Everyone Wins When a Foreclosure Sale Generates Excess Proceeds
August 07, 2018 —
Ben Reeves - Snell & Wilmer Real Estate Litigation BlogIntroduction
When a foreclosure sale generates more money than needed to pay off the lien, the excess proceeds usually go first to creditors in the order of their priority, and second to the owner after creditors are paid in full. So, in truth, not everyone wins when a foreclosure sale brings in too much money. Amusingly, in Steinmetz v. Everyone Wins, the court awarded excess sale proceeds to….you guessed it…Everyone Wins, despite the owner’s argument that Arizona’s anti-deficiency statutes barred it from recovering anything.
In addition to supplying a clever title for this post, Steinmetz v. Everyone Wins provides an important analysis of how Arizona’s anti-deficiency statutes, homeowner’s assessment lien statutes, and foreclosure statutes apply when determining who “wins” when it comes to excess sale proceeds.
Read the court decisionRead the full story...Reprinted courtesy of
Ben Reeves, Snell & WilmerMr. Reeves may be contacted at
breeves@swlaw.com
Value In Being Deemed “Statutory Employer” Under Workers Compensation Law
November 21, 2022 —
David Adelstein - Florida Construction Legal UpdatesWhen it comes to workers compensation law, as a contractor, there are a couple of important considerations. One, you will be deemed a statutory employer. And two, you want your subcontractors (and, of course, yourself) to have workers compensation insurance so that you can enjoy the protection of workers compensation immunity. Workers compensation immunity provides immunity to an employer (i.e., a statutory employer) by workers compensation insurance becoming the exclusive form of liability.
A recent non-construction case, Bar-Harbour Tower Condominium Association, Inc. v. Bellorin, 47 Fla.L.Weekly D2114a (Fla. 3d DCA 2022), illustrates the importance of these considerations. Here, a condominium association per its governing documents (i.e., declaration of condominium) was authorized to contract for valet parking services for its unit owners. An employee of the valet company (hired by the association) got hurt and sued the association. The association argued it should be deemed a statutory employer under workers compensation law and, as such, entitled to workers compensation immunity. The trial court disagreed, and the association appealed. The Third District Court of Appeal held the association was the statutory employer and, thus, workers compensation immunity did apply.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at
dma@kirwinnorris.com
Construction Litigation Roundup: “Just Hanging Around”
August 14, 2023 —
Daniel Lund III - LexologyA subcontractor asserting a payment bond claim for “standby” time for its equipment on the Cline Avenue bridge project (over Indiana Harbor and Ship Canal in East Chicago, Indiana) received pushback from the payment bond surety.
In fact, the duration of the standby time occurred after the surety’s principal, the general contractor, had been placed in default and terminated on the general contract. According to the surety: “After termination of the contract… it is impossible for labor, materials, and equipment to have been furnished for use in performing the terminated contract.” The surety filed a motion for summary judgment.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Lund III, PhelpsMr. Lund may be contacted at
daniel.lund@phelps.com
Lewis Brisbois Ranks Among Top 25 Firms on NLJ’s 2021 Women in Law Scorecard
July 25, 2021 —
Jana Lubert - Lewis BrisboisLewis Brisbois has been ranked among the top 25 law firms included in the National Law Journal's (NLJ) 2021 Women in Law Scorecard (Women’s Scorecard), moving up from 27th place to 23rd place this year. In addition, of the top 25 firms in the Women’s Scorecard, Lewis Brisbois had the highest number of female minority partners.
The Women’s Scorecard is produced as part of the annual NLJ 500 firm head count report, and only the largest 350 firms are eligible to be included on the scorecard. A firm’s score is determined by adding the percentage of female attorneys and percentage of female partners. Diversity staffing counts were based on a firm’s average full-time attorneys in 2020, excluding contract and temporary attorneys.
Read the court decisionRead the full story...Reprinted courtesy of
Jana Lubert, Lewis BrisboisMs. Lubert may be contacted at
Jana.Lubert@lewisbrisbois.com
Robinson+Cole’s Amicus Brief Adopted and Cited by Massachusetts’s High Court
July 31, 2024 —
Erica Whaley - Construction Law ZoneEarlier this year, the
Associated Subcontractors of Massachusetts hired Robinson+Cole attorney
Joseph Barra to submit an amicus brief to the Massachusetts Supreme Judicial Court for consideration in the appeal pending before it in
Business Interiors Floor Covering Business Trust v. Graycor Construction Co., Inc. In its June 17, 2024 decision in that case, the Court interpreted the Massachusetts Prompt Pay Act, which applies to private construction projects and “requires that parties to a construction contract approve or reject payment within” an allotted time period and in compliance with certain procedures else such payments will be deemed approved. Two years ago, the Massachusetts Appeals Court, in
Tocci Building Corp. v. IRIV Partners, LLC, decided that an owner who fails to timely advise its general contractor of the reasons as to why it was withholding payment, coupled with failure to certify that such funds are being withheld in good faith, violates the Prompt Pay Act and makes the owner liable for funds owed.
