Three Kahana Feld Attorneys Selected to 2024 NY Metro Super Lawyers Lists
October 28, 2024 —
Linda Carter - Kahana FeldKahana Feld is pleased to announce that
Tim Capowski was selected to the 2024 NY Metro Super Lawyers list, and
Christopher Theobalt and
Sofya Uvaydov were selected to the 2024 NY Metro Rising Stars list. All three attorneys were recognized in the Appellate practice area.
Tim Capowski is a partner at Kahana Feld and chair of the firm’s
National Appellate Litigation & Consulting Group. He has spent the better part of three decades at the forefront of the insurance defense bar. Tim has litigated hundreds of appeals and thousands of motions in state and federal and appellate courts throughout New York and around the country. He handles a variety of complex litigation including catastrophic property and casualty claims, construction defect, professional liability, labor and employment law, mass torts, insurance coverage, and more.
Read the court decisionRead the full story...Reprinted courtesy of
Linda Carter, Kahana FeldMs. Carter may be contacted at
lcarter@kahanafeld.com
Don’t Sign a Contract that Doesn’t Address Covid-19 (Or Pandemics and Epidemics)
December 14, 2020 —
David Adelstein - Florida Construction Legal UpdatesDo yourself a favor: Don’t sign a construction contract that doesn’t address COVID-19 or any pandemic or epidemic from this point forward!
As the number of COVID-19 numbers rise, it would be reasonable to think this could have an impact on ongoing or future construction projects. For this reason, I want to revisit the subject of addressing COVID-19 (and any pandemic or epidemic) in your construction contract.
The potential impact caused by COVID-19 could result from governmental regulations that impact construction of the project, shutdowns due to affected workers, owners’ decisions to suspend performance or adjust the way the project is being constructed, increased deep cleaning requirements, and increased measures associated with social distancing and re-sequencing of shifts. This all plays into the timeliness of performance and the productivity of manpower and equipment usage. When submitting a price, a lot of these considerations may not be factored in because doing so could lead to a price that will never get accepted.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
More Musings on Why I Mediate
November 18, 2024 —
Christopher G. Hill - Construction Law MusingsWhew! I’m back. And yes, I know it’s been a while (it has been a busy year, both personally and professionally). Hopefully, this will be the first of at least a few more consistent posts here at Construction Law Musings. Now, on with the post:
Over the last few weeks, I’ve had a surge in mediation, both in my capacity as a mediator and as counsel for construction industry clients. These recent events have reaffirmed what I have always believed to be true, namely that no construction case is impossible to settle and avoid the cost and expense of litigation. I was also reminded of why I became a certified mediator and of the satisfaction that I get from helping individuals and construction companies find a business solution and closure.
Read the court decisionRead the full story...Reprinted courtesy of
The Law Office of Christopher G. HillMr. Hill may be contacted at
chrisghill@constructionlawva.com
Mortgage Battle Flares as U.K. Homebuying Loses Allure
January 28, 2015 —
Neil Callanan and Richard Partington – BloombergU.K. banks, which spent six years repairing their balance sheets after the 2008 property crash, want to advance more credit to homebuyers. Borrowers aren’t as enthusiastic.
Cheap funding costs and low default rates have made homebuyers attractive to lenders in recent years, boosting returns for companies such as Nationwide Building Society and Lloyds Banking Group Plc. (LLOY) Now, with demand for property cooling, they’re having to fight harder for business. Interest rates on the most popular mortgages fell to record lows in December, according to the Bank of England.
Mr. Callanan may be contacted at ncallanan@bloomberg.net; Mr. Partington may be contacted at rpartington@bloomberg.net
Read the court decisionRead the full story...Reprinted courtesy of
Neil Callanan and Richard Partington, Bloomberg
Big League Dreams a Nightmare for Town
April 03, 2013 —
CDJ STAFFThe town of Gilbert, Arizona had their own big dreams for Big League Dreams Gilbert, which the town was convinced would bring in financial benefits. Now the amateur sports complex is plagued by defects and failing infrastructure. The town was wondering how to create sufficient recreation facilities when Big League Dreams made a proposal that would bring tax revenue from a new stadium complex.
Ten years later, Gilbert says it’s not getting enough of the revenue from the parks. The proposal, created by Big League Dreams, estimated an economic benefit of $40 million over 30 years with a construction cost of $22.7 million. Instead, construction ran to $42.7 million and over the last two years the town has received only $250,570.
Then there are the construction defects. The structure was warranteed for only one year. That warrantee long over, the complex has problems with various concrete surfaces and has generated injury claims. The town did not inspect the park after Big League Dreams started operating it. They later found out that some parts did not conform to code, with 39 problem areas referenced in a report. Some of these included safety issues like missing handrails.
Read the court decisionRead the full story...Reprinted courtesy of
Exact Dates Not Needed for Construction Defect Insurance Claim
March 01, 2012 —
CDJ STAFFThe Texas Court of Appeals reversed the decision of the trial court in Vines-Herrin Custom Homes v Great American Lloyds Insurance Company on December 21, 2011. Vines-Herrin Custom Homes built a single-family home in Plano, Texas in 1999. They obtained a commercial general liability policy from Great American, later purchasing coverage from Mid-Continent, which the decision describes as “a sister company of Great American.”
While the home was under construction, Emil G. Cerullo sought to purchase it. At the time, it was under contract to another buyer. Two months later, Vines-Herrin told Cerullo that the deal had “fell through.” Cerullo bought the house with modifications from the original plan. Upon moving in, Cerullo began having water intrusion and other problems. “Cerullo noticed water gathering on window sills and damage to the sheetrock and baseboard.” Additional problems followed, including cracks, leaks, “and in early 2002, the ceiling and roof began to sag.”
