Building Materials Price Increase Clause for Contractors and Subcontractors – Three Options
June 21, 2021 —
William L. Porter - Porter Law GroupWith the arrival of inflation come concerns regarding increases in the price of building materials within the construction industry. Contractors, subcontractors and others who contract to perform construction work can suffer significant losses when the prices they must pay for materials rises significantly between the time they sign the contract and actually purchase the materials. The general rule is that, unless there exists a contract clause allowing contractors or subcontractors to pass significant price increases for materials on to others, contractors and subcontractors are stuck with the price stated in the contract or subcontract. When prices rise, the contractor or subcontractor eats the difference. Rising prices can thus turn a profitable project into a catastrophic failure. How are contractors and subcontractors to protect themselves?
Once a contract is executed, there is usually little that can be done to change the document to address rising prices. Effort must therefore turn to future protection. The best technique for dealing with increasing future prices for building materials is by adding a price escalation clause to contracts and subcontracts. While this will not help for past contracts or subcontracts, it can certainly offer significant protection going forward.
Read the court decisionRead the full story...Reprinted courtesy of
William L. Porter, Porter Law GroupMr. Porter may be contacted at
bporter@porterlaw.com
Fatal Crane Collapse in Seattle Prompts Questions About Disassembly Procedures
July 09, 2019 —
Jeff Rubenstone - Engineering News-RecordA tower crane being dismantled collapsed Saturday, April 27 in Seattle, killing four people, including two ironworkers on the crane and two bystanders on the street below. The jobsite, located in a Google office development in Seattle's bustling South Lake Union neighborhood, is adjacent to a busy intersection where traffic had not been blocked off during the crane’s disassembly. It is the first fatal crane accident in the Puget Sound region since a crane collapse in Bellevue, Wash., in 2006 that killed one person.
Read the court decisionRead the full story...Reprinted courtesy of
Jeff Rubenstone, ENRMr. Rubenstone may be contacted at
rubenstonej@enr.com
Reinsurer Must Reimburse Health Care Organization for Settlement Costs
June 17, 2015 —
Tred R. Eyerly – Insurance Law HawaiiThe Indiana Supreme Court reversed summary judgment issued to reinsurer Continental Casualty Company (CNA) and determined it must reimburse the insured for settlement costs under the E & O policy. Wellpoint, Inc., et al. v. National Union Fire Ins. Co. of Pittsburgh, PA, et al., 2015 Ind. LEXIS 316 (Ind. April 22, 2015).
Anthem, Inc. was a large managed health care organization. Anthem was its own primary and excess insurer for E&O liability. It had numerous excess reinsurers. Beginning in 1998, anthem was confronted by various lawsuits alleging it and other managed care organizations failed to pay claims in a full and timely manner, thereby breaching state and federal statutes. The various lawsuits alleged substantially the same wrongful conduct, namely that after promising to pay doctors in a timely manner for their services, Anthem sought to improperly deny, delay and diminish payments due.
The cases were consolidated into a federal multi-district litigation proceeding in the Southern District of Florida. Claims for breach of contract, unjust enrichment, and violations of state prompt pay statutes were dismissed or dropped. Anthem then settled the underlying litigation in July 2005 without admitting and instead denying any wrongdoing or liability. The settlement called for both cash payments and implementation of specific business practices consistent with requested injunctive relief.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Deferred Maintenance?
December 17, 2024 —
Daniel Lund III - LexologyA Tennessee-based “outsourced maintenance vendor” to an engine company filed suit in Louisiana state court seeking to recover nearly $150,000 on “open account,” for work previously performed. The engine company removed the case to the Federal District Court in New Orleans and asserted as a defense that the vendor lacked a proper Louisiana construction contractor’s license. The engine company filed a motion for summary judgment based on the defense.
Under Louisiana law, a contract between parties is “absolutely null”--considered to have never existed--where one of the parties performed services without a required Louisiana contractor’s license, and the combined work reaches a $50,000 threshold. The engine company asserted that the vendor performed typical construction contractor work, including plywood flooring, applied epoxy to concrete flooring, erected part of a commercial carport, undertook certain heavy demolition, and installed fences, guardrails, and wire racks.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Reconstructing the Francis Scott Key Bridge Utilizing the Progressive Design-Build Method
June 04, 2024 —
Lisa D. Love - The Dispute ResolverHaving awakened on the morning of March 26 to the devastating news of the collapse of Baltimore’s Francis Scott Key Bridge after being struck by the Dali, a 984 length /52 beam foot cargo container ship, I thought of the many times I crossed the bridge as a child growing up in Washington, D.C. I also recalled Montgomery Schyler’s comments on the opening of the Brooklyn Bridge, when he stated that “the work which is likely to be our most durable monument, and to convey some knowledge of us to the most remote posterity, is a work of bare utility; not a shrine, not a fortress, not a palace, but a bridge.”
