State Farm Unsuccessful In Seeking Dismissal of Qui Tam Case
January 26, 2017 —
Tred R. Eyerly – Insurance Law HawaiiIn an insurance related case, the United States Supreme Court affirmed the Fifth Circuit's decision that State Farm was not entitled to a dismissal of a qui tam case involving its claims-handling after Hurricane Katrina. State Farm Fire & Cas. Co. v. United States ex rel. Rigsby, ___ U.S. ___, 137 S. Ct. 436 (2016).
Before Katrina, State Farm issued two types of policies to homeowners: (1) Federal Government-back flood policies and (2) its own general homeowner policies. After Hurricane Katrina, State Farm's policies were responsible for wind damage, and the government policies were responsible for flood damage. Therefore, it was in State Farm's interest to classify hurricane damage as flood-related.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Bidder Be Thoughtful: The Impacts of Disclaimers in Pre-Bid Reports
August 04, 2021 —
Joshua A. Morehouse - ConsensusDocsWhen bidding a project, subsurface or latent site conditions that are not immediately apparent can massively impact the costs of performance to general contractors. Were contractors required to bid on projects without any information on pre-existing conditions, they would need either to be assured that any additional costs would be reimbursed by the owner, or to include significant contingencies for subsurface conditions in their bids. For owners, these options result in either increased risk or increased cost—neither of which is particularly palatable. Owners therefore implement several contractual tools to minimize these risks and costs.
One of these tools is providing bidders with a report on latent conditions, often called a “geotechnical data report” or “GDR”, but otherwise shifting as much of the subsurface-related risk as possible to the contractor. In theory, these reports permit contractors to appropriately adjust their contingencies for latent conditions, thus saving owners money. However, several independent and thorny issues arise where site reports provided by the owner are either inconsistent with or silent on the actual conditions of a project site. Hence owners often include disclaimers with these reports, such as noting that the report is for “informational purposes only” or that the report is “not part of the contract documents."
Read the court decisionRead the full story...Reprinted courtesy of
Joshua A. Morehouse, Peckar & Abramson, P.C.Mr. Morehouse may be contacted at
jmorehouse@pecklaw.com
Arizona Supreme Court Clarifies Area Variance Standard; Property Owners May Obtain an Area Variance When Special Circumstances Existed at Purchase
October 19, 2017 —
Nick Wood, Adam Lang, Noel Griemsmann, & Brianna Long – Snell & Wilmer Real Estate Litigation BlogIn Pawn 1st v. City of Phoenix, the Arizona Supreme Court rejected a Court of Appeals rule that would have unduly restrained alienation of property in Arizona. The Court of Appeals found that the City of Phoenix Board of Adjustment acted beyond its authority when it granted an area variance to a pawn shop where the special circumstances causing a need for the variance existed before the pawn shop purchased the property. Under Arizona law, boards of adjustment cannot grant an area variance where the special circumstances requiring the variance are self-imposed. The Court of Appeals adopted a rule that knowledge of special circumstances at the time of purchase made the special circumstances self-imposed, foreclosing the purchaser’s ability to obtain a variance. This rule would have severely restricted property purchasers’ ability to obtain area variances in Arizona and by extension likely strained property transactions.
The underlying case involved a pawn shop that was proposed in southeast Phoenix. After the property purchaser obtained approval for a required use permit (for a pawn shop) and a variance (for a 500 foot residential setback) from the City of Phoenix Board of Adjustment, a competing pawn shop filed a special action arguing that the variance was a use variance, not an area variance, beyond the board of adjustment’s authority.
Reprinted courtesy of Snell & Wilmer attorneys
Nick Wood,
Adam Lang,
Noel Griemsmann and
Brianna Long
Mr. Wood may be contacted at nwood@swlaw.com
Mr. Lang may be contacted at alang@swlaw.com
Mr. Noel may be contacted at ngriemsmann@swlaw.com
Ms. Brianna may be contacted at bllong@swlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Gordon & Rees Ranked #4 of Top 50 Construction Law Firms in the Nation by Construction Executive Magazine
July 11, 2022 —
GRSM Construction Team - Gordon & Rees Construction Law BlogGordon Rees Scully Mansukhani has been ranked as the No. 4 construction law firm in the nation by Construction Executive in the magazine’s 2022 ranking of The Top 50 Construction Law Firms™. As the only law firm with offices and attorneys in all 50 states, Gordon & Rees’ construction group (with over 150 construction lawyers) delivers maximum value to our clients by understanding their business and combining the resources of a full-service national firm with the local knowledge of a regional firm.
