Michigan Claims Engineers’ Errors Prolonged Corrosion
June 30, 2016 —
Richard Korman & Erin Richey – Engineering News-RecordOnly a few months ago, Michigan’s state agencies stood at the center of a circle of blame for the Flint water crisis. A special advisory task force had condemned the state’s use of an emergency manager to make key decisions about the city, including, in 2014, the money-saving switch of the water source from Lake Huron to the Flint River and the state Dept. of Environmental Quality’s slow response to citizen reports of smelly, discolored water. On June 22, Michigan Attorney General Bill Schuette started working to expand the circle via a new lawsuit in a Genesee County state court, accusing engineers Veolia N.A. and Houston-based Lockwood, Andrews & Newnam (LAN) and its parent company, Leo A Daly Co., of professional negligence.
Reprinted courtesy of
Richard Korman, Engineering News-Record and
Erin Richey, Engineering News-Record
Mr. Korman may be contacted at kormanr@enr.com
Read the court decisionRead the full story...Reprinted courtesy of
Personal Guarantor Cannot Escape a Personal Guarantee By…
June 02, 2016 —
David Adelstein – Florida Construction Legal UpdatesIn a prior article, I discussed the point that a
personal guarantor cannot escape a contractual requirement of a
personal guarantee merely by executing the guarantee as a corporate officer.
The recent decision Frieri v. Capital Investment Services, Inc., 41 Fla. L. Weekly D1189a (Fla. 3d DCA 2016) illustrates this point. In this case, a company hired an individual to help grow that company’s business. The contract required the individual to invest $6 Million into a trust in consideration of the company’s president transferring substantial shares of the company into the trust. The objective was that the trust would own the controlling shares of the company. The money was transferred. However, the shares were never placed in the trust and the trust never received controlling interest in the company.
Read the court decisionRead the full story...Reprinted courtesy of
David M. Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Homeowner’s Claims Defeated Because “Gravamen” of Complaint was Fraud, not Breach of Contract
September 29, 2021 —
Garret Murai - California Construction Law BlogBe careful what you wish for or, as in the next case, what you plead. In Vera v. REL-BC, LLC, Case Nos. A155807, A156823, and A159141 (June 30, 2021) 1st District Court of Appeal, a the buyer of a remodeled home who asserted breach of contract and fraud claims against a developer discovered that her claims, including her breach of written contract claim, was subject to a shorter 3 year statute of limitations because the “gravamen” of her complaint was fraud.
The REL-BC Case
Homeowner Adriana Vera purchased a remodeled home in Oakland, California from developers REL-BC, LLC and SNL Real Estate Solutions, LLC. The developers had purchased the home in July 2011, remodeled it, and sold it to Vera in November 2011.
As is typical in such transactions, the purchase agreement for the house required that the sellers disclose known material facts and defects affecting the property. In their disclosure, the sellers stated that they were not aware of any significant defects or malfunctions with respect to the property. The disclosure also stated that the sellers were not aware of any water intrusion issues with respect to the property.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Comparing Contracts: A Review of the AIA 201 and ConsensusDocs - Part I
March 22, 2018 —
Michael Sams and Amanda Cox – Construction Executive, A publication of Associated Builders and Contractors. All Rights Reserved.Here’s a helpful comparison of and analysis of some important contract sections in the
AIA 201 (2007 and 2017 versions) and
ConsensusDocs (2014 and 2017 versions). While not intended to be all inclusive, this summary comparison of the contract documents will run as a three-part series. Part I covers Financial Assurances, Design Risk, Project Management and Contract Administration. Part II will cover Schedule/Time, Consequential Damages/LDs, Claims and Disputes/ADR. Part III will cover Insurance and Indemnification and Payment.
FINANCIAL ASSURANCES
- What assurances are there that the owner can pay for the project?
- The Contractor should have the right to request and obtain proof that the Owner has funding sufficient to pay for the Work. The provision should also provide that the Contractor may terminate the Contract if the Owner refuses to allow a review of funding documents, or should the Contractor reasonably determine that the Owner does not have sufficient funds to pay for the Work.
Relevant Sections:
- A201 2007 Section 2.2.1; 2017 Section 2.2.1-2.2.2 A201
- 2014 & 2017 ConsensusDocs 200: Section 4.2
AIA:
- Section 2.2.1 A201 2007 & 2017: Both editions require the Owner, upon Contractor’s written request, to provide, “reasonable evidence that the Owner has made financial arrangements to fulfill the Owner’s obligations under the Contract.” Thereafter, the Contractor may only request such evidence if (1) the Owner fails to make payments; (2) a change in the Work materially changes the Contract Sum; or (3) the Contractor identifies in writing a reasonable concern regarding the Owner’s ability to make payment when due. If the Owner does not comply, the Contractor may stop work.
- Additionally, A201 2017 Section 2.2.2 awards costs to the Contractor for demobilization and remobilization.
