Insurance Alert: Insurer Delay Extends Time to Repair or Replace Damaged Property
November 26, 2014 —
Valerie A. Moore & Christopher Kendrick – Haight Brown & Bonesteel LLPIn Stephens & Stephens XII v. Fireman's Fund Ins. (No. A135938, filed November 24, 2014), the plaintiffs obtained property insurance on a warehouse. Within a month, it was discovered to be stripped of all wiring and metal. Fireman's Fund paid for emergency repairs but nothing more, concerned that the damage had occurred outside the policy period.
The policy provided for valuation of either "replacement cost," meaning the expenditure required to replace the damaged property with "new property of comparable material and quality," or "actual cash value," defined as the actual, depreciated value of the damaged property. For replacement cost, Fireman’s Fund was not required to pay "until the lost or damaged property is actually repaired ... as soon as reasonably possible after the loss or damage," and only "[t]he amount [the insured] actually spend[s]...."
In the subsequent bad faith lawsuit, the jury awarded the full cost of repair, despite there being no repairs. The appeals court reversed, holding that there was no right to an immediate award for the costs of repairing the damage; however, the court nonetheless held that the insured was entitled to a "conditional judgment," awarding those costs if repairs were actually made.
Reprinted courtesy of
Valerie A. Moore, Haight Brown & Bonesteel LLP and
Christopher Kendrick, Haight Brown & Bonesteel LLP
Ms. Moore may be contacted at vmoore@hbblaw.com; Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Bankrupt Canada Contractor Execs Ordered to Repay $26 Million
April 25, 2022 —
Scott Van Voorhis - Engineering News-RecordJohn Aquino, the former president of a major and now bankrupt Ontario construction contractor, plans to appeal a provincial court ruling that puts him and his associates on the hook for $26.2 million drained from the company, according to his attorney.
Reprinted courtesy of
Scott Van Voorhis, Engineering News-Record
ENR may be contacted at enr@enr.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Las Vegas Partner Sarah Odia Named a 2023 Mountain States Super Lawyer Rising Star
August 28, 2023 —
Payne & Fears LLPPayne & Fears’ partner
Sarah J. Odia has been named to the list of 2023 Super Lawyers® Mountain States Rising Stars, recognizing her excellent contributions to the Las Vegas area legal community.
A Super Lawyers® Rising Stars selection is an honor reserved for those attorneys who exhibit excellence in practice. Lawyers nominate fellow attorneys who demonstrate excellence in the legal profession.
Reprinted courtesy of
Payne & Fears LLP
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Hudson River PCB Cleanup Lands Back in Court
September 03, 2019 —
Mary B. Powers - Engineering News-RecordAs it previously had warned, New York state on Aug. 21 filed a federal lawsuit against the U.S. Environmental Protection Agency seeking to reverse its certification that General Electric Co.'s removal of PCBs from the Hudson River was complete, despite the agency’s five-year review finding that the cleanup was not adequate to protect human health and the environment.
Read the court decisionRead the full story...Reprinted courtesy of
Mary B. Powers, ENRENR may be contacted at
ENR.com@bnpmedia.com
UPDATE: ACS Obtains Additional $13.6 Million for General Contractor Client After $19.2 Million Jury Trial Victory
June 27, 2022 —
Kristina Southwell - Ahlers Cressman & Sleight PLLCIn March 2022, ACS obtained a $19.2 million jury verdict in favor of its general contractor client after a lengthy trial against the project owner. Since that time, ACS has successfully obtained awards through post-trial motion practice for an additional $13.6 million in favor of the general contractor. These awards increased to total judgment to more than $32 million.
When moving to enter judgment on the jury verdict, ACS successfully argued for and obtained more than $5 million in prejudgment interest on the jury verdict to compensate the general contractor for having to go years without payment for work performed. ACS also successfully obtained a decree of foreclosure on its construction lien and incorporated language in the judgment requiring the owner to pay an additional $1.9 million in Washington State sales tax on the jury award. Finally, under the authority of the Washington construction lien statute (RCW 60.04.181), ACS sought to recover the attorneys’ fees, costs, and expenses incurred by the general contractor client during the course of litigation. ACS succeeded in obtaining an award for more than $6.6 million for various expenses and costs including ACS’s attorney fees, all the costs of hiring expert witnesses, costs and expenses related to subcontractors’ presentation of pass-through claims against the owner, and other litigation costs and expenses.
Read the court decisionRead the full story...Reprinted courtesy of
Kristina Southwell, Ahlers Cressman & Sleight PLLCMs. Southwell may be contacted at
wendy.wheatmccoy@acslawyers.com
Trumark Homes Hired James Furey as VP of Land Acquisition
April 08, 2014 —
Beverley BevenFlorez-CDJ STAFFAccording to GlobeSt.com, “Homebuilder Trumark Homes has hired James Furey as VP of land acquisition.” The “veteran developer” has held positions at Meritage Homes, Richmond American Homes, and Beazer Homes USA.
“James is a versatile manager who brings a wealth of experience in many elements of the homebuilding process,” Jason Kliewer, partner and general counsel for Trumark, told GlobeSt.com. “He will be an invaluable asset as Trumark moves aggressively in the California market.”
