progeny set forth a default rule of fundamental fairness that when a general contractor requires a subcontractor to follow certain plans and specifications, the general contractor impliedly warrants that those plans and specifications are ‘free from design defects.’ Put simply, Spearin protects subcontractors from liability for simply following the general contractor’s direction and requirements.
However, the implied warranty set forth in Spearin and its progeny may be overcome by express agreement. Where a general contractor and subcontractor expressly agree to allocate the risk of a defective product to the subcontractor, that express agreement must prevail over Spearin’s implied warranty.
Lighting Retrofit International, LLC v. Consellation NewEnergy, Inc., 2022 WL 541156 (D. Md. 2022) (internal citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Surviving the Construction Law Backlog: Nontraditional Approaches to Resolution
June 07, 2021 —
Jeffrey Kozek - Construction ExecutiveAcross the construction industry, COVID-19’s impact has caused a range of problems for contractors and projects—prolonged or intermittent work shutdowns, supply chain delays, pricing increases on materials and funding shortfalls. It has also led to court closures. The legal backlog for claims and disputes means that owners and contractors are facing the option of waiting until the courts are functioning the way they were previously or utilizing alternative approaches to resolution to keep projects and businesses running.
Though courts across the country reopened to some extent in the latter half of 2020, many state and federal facilities were shut down or working with a limited capability for weeks or months. The closures not only froze the progress of numerous disputes already underway, but caused new schedule, cost and COVID-19-related claims to also be held up in the same backlog that is slowly being addressed under current restricted operations. New safety measures to reduce viral transmission, including reduced usage of courtrooms, restrictions on personnel and increased cleaning and sanitizing measures, have limited the number of cases courts can handle on a daily basis and lengthened legal timelines in ways many parties had not anticipated and cannot afford.
Reprinted courtesy of
Jeffrey Kozek, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
“But it’s 2021!” Service of Motion to Vacate Via Email Found Insufficient by the Eleventh Circuit
June 21, 2021 —
Justin K. Fortescue - White and WilliamsWhile we are all getting used to the “new normal” of working remotely and relying on emails for almost all communications, a recent decision from the United States Court of Appeals for the Eleventh Circuit provides arbitration practitioners with a stark reminder – the “notice” requirements of the Federal Arbitration Act (FAA) will be strictly enforced and providing notice of a motion to vacate via email may not qualify as proper service.
In O'Neal Constructors, LLC v. DRT Am., LLC, 991 F.3d 1376 (11th Cir. 2021), O’Neal Constructors, LLC (O’Neal) and DRT America (DRT) entered into a contract containing an arbitration provision. Following a dispute, the parties went to arbitration and, on January 7, 2019, the panel issued an award requiring DRT to pay O’Neal a total of $1,415,193. The amount awarded to O’Neal consisted of two parts: $765,102 for the underlying contract dispute and $650,090 for reimbursement of O’Neal’s attorneys’ fees. While DRT paid O’Neal the first portion of the award, DRT refused to pay the portion that related to O’Neal’s attorneys’ fees.
On April 4, 2019, as a result of DRT’s refusal to pay O’Neal’s attorneys’ fees, O’Neal filed a motion to confirm the award in Georgia state court (which was subsequently removed to the Northern District of Georgia). The next day, in a separate action, DRT filed a motion to vacate the attorneys’ fees portion of the award and, that same night, DRT’s counsel emailed O’Neal’s counsel a “courtesy copy” of DRT’s memorandum in support of the motion to vacate. A few weeks later, on April 30, 2019 (i.e., more than three months after the award was issued), DRT served O’Neal (via U.S. Marshall) with a copy of the motion to vacate.
Read the court decisionRead the full story...Reprinted courtesy of
Justin Fortescue, White and WilliamsMr. Fortescue may be contacted at
fortescuej@whiteandwilliams.com
Kansas City Airport Terminal Project Faces Delays, Rising Costs
February 06, 2019 —
Kansas City Star - Engineering News-RecordCosts have long since blown past initial estimates, prompting an independent review of the price tag. Its opening is eight months behind schedule and mounting delays drew heated questions from local officials last year.
Sounds like the continuing saga of Kansas City's planned airport terminal, overwhelmingly approved by voters in November 2017 . It's actually about the new international arrivals facility under construction at Seattle-Tacoma International Airport , or Sea-Tac.
Read the court decisionRead the full story...Reprinted courtesy of