Reprinted courtesy of
Michael Sams , Kenney & Sams and
Amanda Cox, Kenney & Sams
Mr. Sams may be contacted at mpsams@KandSlegal.com
Ms. Cox may be contacted at ajcox@KandSlegal.com
Read the court decisionRead the full story...Reprinted courtesy of
California Supreme Court Finds Negligent Supervision Claim Alleges An Occurrence
July 21, 2018 —
Tred R. Eyerly - Insurance Law HawaiiAnswering a question posed by the Ninth Circuit, the California Supreme Court found that a suit against a employer for negligent hiring, retention and supervision of a employee who intentionally injures a third party alleges an occurrence under a CGL policy. Liberty Surplus Co. Corp. v. Ledesma & Meyer Construction Co., 2018 Cal. LEXIS 4063 (Cal. June 4, 2018)
Ledesma & Meyer Construction Company (L&M) contracted with the school district to manage a construction project at a middle school. L&M hired Darold Hecht as an assistant superintendent on the project. In 2010, Jane Doe, a 13-year-old student at the school, sued alleging that Hecht had sexually abused her. Doe’s claims included a cause of action against L&M for negligent hiring, retaining, and supervising Hecht.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
Ensuring Arbitration in Construction Defect Claims
February 04, 2013 —
CDJ STAFFJared E. Berg and John W. Mill of Sherman & Howard note that developers and general contractors would prefer that construction defect claims against them go to arbitration, instead of ending up in front of a jury. They say “there is a way to do this.” For the developer and general contractor, arbitration is “typically less costly and time consuming than litigation.”
On the other side, home owner associations “tend to prefer litigation because the up-front costs of arbitration are greater and they would rather have their cases tried to a jury than a panel of arbitrators in the belief juries offer greater potential for high damage awards. In order to avoid arbitration, “HOAs have taken advantage of their statutory rights to amend declarations by instructing their members to approve amendments removing arbitration clauses.
However, in a recent Colorado case, the developer had taken a precaution of including in the arbitration clauses that “they could not be removed from the declarations by amendment with the developer’s and general contractor’s consent.” The homeowners association had voted to remove these clauses, but the judge found that they could not do so.
Berg and Mill give the advice to “include in the declaration’s arbitration clause a provision making your consent required to amend or nullify the arbitration provision,” adding that “courts will enforce this kind of consent provision.”
Read the court decisionRead the full story...Reprinted courtesy of
Newmeyer Dillion Attorneys Named to 2020 Southern California Rising Stars List
June 22, 2020 —
Newmeyer DillionProminent business and real estate law firm Newmeyer Dillion is pleased to announce that partner Eric Rollins and associates Jason Moberly Caruso and Richard Protzmann have been selected to the 2020 Southern California Rising Stars list by Super Lawyers. Each year, no more than 2.5 percent of the lawyers in the state are selected to receive this honor. The attorneys will be recognized in the June 2020 issues of Super Lawyers Magazine, Los Angeles Magazine and Orange Coast Magazine.
Eric Rollins, a partner in the Newport Beach office, provides legal counsel in a diverse array of practice areas with a focus on business, real estate, construction, insurance, and entertainment law. In his more than ten years at the firm, Eric has litigated and resolved hundreds of matters in both state and federal court through negotiation, mediation, arbitration, and trial. This is his third year as a Rising Star honoree.
Jason Moberly Caruso is an associate in the Newport Beach office. Jason's practice focuses on various aspects of "contaminated sites" environmental legal work, complex litigation, and appellate matters. This is the fifth consecutive year Jason has been honored.
Richard Protzmann is an associate in the Newport Beach office. Richard's practice focuses on focuses his practice on areas of business litigation, eminent domain, environmental law, zoning and land use, and general real estate litigation. This is the first year Richard has been selected.
Super Lawyers is a rating service of outstanding lawyers from more than 70 practice areas who have attained a high degree of peer recognition and professional achievement. The patented selection process evaluates candidates on 12 indicators of peer recognition and professional achievement, resulting in a comprehensive, credible and diverse listing of exceptional attorneys. The Rising Stars list is developed using the same selection process except candidates must be either 40 years old or younger, or have been in practice for 10 years or less.
About Newmeyer Dillion
For 35 years, Newmeyer Dillion has delivered creative and outstanding legal solutions and trial results that achieve client objectives in diverse industries. With over 70 attorneys working as a cohesive team to represent clients in all aspects of business, employment, real estate, environmental/land use, privacy & data security and insurance law, Newmeyer Dillion delivers holistic and integrated legal services tailored to propel each client's operations, growth, and profits. Headquartered in Newport Beach, California, with offices in Walnut Creek, California and Las Vegas, Nevada, Newmeyer Dillion attorneys are recognized by The Best Lawyers in America©, and Super Lawyers as top tier and some of the best lawyers in California and Nevada, and have been given Martindale-Hubbell Peer Review's AV Preeminent® highest rating. For additional information, call 949.854.7000 or visit www.newmeyerdillion.com.
Read the court decisionRead the full story...Reprinted courtesy of
Include Materials Price Escalation Clauses in Construction Clauses
December 26, 2022 —
Robert Alfert Jr. - Construction ExecutiveThe construction sector has been in a bull market for an unprecedented period of time. With the novel impacts from the coronavirus—and all the associated side effects, such as government moratoria, shipping delays and materials availability—we are now in a market of extreme volatility in pricing, inflation and increasing capital finance rates. And yet the construction sector continues to plow forward despite uncertainty, producing critical infrastructure, and much necessary housing, among other projects. The signs are that this trend will continue at least through Q1 of 2023, and likely beyond that, especially when you factor into the equation the many billions of dollars being placed into the market through the Bipartisan Infrastructure Law.
It is not surprising, therefore, that the number one issue in construction contracts in 2022 is how parties handle inflation and materials cost escalations in existing contracts and in the negotiations for new contracts. There is no other issue more heavily negotiated, often disputed and hotly debated in the construction sector today.
Reprinted courtesy of
Robert Alfert Jr., Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Mr. Alfert may be contacted at
robert.alfert@nelsonmullins.com