[1] However, the Tocci Building Court left open the question of whether one who violates the Prompt Pay Act forfeits its substantive defenses to non-payment, such as fraud, defective work, or breach of material obligation of the contract.
The facts of Business Interiors involve a general contractor, Graycor, which subcontracted Business Interiors to perform certain flooring work for a movie theatre in Boston’s North End. When Graycor failed to formally approve, reject, or certify, in good faith, its withholding of payment of three of Business Interiors’ applications for payment as prescribed by the Prompt Pay Act, Business Interiors brought suit alleging, among other things, breach of contract. Business Interiors then moved for summary judgement arguing that Graycor’s failure to comply with the Act rendered it liable for the unpaid invoices.
Read the court decisionRead the full story...Reprinted courtesy of
Robinson + Cole
Attorney's Erroneous Conclusion that Limitations Period Had Not Expired Was Not Grounds For Relief Under C.C.P. § 473(b)
February 27, 2019 —
David W. Evans & Stephen J. SquillarioIn Jackson v. Kaiser Foundation Hospitals, Inc. (2/8/19 No. A150833), the First District Court of Appeal affirmed the trial court’s denial of a motion for relief from a voluntary dismissal, without prejudice, filed by the plaintiff based on the erroneous conclusion of an attorney who she had consulted (but who had not yet appeared as counsel in her case) that the applicable statute of limitations had not yet expired. In reality, the limitations period had expired on the same date plaintiff had filed her complaint in propria persona. The plaintiff later retained the attorney on a limited basis to present the motion for relief pursuant to Code of Civil Procedure § 473(b) based on the attorney’s affidavit of fault. Therein, the attorney testified that he had advised the plaintiff to dismiss her action voluntarily based on a misinterpretation of the applicable limitations period, which the attorney characterized as having been based on his “mistake, inadvertence, surprise, or neglect.”
Section 473 provides two distinct provisions for relief from default or dismissal – one is discretionary, while the other is mandatory. Discretionary relief is available in the case of an attorney’s mistake, inadvertence, surprise, or excusable neglect. In contrast, mandatory relief is available where the resulting dismissal was caused by an attorney’s mistake, whether or not excusable. In denying the plaintiff’s motion, the trial court reasoned that the plaintiff could not rely upon Section 473(b) because (1) the attorney did not represent the plaintiff at the time and (2) this provision did not apply to the voluntary dismissal of an action without prejudice.
Reprinted courtesy of
David W. Evans, Haight Brown & Bonesteel LLP and
Stephen J. Squillario, Haight Brown & Bonesteel LLP
Mr. Evans may be contacted at devans@hbblaw.com
Mr. Squillario may be contacted at ssquillario@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Appeals and Agency Developments at the Close of 2020
December 29, 2020 —
Anthony B. Cavender - Gravel2GavelTHE FEDERAL APPELLATE COURTS
The U.S. Court of Appeals
On November 23, 2020, the court, in a 2-to-1 vote, rejected the plaintiff’s request for an emergency injunction pending appeal in the case of Manzanita Band of Kumeyaay Nation, et al. v. Wolf. The majority held the requirement for such relief did not meet the requirements set forth in Winter v. NRDC, 555 US 7 (2008). Here, the plaintiffs allege that that the government’s construction of a border wall violates several environmental laws that were illegally waived by the Secretary of the Interior. Judge Millett dissented in part because the plaintiffs demonstrated a likelihood of success on the merits. She pointed to the argument that the authority of the Secretary—or Acting Secretary—to take these actions has been successfully challenged in several federal district courts. An expedited pleading schedule was established by the court.
The U.S. Court of Appeals for the Fourth Circuit
On November 17, 2020, in Ergon-West ,Inc. v. EPA, the court again reversed the EPA’s decision denying regulatory relief to a small refinery seeking a waiver of the renewable fuels mandate of the Clean Air Act. Ergon is a small refinery and requested relief in the basis of the economic harm that compliance would entail. In 2018, the court ruled in Ergon’s favor and remanded the case back to the agency. After relief was again denied, the court held that “Ergon has come forward with sufficient evidence undermining one aspect” of the agency’s latest decision, and the ruling was returned to EPA for additional analysis. It appears that a complicated process has become even more complicated.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Eyerly may be contacted at
te@hawaiilawyer.com
“Pay When Paid” Provisions May Not Be Dead, at Least Not Yet
August 24, 2020 —
Garret Murai - California Construction Law BlogSophisticated contractors know that in California contractual “pay when paid” provisions are enforceable but that “pay if paid” provisions are not.
“Pay If Paid” v. “Pay When Paid” Provisions
A “pay if paid” provision is one in which a higher tier party agrees to pay a lower tier party “if” it is paid in turn by a still higher party. Most commonly they are found in subcontracts between general contractors and subcontractors and provide that the general contractor will pay the subcontractor “if” the general contractor is paid by the project owner. However, they can also be found in subcontracts between higher and lower tiered subcontractors and between subcontractors and material suppliers and equipment lessors. In California, such provisions, which create a condition precedent to payment, namely, a condition that must precede payment to a lower tiered party, are void as a matter of law.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at