California Supreme Court Finds that When it Comes to Intentional Interference Claims, Public Works Projects are Just Different, Special Even
November 21, 2017 —
Garret Murai - California Construction Law BlogOriginally published by CDJ on April 20, 2017
Earlier, we reported on a California Court of Appeals decision – Roy Allan Slurry Seal, Inc. v. American Asphalt South, Inc. – which held for the first time that a second-place bidder on a public works contract could sue a winning bidder who failed to pay its workers prevailing wages, under the business tort of intentional interference with prospective economic advantage.
Fast forward nearly two years, several amicus briefs, and “one doghouse”* later and the California Supreme Court has . . . reversed.
The Roy Allan Slurry Seal Case
To catch you up, or rather, refresh your recollection . . .
Between 2009 and 2012, American Asphalt South, Inc. was awarded 23 public works contracts totaling more than $14.6 million throughout Los Angeles, Orange, San Bernardino and San Diego counties. Two of the losing bidders on those projects – Roy Allan Slurry Seal, Inc. and Doug Martin Contracting, Inc. – sued American in each of these counties for intentional interference with prospective economic advantage as well as under the Unfair Practices Act (“UPA”) (Bus. & Prof. Code §§ 17000 et seq.) and the Unfair Competition Law (“UCL”) (Bus. & Prof. Code §17200).
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Wendel Rosen Black & Dean LLPMr. Murai may be contacted at
gmurai@wendel.com
White and Williams Selected in the 2024 Best Law Firms ranked by Best Lawyers®
December 04, 2023 —
White and Williams LLPWhite and Williams LLP is proud to be selected in the 2024 Best Law Firms ranked by Best Lawyers®.
The firm was recognized in the National Rankings in four practice areas including both Bankruptcy and Creditor Debtor Rights/Insolvency and Reorganization Law and Insurance Law (Tier 1). In addition, the firm’s office locations in Philadelphia, New York City, Boston, Baltimore, Delaware and New Jersey were recognized for 30 practice areas in the Metropolitan rankings.
Achieving a tiered ranking in Best Law Firms signals a unique combination of quality law practice and breadth of legal expertise. The Best Law Firms research methodology includes the collection of client and lawyer evaluations, peer review from leading attorneys in their field and review of additional information provided by law firms as part of the formal submission process.
The 2024 Best Law Firms rankings can be accessed at www.bestlawfirms.com.
2024 Best Law Firms
National Tier 1
- Bankruptcy and Creditor Debtor Rights / Insolvency and Reorganization Law
- Insurance Law
National Tier 3
- Construction Law
- Litigation – Construction
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP
Real Estate & Construction News Round-Up (01/25/23) – Artificial Intelligence, Proptech Innovation, and Drone Adoption
February 14, 2023 —
Pillsbury's Construction & Real Estate Law Team - Gravel2Gavel Construction & Real Estate Law BlogThis week’s round-up explores new artificial intelligence tools and their projected impact on real estate agents, key trends driving proptech innovation, barriers to adopting drones in the construction industry, and more.
- Artificial intelligence (AI) has the potential to become an invaluable tool to streamline the selling journey of a property, empower buyers to make informed decisions, and enhance the work of real estate agents. (Alexandra Cain, The Urban Developer)
- Miami real estate agents experiment with the new artificial intelligence tool, ChatGPT, which can generate text based on simple prompts, to write house listings, communicate with developers, and produce content. (Martin Vassolo, Axios)
- Asset owners in Asia and Europe turn to artificial intelligence to collect ESG information across public and private markets, including from residential buildings in Japan. (Hugo Cox, Asian Investor)
Read the court decisionRead the full story...Reprinted courtesy of
Pillsbury's Construction & Real Estate Law Team
There Are Consequences to Executed Documents Such as the Accord and Satisfaction Defense
October 01, 2024 —
David Adelstein - Florida Construction Legal UpdatesA federal government contractor in Jackson Construction Co., Inc. v. U.S., 62 Fed.Cl. 84 (Fed.Cl. 2024) sought delay damages against the government. It lost. The reason for the loss is a crucial reminder that documents parties sign ALWAYS matter. ALWAYS!!
In Jackson Construction Co., the contractor’s delay claim was premised on relocating a waterline. The contractor, however, received additional money for relocating the waterline, but no additional time, and this was memorialized in a modification to the contract (i.e., a change order). In executing the modification for the additional work, the contractor did NOT reserve rights for time or money. Indeed, the modification reflected that the monetary adjustment constitutes full compensation for the additional work including delay, namely:
The contract period of performance remains the same. It is further understood and agreed that this adjustment constitutes compensation in full on behalf of the contractor and his subcontractors and suppliers for all costs and markup directly or indirectly, including extended overhead, attributable to the change order, for all delays related thereto, and for performance of the change within the time frame stated.
Jackson Construction Co., supra, at 90.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Contractor Liable for Soils Settlement in Construction Defect Suit
February 10, 2012 —
CDJ STAFFThe California Court of Appeals ruled on January 9 in Burrow v. JTL Dev. Corp., a construction defect case in which houses suffered damage due to improperly compacted soil, upholding the decision of the lower court.