Led by Allen Estes and Angela Richie, the construction lawyers at Gordon & Rees are uniquely situated to serve our construction clients. We have attorneys with professional training and practical experience in related fields such as engineering and construction management, as well as lawyers with leadership experience in various construction industry related trade associations, legal advisory committees and government agencies. “If a client is looking for a legal partner in multiple states who understands their business, Gordon & Rees is that partner,” said Angela Richie.
Read the court decisionRead the full story...Reprinted courtesy of
GRSM Construction Team, Gordon Rees Scully Mansukhani
Contractor Sues Supplier over Defective Products
June 28, 2011 —
CDJ STAFFFast Track Specialties has sued RJF International after needing to remove wall protection units at Methodist West Houston Hospital, according to an article in the Houston Chronicle. Fast Track claims that contractors had to disconnect gas, water, and electric from the area to facilitate removal of corner guards, handrails, and crash guards from the hospital. This cost the contractor more than $135,000.
Fast Track is claiming that RJD International has committed breach of contract, breach of warranty, and negligent representation.
Read the full story…
Read the court decisionRead the full story...Reprinted courtesy of
Anticipatory Repudiation of a Contract — The Prospective Breach
July 05, 2021 —
David Adelstein - Florida Construction Legal UpdatesThere are instances where a party can engage in the anticipatory repudiation of their obligations under a contract. In essence, this is basically a party prospectively breaching the contract by repudiating their obligations in the contract.
A prospective breach of contract occurs where there is absolute repudiation by one of the parties prior to the time when his performance is due under the terms of the contract. Such a repudiation may be evidenced by words or voluntary acts but the refusal must be distinct, unequivocal, and absolute. Moreover, repudiation can be shown where one party makes additional demands not included in the initial agreement:
The law is clear that where one party to the contract arbitrarily demands performance not required by the contract and couples this demand with a refusal to further perform unless the demand is met, the party has anticipatorily repudiated the contract, which anticipatory repudiation relieves the non-breaching party of its duty to further perform and creates in it an immediate cause of action for breach of contract.
24 Hr Air Service, Inc. v. Hosanna Community Baptist Church, Inc., 46 Fla. L. Weekly, D1344a (Fla. 3d DCA 2021) (quotations and citations omitted).
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Congratulations to BWB&O’s Newport Beach Team on Obtaining a Defense Verdict in Favor of their Subcontractor Client!
April 02, 2024 —
Dolores Montoya - Bremer Whyte Brown & O'Meara LLPBremer Whyte Brown & O’Meara’s Newport Beach Partner Morgan Stiefel and Associate Brandon Cook obtained a defense verdict after years-long litigation in favor of their subcontractor client.
This lawsuit stemmed from a claim made by Plaintiff for eye injuries arising out of claimed negligence and strict liability associated with our client’s performance of a sandblasting job at a construction site adjacent to Plaintiff’s home. Plaintiff alleges that while she was in her backyard, sand hit her in the eyes at a high velocity speed, resulting in permanent damage to her eyes.
We argued our clients took all necessary safety precautions in the performance of this job, and Plaintiff’s eye irritation symptoms could not have been caused by our client. All of her alleged injuries were either pre-existing or could be explained by circumstances other than our client’s actions. Through expert testimony and our arguments, we were able to show the jury that Plaintiff lied about the sand entering her eyes at a high velocity and her symptoms being caused by our clients’ performance of the sandblasting job.
Read the court decisionRead the full story...Reprinted courtesy of
Dolores Montoya, Bremer Whyte Brown & O'Meara LLP
Court Rejects Efforts to Limit Scope of Judgment Creditor’s Direct Action Under Insurance Code Section 11580
May 01, 2019 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Ins. Co. of St. of PA v. Amer. Safety Indemnity Co. (No. B283684, filed 3/1/19) (“ICSOP”), a California appeals court rejected one insurer’s efforts to limit the scope of another insurer’s direct action as a judgment creditor under Insurance Code section 11580(b)(2).
In ICSOP, homeowners filed a claim in arbitration against their general contractor alleging damages from subsidence. While the arbitration was pending, the general contractor filed suit against the grading subcontractor seeking indemnity and contribution. The complaint attached the homeowners’ complaint in arbitration pleading damages of $2.3 million, and alleged that the subcontractors had a duty to indemnify for those damages. The arbitrator awarded the homeowners $1.1 million.
The general contractor was insured by plaintiff ICSOP, which paid the arbitration award. A default judgment was entered against the grading subcontractor for $1.5 million, that included both the arbitration award plus $356,340 for the general contractor’s attorney’s fees. American Safety insured the grading subcontractor but refused to indemnify ICSOP. ICSOP then sued American Safety on the default judgment, pursuant to Insurance Code section 11580(b). The trial court granted summary judgment for ICSOP and the appeals court affirmed.
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP Read the court decisionRead the full story...Reprinted courtesy of