Cerullo sued Vines-Herrin, claiming negligent construction. Vines-Herrin filed a claim seeking defense and indemnification under the insurance policies. Coverage was denied and Vines-Herrin filed suit to require coverage and also bringing claims for “breach of the duty of good faith and fair dealing, breach of contract, and DTPA and insurance code violations.”
In May, 2006 Vines-Herrin stated that it had no more defense funds and went into arbitration with Cerullo. The underlying construction defect action was settled for about $2.5 million. As part of the settlement, “Cerullo became the rightful owner of all remaining claims, rights, and causes of action against” Vines-Herrin’s insurers. He then joined the coverage lawsuit.
The non-jury trial was held under the controlling law of the time which “imposed a duty to defend only if the property damage manifested or became apparent during the policy period.” The court concluded in Cerullo’s favor. During the post-judgment motions, the Texas Supreme Court rejected the manifestation rule. Under this ruling, the trial court set aside its judgment and found in favor of the insurance companies. The trial court noted that although “the Residence was covered by an uninterrupted period of insurance (which began before the Residence was constructed) and that the damages to the Residence manifested during the uninterrupted period of insurance coverage,” “Mr. Cerullo failed to allege the date when actual physical damage to the property occurred.”
The first claim by Cerullo and Vines-Herrin was that the “Final Judgment” occurred in October 2004, and that all proceedings thereafter were void. The court rejected this as the “final judgment” is not “final for the purposes of an appeal unless it actually disposes of every pending claim and party or unless it clearly and unequivocally states that it finally disposes of all claims and all parties.” Despite the use of the word “final,” the trial court’s decision did not do this.
The second issue was the application of the Texas Supreme Court case Don’s Building Supply Inc. v. OneBeacon Insurance. In this case, framing rot due to defective stucco was not discovered until after the end of the policy period. The Supreme Court noted that “the key date is when injury happens, not when someone happens on it.”
The appeals court found that the trial court misapplied the Don’s Building Supply decision. Rather than an exact date, “so long as that damage occurred within the policy period, coverage was provided.” The appeals court noted that “Cerullo alleged the house was constructed in 1999 and he purchased it in May 2000.” “By April of 2001, Cerullo noticed that the windowsills in the study were showing signs of leakage and water damage.” As the court put it, “the petitions then alleged a litany of defects.”
The court noted that coverage by Great American was in effect from November 9, 1999 to November 9, 2000. In May of 2000, the house suffered “substantial flooding from a rainstorm that caused damage.” This was during the policy period. “As a matter of law, actual damages must occur no later than when they manifest.”
The court concluded that as damage manifested during the period of coverage, so must have the damage. The court ruled that “contrary to the trial court’s determination otherwise, the evidence showed Great American’s duty to indemnify was triggered, and expert testimony establishing the exact date of injury was not required to trigger the duty.”
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
A New Way to Design in 3D – Interview with Pouria Kay of Grib
August 24, 2017 —
Aarni Heiskanen - AEC BusinessIn this podcast interview with Pouria Kay, CEO and Co-founder at Grib, we talk about the startup’s new, intuitive 3D design tool.
Grib® is a cloud–based software that turns a mobile device into a universal controller. With Grib, both young and professional designers can sketch complex objects without first having to learn cumbersome 3D software.
You work intuitively in actual 3D space and interact with your environment using augmented reality. All you need is pen, paper, and your mobile device. You can share models with friends, order a print, or export them if needed.
Read the court decisionRead the full story...Reprinted courtesy of
Aarni Heiskanen, AEC BusinessMr. Heiskanen may be contacted at
info@aepartners.fi
Overruling Henkel, California Supreme Court Validates Assignment of Policies
October 02, 2015 —
Tred R. Eyerly – Insurance Law HawaiiIn a major ruling, the California Supreme Court applied a statutory provision to overrule its prior decision in Henkel Corp. v. Hartford Accident & Indemn. Co., 29 Cal. 4th 934 (2003) and ruled that liability policies can be assigned despite non-assignment provisions. See Fluor Corp. v. Superior Court, 2015 Cal. LEXIS 5631 (Cal. Aug. 20, 2015). The Hawaii Supreme Court relied on Henkel when it also found anti-consent provisions valid. See Del Monte Fresh Fresh Produce (Hawaii), Inc. v. Fireman's Fund Ins. Co., 117 Haw. 357, 183 P.3d 734 (2007) [see posts here and here].
For decades, Fluor Corporation performed engineering, procurement, and construction (EPC) operations through various corporate entities and subsidiaries. Beginning in 1971, Hartford issued up to 11 CGL policies to Fluor from 1971 to 1986. Each policy contained a consent-to-assignment clause reading: "Assignment of interest under the policy shall not bind the Company until its consent is endorsed hereon."
Beginning in the mid-1980s, Fluor Corporation was sued in numerous lawsuits claiming personal injury from asbestos exposure. Fluor Corporation tendered the early lawsuits to Hartford, which accepted the defense. Fluor Corporation subsequently went through a reverse spinoff under which a newly formed subsidiary, Fluor 2, took over the continuation of the company's EPC businesses. The original Fluor transferred all of its EPC-related assets and liabilities to Fluor-2, making Fluor-2 the parent of the EPC subsidiaries. The transaction did not except any insurance rights from the transfer of "any and all" assets.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at