Turf Construction entered into a deal with JTL to develop a parcel they acquired. A third firm, Griffin Homes, withdrew from the agreement “when a geotechnical and soils engineering firm reported significant problems with soil stability on 14 of the lots.” Turf Construction then took over compacting and grading the lots. Turf “had never compacted or graded a residential tract before.” Robert Taylor, the owner of Turf, “testified he knew there was a significant problem with unstable soils.”
After homes were built, the plaintiffs bought homes on the site. Shortly thereafter, the homes suffered damage from soil settlement “and the damage progressively worsened.” They separately filed complaints which the court consolidated.
During trial, the plaintiff’s expert said that there had been an inch and a half in both homes and three to five inches in the backyard and pool areas. “He also testified that there would be four to eight inches of future settlement in the next fifteen to twenty years.” The expert for Turf and JTL “testified that soil consolidation was complete and there would be no further settlement.”
Turf and JTL objected to projections made by the plaintiffs’ soil expert, William LaChappelle. Further, they called into question whether it was permissible for him to rely on work by a non-testifying expert, Mark Russell. The court upheld this noting that LaChappelle “said that they arrived at the opinion together, through a cycle of ‘back and forth’ and peer review, and that the opinion that the soil would settle four to eight inches in fifteen to twenty years was his own.”
Turf and JTL contended that the court relied on speculative damage. The appeals court disagreed, stating that the lower court based its award “on evidence of reasonably certain damage.”
Turf also that it was not strictly liable, since it did not own or sell the properties. The court wrote that they “disagree because Turf’s grading activities rendered it strictly liable as a manufacturer of the lots.” The court concluded that “Turf is strictly liable as a manufacturer of the lots.”
Judge Coffee upheld the decision of the lower court with Judges Yegan and Perren concurring.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
Court Agrees to Stay Coverage Matter While Underlying State Action is Pending
October 29, 2014 —
Tred R. Eyerly – Insurance Law HawaiiThe federal district court granted the insured's motion to stay the coverage action while the construction defect case was pending in state court. Auto Owners Ins. Co. v. Essex Homes Southeast, Inc., 2014 U.S. Dist. LEXIS 133120 (D. S.C., Sept. 23, 2014).
The homeowners sued Essex Homes in state court for construction defects in a home built and sold to them by Essex Homes. The suit sought damages for property damage based on negligence, breach of implied warranty, and breach of express warranties arising out of the alleged construction defects. The complaint alleged that a water leak in the house caused water damage and resulted in mold growth that was not discovered for several years.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
Indiana Court of Appeals Rules Against Contractor and Performance Bond Surety on Contractor's Differing Site Conditions Claim
April 03, 2013 —
Brian M. Falcon - Frost Brown Todd LLCEarlier this year, the Indiana Court of Appeals issued an important opinion that impacts contractors and sureties alike. The decision should give contractors in Indiana pause before ceasing work while a dispute with the owner is pending. Sureties also have been placed on notice that strict compliance with the terms of their bonds is amongst their best defenses to claims made by owners and bond claimants.
In Dave's Excavating, Inc. and Liberty Mutual Insurance Co. v. City of New Castle, Indiana, 959 N.E.2d 369 (Ind. Ct. App. 2012), the contractor (“Dave’s”) was the successful bidder on a public sanitary sewer and water main extension project. Dave's procured a performance bond from Liberty Mutual to guarantee its performance obligations to the owner (the "City"). After encountering what it deemed different subsurface conditions—and indeed after having been previously granted a change order to use excavated materials as backfill in light of the subsurface conditions on site—Dave’s placed the project engineer on notice of a differing site conditions claim. The total claim amounted to an 84% increase in the total contract price. With the claim, Dave's advised the project engineer it was ceasing further work until the project engineer provided direction.
While the project engineer reviewed the claim, it reminded Dave's of its contractual obligation to "carry on the work and adhere to the progress schedule during all disputes or disagreements with the OWNER." A dispute immediately occurred regarding whether Dave's was required to continue to work while the project engineer resolved the differing site condition claim. After Dave's maintained its position that it was not required to continue to work, the project engineer placed it on notice of default and copied the letter to Liberty Mutual.
Read the court decisionRead the full story...Reprinted courtesy of
Brian M. FalconBrian M. Falcon can be contacted at http://www.frostbrowntodd.com/contact.html
City and Contractor Disclaim Responsibility for Construction Error that Lead to Blast
November 13, 2013 —
CDJ STAFFThe city of Grand Junction, Colorado and their contractor, Aperion Utility Construction, LLC, have both denied any wrongdoing in the construction accident that lead to the destruction of two homes. Aperion was drilling in order to repair traffic signals. Their drill damaged a gas line. In the subsequent explosion, three people were injured and two homes destroyed. Homes for 10 blocks were subsequently evacuated.
The three men who were injured have filed a lawsuit claiming negligence on the part of the contractor and the city. The city has released a report from their insurers that concluded that the city was not responsible.
Read the court decisionRead the full story...Reprinted courtesy of