2017 Legislative Changes Affecting the Construction Industry
July 13, 2017 —
Melinda S. Gentile – Peckar & Abramson, P.C.The 2017 Florida Legislative Session recently concluded, and a number of important construction-related House Bills (HB) and Senate Bills (SB) were presented during the Session, most notably SB 204/HB 377. These Bills may impact General Contractors and Construction Managers in a number of ways, not the least of which is the period of time that a cause of action may be initiated for the design, planning or construction of an improvement.
The following construction-related Bills passed in both the House and Senate and will become law if approved by the Governor.
Senate Bill (SB) 204/House Bill (HB) 377: Relating to the Statute of Repose for causes of action based on design, planning or construction of an improvement to real property. This bill passed both the House and the Senate and was approved by the Governor on June 14, 2017. This bill becomes effective on July 1, 2017.
Read the court decisionRead the full story...Reprinted courtesy of
Melinda S. Gentile, Peckar & Abramson, P.C.Ms. Gentile may be contacted at
mgentile@pecklaw.com
Third Circuit Follows Pennsylvania Law - Damage Caused by Faulty Workmanship Does Not Arise from an Occurrence
May 10, 2013 —
Tred EyerlyThe Third Circuit followed Pennsylvania law in determining that damage caused by faulty workmanship did not arise from an occurrence. Zurich Am. Ins. Co. v. R. M. Shoemaker Co., 2013 U.S. App. LEXIS 6093 (3d Cir. March 27, 2013).
The County sued R. M. Shoemaker, alleging faulty construction of an addition to a correctional institution. The County alleged Shoemaker negligently supervised its subcontractor, thereby permitting the subcontractor to engage in willful misconduct, resulting in damage to structural elements of the correctional institution. The County alleged that Shoemaker's negligence permitted water to intrude, damaging the electrical systems, acoustic ceilings and miscellaneous equipment.
Zurich sought a declaratory judgment that it was not required to defend or indemnify Shoemaker. The district court granted Zurich summary judgment. Relying on Pennsylvania law, the district court found that the allegations in the underlying action did not arise from an occurrence.
Read the court decisionRead the full story...Reprinted courtesy of
Tred EyerlyMr. Eyerly can be contacted at
te@hawaiilawyer.com
Construction Law Client Alert: Hirer Beware - When Exercising Control Over a Job Site’s Safety Conditions, You May be Held Directly Liable for an Independent Contractor’s Injury
April 06, 2011 —
Mark VonderHaar and Yvette DavisOn February 24, 2011, the California Court of Appeal held in Jeffrey Tverberg, et al v. Fillner Construction, Inc. that the imposition of direct liability on a hirer turns on whether the hirer exercised retained control of worksite safety in such a manner that affirmatively contributed to the independent contractor’s injury. Twice, Tverberg, an independent contractor hired by a general contractor's subcontractor, asked the general contractor to make the job site safe by covering up open holes created by another unrelated subcontractor while Tverberg was working at the site. After Tverberg was injured at the site by falling in a hole, he sued both the general contractor and the subcontractor which had hired him.
The Court of Appeal reasoned that when the general contractor instructed another subcontractor to create a condition that was potentially dangerous (i.e., creating open and uncovered bollard holes), and simultaneously required Tverberg to perform unrelated work near the open holes, the general contractor s conduct may have constituted a negligent exercise of its retained control which affirmatively contributed to Tverberg’s injury. The Court also reasoned that the general contractor affirmatively assumed responsibility for the safety of the workers near the holes by only requiring stakes and safety ribbon, and negligently discharged that responsibility which resulted in injury.
Read the full story...
Reprinted courtesy of Mark VonderHaar and Yvette Davis of Haight Brown & Bonesteel. Mr. VonderHaar can be contacted at mvonderhaar@hbblaw.com and Ms. Davis at ydavis@hbblaw.com.
Read the court decisionRead the full story...Reprinted courtesy of
Recording “Un-Neighborly” Documents
April 03, 2019 —
Bob Henry - Snell & Wilmer Real Estate Litigation BlogIn September 2018, in Baumgartner v. Timmins, 245 Ariz. 334, 429 P.3d 567, the Arizona Court of Appeals provided further clarification on what constitutes an “encumbrance” on a property for purposes of Arizona’s statutory scheme prohibiting the recording of “false documents.” The statute, A.R.S. § 33-420, prohibits the recording of documents that a person knows to be forged, are groundless, or that contain material misstatements (or false claims). A person who claims an “interest in, or a lien or encumbrance against” real property who records such documents can be held liable for $5,000 or treble the actual damages caused by the recording (whichever is greater), A.R.S. § 33-420(A), and perhaps even be found guilty of a class 1 misdemeanor, A.R.S. § 33-420(E).