I thought of the beauty of New York’s Mario Cuomo Bridge, a 3.1-mile cable-stayed twin-span bridge with eight traffic lanes, bicycle and pedestrian paths, six lookout points and room for future rapid transit. It was completed in 2018 and constructed under a design-build procurement model[i] at a cost of $3.98 billion. Accelerated bridge construction (ABC) techniques were utilized in its construction. ABC techniques employ innovative planning, design, materials, and construction methods in a safe and cost-effective manner to reduce the on-site construction time that occurs when building new bridges or replacing and rehabilitating existing ones. ABC techniques improve site constructability, total project delivery time, work-zone safety for the traveling public and traffic impacts, on-site construction time, and weather-related time delays.[ii]
I also thought of the gracefulness of Boston’s Leonard P. Zakim Bunker Hill Memorial Bridge, a 0.27-mile hybrid cable-stayed steel and concrete bridge with pedestrian and bicycle access that holds 10 lanes of traffic. The Zakim Bridge was completed in 2004 at a cost of approximately $100 million as part of the $24.3 billion Big Dig.[iii] Despite its elegant, streamlined appearance, the bridge was designed to be exceptionally strong, withstand winds over 400 miles per hour and endure a magnitude 7.9 earthquake.[iv]
Read the court decisionRead the full story...Reprinted courtesy of
Lisa D. Love, JAMS
Georgia Court of Appeals Holds That Insurer Must Defend Oil Company Against Entire Lawsuit
October 07, 2019 —
Lawrence J. Bracken II, Michael S. Levine & Alexander D. Russo - Hunton Andrews KurthThe Georgia Court of Appeals recently affirmed a grant of summary judgment in favor of Mountain Express Oil Company on its breach of contract claim against liability insurer, Southern Trust Insurance Company. Empire Petroleum brought claims against Mountain Express for breach of contract, injunctive relief, and libel or slander, among others. Mountain Express sought a defense to that lawsuit under its insurance policy with Southern Trust. Southern Trust contended that the insurance policy did not cover Empire’s non-libel/slander claims, and therefore reimbursed Mountain Express for only a portion of its attorneys’ fees. After the Empire lawsuit settled, Mountain Express sued Southern Trust for breach of contract and bad faith for failing to pay the remaining defense costs, contending that Southern Trust had a duty to defend the entire lawsuit.
The Georgia Court of Appeals affirmed the trial court’s grant of summary judgment to Mountain Express on its breach of contract claim. Citing policy language stating that “[the insurer] will have the right and duty to defend the insured against any ‘suit’ seeking those damages,” the court held that Southern Trust was obligated to defend the entire lawsuit. Specifically, in reaching that conclusion, the court noted that by agreeing to defend any “suit,” not any “claim,” Southern Trust obligated itself to defend the entire lawsuit if any claim could be covered under the policy. Accordingly, Southern Trust breached the policy when it only agreed to defend some of the claims against its insured.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and Alexander D. Russo, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Litigation Roundup: “You Can’t Make Me Pay!”
August 19, 2024 —
Daniel Lund III - LexologyThe foregoing is an accurate statement, generally speaking, for Louisiana public entities. Statutory and constitutional provisions in Louisiana protect public entities from being forced to pay monies – including satisfying court judgments – when the monies have not been specifically allocated for the purpose. Correspondingly, there is ordinarily no means to seize public assets to satisfy judgments.
On the other hand, writs of mandamus in Louisiana – actions designed to compel a public official to undertake a ministerial duty over which the public official has no discretion – can be aimed at forcing a public official (on behalf of the public entity) to pay money.
In an inverse condemnation case, plaintiffs prevailed on the theory that a Louisiana public entity had “damaged and interfered with their use and enjoyment of their private homes and church” during a New Orleans drainage project. The plaintiffs pursued a writ of mandamus to compel payment their approximately $1.5 million judgment for damages and fees as a “ministerial duty” of the public entity. To be sure, in connection with the judgment, the public entity had not at any time specifically allocated funds for the payment.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Does a No-Damage-for-Delay Clause Also Preclude Acceleration Damages?
January 27, 2020 —
Ted R. Gropman & Christine Z. Fan - ConsensusDocsConstruction contracts often include a “no damage for delay” clause that denies a contractor the right to recover delay-related costs and limits the contractor’s remedy to an extension of time for noncontractor-caused delays to a project’s completion date. Depending on the nature of the delay and the jurisdiction where the project is located, the contractual prohibition against delay damages may well be enforceable. This article will explore whether an enforceable no-damage-for-delay clause is also a bar to recovery of “acceleration” damages, i.e., the costs incurred by the contractor in its attempt to overcome delays to the project’s completion date.
Courts are split as to whether damages for a contractor’s “acceleration” efforts are distinguishable from “delay” damages such that they may be recovered under an enforceable no-damage-for-delay clause. See, e.g., Siefford v. Hous. Auth. of Humboldt, 223 N.W.2d 816 (Neb. 1974) (disallowing the recovery of acceleration damages under a no-damage-for-delay clause); but see Watson Elec. Constr. Co. v. Winston-Salem, 109 N.C. App. 194 (1993) (allowing the recovery of acceleration damages despite a no-damage-for-delay clause). The scope and effect of a no-damage-for-delay clause depend on the specific laws of the jurisdiction and the factual circumstances involved.
There are a few ways for a contractor to circumvent an enforceable no-damage-for-delay clause to recover acceleration damages. First, the contractor may invoke one of the state’s enumerated exceptions to the enforceability of the clause. It is helpful to keep in mind that most jurisdictions strictly construe a no-damage-for-delay clause to limit its application. This means that, regardless of delay or acceleration, courts will nonetheless permit the contractor to recover damages if the delay is, for example, of a kind not contemplated by the parties, due to an unreasonable delay, or a result of the owner’s fraud, bad faith, gross negligence, active interference or abandonment of the contract. See Tricon Kent Co. v. Lafarge N. Am., Inc., 186 P.3d 155, 160 (Colo. App. 2008); United States Steel Corp. v. Mo. P. R. Co., 668 F.2d 435, 438 (8th Cir. 1982); Peter Kiewit Sons’ Co. v. Iowa S. Utils. Co., 355 F. Supp. 376, 396 (S.D. Iowa 1973).
Reprinted courtesy of
Ted R. Gropman, Pepper Hamilton LLP and Christine Z. Fan, Pepper Hamilton LLP
Mr. Gropman may be contacted at gropmant@pepperlaw.com
Read the court decisionRead the full story...Reprinted courtesy of