Read the court decisionRead the full story...Reprinted courtesy of
The Future for Tall Buildings Could Be Greener
October 01, 2013 —
CDJ STAFFSkidmore, Owens and Merrill made its reputation by creating iconic structures of steel, concrete, and glass, but in a new report, the firm puts forth ways in which the first item would be wood. Building codes in many cities stipulate that buildings taller than four stories be built of steel and concrete, but the firm says that it has come up with a way of building structures of 30 stories or more using wood.
The tallest wood-framed building currently is only ten stories tall. In order to calculate a comparison, Skidmore, Owens and Merrill designed a forty-two story building based on the design of an existing apartment building. Actually building it would require almost 4 million board-feet of wood. Unlike a typical single-family home (and its 20,000 board-feet of wood), these building would use glue-laminated timber and slabs.
The study found that the building would weigh less than half as much, allowing a less massive foundation. If the wood came from sustainable sources, its environmental impact would be drastically reduced. They calculated that instead of 9,500 tons of CO2 emissions for the conventional tower, the wood structure would be responsible for only 2,100 tons of emissions.
Skyscrapers will continue to be a feature of large cities. But instead of urban canyons of steel and concrete, in the future those towering buildings might be made of wood.
Read the court decisionRead the full story...Reprinted courtesy of
New California "Construction" Legislation
November 08, 2018 —
Richard H. Glucksman, Esq. & Chelsea L. Zwart, Esq. - Chapman Glucksman Dean Roeb & BargerGovernor Jerry Brown signed two potentially impactful Senate Bills relating to the construction of apartment buildings late last month. These Bills, discussed further below, were introduced, in part, in response to the Berkeley balcony collapse in June 2015, which was determined by the California Contractors State License Board to be caused by the failure of severely rotted structural support joists the repair of which were deferred by the property manager, despite indications of water damage.
SENATE BILL 721 ESTABLISHES HEIGHTENED “LOAD-BEARING” INSPECTION REQUIREMENTS
On August 21, 2018, the California State Senate passed SB 721, one of two bills by Senator Jerry Hill introduced this year seeking to address the safety of multifamily rental residences. Now that the Governor has signed the Bill, a new section will be added to the California Health and Safety Code, requiring that every 6 years, destructive testing be performed on at least 15% of each type of load-bearing, wood framed exterior elevated element (such as balconies, walkways, and stair landings) in apartment buildings with 3 or more units. Interestingly, prior to being passed by the State Senate, SB 721 was revised in June 2018, such that the inspection requirements do not apply to common interest developments (i.e., condominiums).
As set forth in the new Health and Safety Code Section 17973:
"the purpose of the inspection is to determine that exterior elevated elements and their associated waterproofing elements are in a generally safe condition, adequate working order, and free from any hazardous condition caused by fungus, deterioration, decay, or improper alteration to the extent that the life, limb, health, property, safety, or welfare of the public or the occupants is not endangered."
The inspection must be paid for by the building owner and performed by a licensed contractor, architect, or civil or structural engineer, or a certified building inspector or building official from a recognized state, national, or international association. Emergency repairs identified by the inspector must be made immediately. For non-emergency repairs, a permit must be applied for within 120 days and the repair completed within 120 days of the permit’s issuance. If repairs are not completed within 180 days, civil penalties of $100-$500 per day may be imposed.
The required inspection must be completed by January 1, 2025 and every 6 years thereafter, unless an equivalent inspection was performed during the 3 years prior to January 1, 2019, the effective date of the new law. For a building converted to condominiums that will be sold after January 1, 2019, the inspection required by Health and Safety Code Section 17973, must be performed prior to the first close of escrow.
SENATE BILL 1465 SETS CONTRACTOR REPORTING REQUIREMENTS
The Governor also signed SB 1465, adding Sections 7071.20, 7071.21, and 7071.22 to the California Business and Professions Code. The new law requires that a contractor licensed with the Contractors’ State License Board "report to the registrar in writing within 90 days after the licensee has knowledge of any civil action resulting in a final judgment, executed settlement agreement, or final arbitration award in which the licensee is named as a defendant or crossdefendant, filed on or after January 1, 2019," that meets certain and specific criteria, including that it is over $1 million and arises out of an action for damages to a property or person allegedly caused by specified construction activities of the contractor on a multifamily rental residential structure.
Where more than one contractor was named as a defendant or cross-defendant, each of the contractors apportioned more than $15,000 in liability must report the action. Importantly, the new statute also imposes similar reporting requirements on insurers of contractors. SB 1465 also addresses an impacted party’s failure to comply with the reporting requirements.
COMMENT
Both SB 721 and SB 1465 are potentially significant and seek “legislative reform” to address construction issues by placing a greater burden on apartment owners as well as builders and subcontractors. How pragmatic and what impact they will have on the industry is obviously developing. If you are interested in receiving further detail concerning the Bills, please contact us. We are analyzing the new legislation and its intent and will be providing our ongoing comments.
Read the court decisionRead the full story...Reprinted courtesy of
RICHARD H. GLUCKSMAN, ESQ. CHELSEA L. ZWART, ESQ., CGDRBChelsea L. Zwart may be contacted at