At issue in Baumgartner were neighbors fighting about CC&Rs—a typical neighborhood fight. In 2015, some of the neighbors filed suit against the Timminses for violating the CC&Rs. The Timminses did not contest the lawsuit, resulting in a default judgment. In what the Court of Appeals characterized as a lawsuit filed by the Timminses “in apparent response to the [first] lawsuit and resulting default judgment,” the Timminses created, signed, and recorded affidavits contending that the Plaintiffs in the original lawsuit were themselves “in violation of several provisions of the CC&Rs.” The Plaintiffs then filed suit again against the Timminses, this time contending that the Timminses had violated A.R.S. § 33-420 by recording the affidavits because the affidavits, the Plaintiffs contended, created encumbrances on their properties. The Apache County Superior Court agreed, and issued a final judgment nullifying the recorded documents and awarding the Timminses damages, along with their attorneys’ fees and costs.
Read the court decisionRead the full story...Reprinted courtesy of
Bob Henry, Snell & WilmerMr. Henry may be contacted at
bhenry@swlaw.com
Traub Lieberman Partner Lisa Rolle Wins Summary Judgment on Behalf of Contract Utility Company in Personal Injury Action
April 25, 2023 —
Lisa M. Rolle - Traub LiebermanTraub Lieberman Partner Lisa Rolle obtained summary judgment on behalf of a contract utility company (“Utility Company”) in a matter brought before the New York Supreme Court, Queens County. In the complaint, the Plaintiff alleged that she sustained injuries as a result of a trip and fall accident where the Plaintiff’s foot allegedly went into a hole in the grass strip abutting the sidewalk adjacent to a premises located in Queens, NY. The Plaintiff claimed that the defect in the sidewalk was caused by the removal of a utility pole at the curb strip that was not correctly backfilled.
The Defendant Utility Company is in the business of inspecting, treating, and repairing utility and telecommunication structures, including wooden utility poles. TLSS was successfully able to establish that, three years prior to the accident, the Utility Company was retained to conduct a visual inspection of the subject pole. However, the Utility Company does not and has not owned, installed, removed or replaced in-service utility poles in New York or at the location of the alleged accident. Further, TLSS established that the Utility Company did not service or remove the subject pole at the accident site or backfill the curb strip.
Read the court decisionRead the full story...Reprinted courtesy of
Lisa M. Rolle, Traub LiebermanMs. Rolle may be contacted at
lrolle@tlsslaw.com
What is a Civil Dispute?
August 07, 2018 —
Bremer Whyte Brown & O’MearaBroadly speaking, all lawsuits can be put into one of two categories: criminal or civil. Criminal cases are brought by the government against a private person and/or organization for committing an act that is considered harmful to society as a whole; whereas civil cases involve private disputes between individuals and/or organizations.
Civil litigation begins when one person or organization claims that another person or organization has failed to carry out a legal duty owed to the claimant. Legal duties are those prescribed either by contract between the parties, or by the law.
In order for a claimant to commence legal action against another party, the claimant must file a summons and complaint with the court and serve a copy of the summons and complaint on the party against whom the lawsuit is being brought. The person who brings the lawsuit is called the “Plaintiff” and the person against whom the lawsuit is brought is called the “Defendant.”
Read the court decisionRead the full story...Reprinted courtesy of
Bremer Whyte Brown & O’Meara
Virtual Jury Trials: The Next Wave of Remote Legal Practice
July 13, 2020 —
David R. Zaslow & Mark Paladino - White and WilliamsOne of the most obvious and unavoidable results of the COVID-19 crisis has been the postponement of jury service and, by extension, all jury trials. Given the inherent difficulties of convening juries in a world of social distancing, it is likely that multiple jurisdictions will be unable to conduct live jury trials for at least the next several months.
Recognizing the mounting delay and substantial docket backlog that is attendant to several months without jury trials, one court most recently permitted the litigants, upon consent, to try a new innovation – the nation’s first virtual jury trial conducted entirely on the Zoom platform. More than two dozen potential jurors in Collin County, Texas attended jury selection from home by smartphone, laptop, and tablet, a process that was streamed live on YouTube. The presiding judge occasionally provided prospective jurors technical advice on how to best use their devices.
Once selected, the jurors virtually attended a one-day, “summary jury trial” of an insurance dispute in which they heard a condensed version of the case and delivered a non-binding verdict. The parties were then able to gauge how their cases would fare before a jury in a full-scale trial and, with that insight, agreed to proceed to a mediation in an attempt to reach a resolution. Court officials further touted the abbreviated, non-binding experience as an ideal test for the viability of remotely holding jury trials that would result in a final judgment. This real-world test, albeit in a non-binding exercise, may be an indication of things to come, as courts in Indiana and Arizona have already communicated an intention to conduct jury trials remotely once able.
Reprinted courtesy of
David R. Zaslow, White and Williams and
Mark Paladino, White and Williams
Mr. Zaslow may be contacted at zaslowd@whiteandwilliams.com
Mr. Paladino may be contacted at paladinom@whiteandwilliams.com
Read the court decisionRead the full story...Reprinted courtesy of
CSLB Releases New Forms and Announces New Fees!
April 05, 2017 —
Garret Murai – California Construction Law BlogThe California Contractors State License Board (CSLB”) has issued new application forms. Effective May 1, 2017, the CSLB will only accept forms with a revision date of October 2017 (Pro tip: see bottom of form to verify it indicates a revision date of “10/16” or later).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com