Ambiguous Application Questions Preclude Summary Judgment on Rescission Claim
July 19, 2017 —
Christopher Kendrick & Valerie A. Moore – Haight Brown & Bonesteel LLPIn Duarte v. Pacific Specialty Ins. (No. A143828; filed 6/12/17, ord. pub. 6/29/17) a California appeals court held that an insurer was not entitled to summary judgment on its rescission claim because the disputed questions in the insurance application were ambiguous.
In Duarte, the insured/owner purchased a tenant-occupied property in Oakland. Several years later the tenant’s daughter moved in, and continued living there after the tenant died. The insured/owner served the daughter with an eviction notice and shortly thereafter applied for Owners, Landlords & Tenants (“OLT”) liability coverage. The tenant/daughter responded to the eviction notice by filing a habitability lawsuit, claiming emotional distress and physical injury, among other things.
The insurer denied coverage and a defense, drawing a bad faith lawsuit for failure to defend and “wrongful cancellation” of the policy. The insurer answered and raised rescission as an affirmative defense, based on alleged fraud and misrepresentation in the OLT policy application.
Reprinted courtesy of
Christopher Kendrick, Haight Brown & Bonesteel LLP and
Valerie A. Moore, Haight Brown & Bonesteel LLP
Mr. Kendrick may be contacted at ckendrick@hbblaw.com
Ms. Moore may be contacted at vmoore@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Extreme Heat, Smoke Should Get US Disaster Label, Groups Say
July 15, 2024 —
Jennifer A Dlouhy - BloombergActivists are petitioning the US government to formally classify extreme heat and wildfire smoke as major disasters, as soaring temperatures threaten to set records across much of the country.
In a petition filed with the Federal Emergency Management Agency, they seek to unlock new funding to help communities address such events before they strike, with money for air filters that strip out smoke and rooftop solar systems that can supply electricity when demand overwhelms power grids.
Climate change has made fatal heat waves more intense and frequent, while hotter, drier conditions stoke the risk of fires that can blanket the US in toxic smoke. An estimated 2,300 people in the US died from heat-related illness in 2023, the hottest year on record. And heavy smoke from wildfires in Canada last year traveled as far south as Georgia, prompting people to shelter inside and canceling flights in some of the largest US cities.
Read the court decisionRead the full story...Reprinted courtesy of
Jennifer A Dlouhy, Bloomberg
Daniel Ferhat Receives Two Awards for Service to the Legal Community
July 19, 2021 —
Daniel Ferhat - White and Williams LLPPartner Daniel Ferhat was recently recognized by The Philadelphia Association of Defense Counsel (PADC) with the President’s Award at PADC’s Annual Meeting. This award was given in recognition of Dan’s leadership as President of PADC over the past year. Recognized as the oldest continuously operating local defense organization in the United States, PADC is comprised of over 300 attorneys and acts as a voice for its members and the clients they serve on emerging issues of interest.
Dan also received the Exceptional Performance Award from the Defense Research Institute (DRI), which is the largest international membership organization of attorneys defending the interests of businesses and individuals in civil litigation. DRI’s Exceptional Performance Award is given annually to an individual who has supported and improved the standards and education of the defense bar, and for having contributed to the improvement of the administration of justice in the public interest.
Read the court decisionRead the full story...Reprinted courtesy of
Daniel Ferhat, White and Williams LLPMr. Ferhat may be contacted at
ferhatd@whiteandwilliams.com
Maybe California Actually Does Have Enough Water
September 06, 2021 —
Francis Wilkinson - BloombergIt’s hard to know how much to panic over California’s dwindling water supplies. The state has never really had enough water, after all, yet lawns in Beverly Hills somehow remain perpetually green. Earlier this month, however, came a sign that life might soon be getting more uncomfortable for more Californians.
On Aug. 3, the State Water Resources Control Board voted 5 to 0 to issue an “emergency curtailment” order for the Sacramento-San Joaquin Delta watershed. Last week the order was submitted to the state’s Office of Administrative Law, which is likely to approve it.
The watershed covers about 40% of the state, stretching roughly from Fresno to Oregon, and is California’s largest source of surface water. About 5,700 holders of water rights, largely in agriculture and business, will be affected by the reduction in water access. Although many farms have already drawn most of the water they need for the season, the board’s move was a sign that ancestral water rights won’t be a guarantee of actual water if drought persists.
Read the court decisionRead the full story...Reprinted courtesy of
Francis Wilkinson, Bloomberg
No Occurrence Where Contract Provides for Delays
March 01, 2017 —
Tred R. Eyerly – Insurance Law HawaiiApplying Montana law, the federal district court found there was no coverage for a subcontractor who was sued by the contractor for breach of the subcontract. Phoenix Ins. Co. v. Ed Boland Constr., Inc., 2017 U.S. Dist. LEXIS 6654 (D. Mont. Jan 18, 2017).
Northbank was the general contractor on a project to repair a bridge for the Federal Highway Administration (FHA). Ed Boland Construction, Inc. (EBC) was the subcontractor to perform drilling and pile installation. After beginning its work, EBC ran into difficulties with unforeseen conditions at the work site. The FHA informed Northbank that it had concerns over EBC's ability to complete the work. The FHA alleged that EBC had brought equipment to the work site that differed from the equipment it had represented would be used.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Insurance Law HawaiiMr. Eyerly may be contacted at
te@hawaiilawyer.com
California Contractor Tests the Bounds of Job Order Contracting
March 01, 2021 —
Garret Murai - California Construction Law BlogMost contractors have heard of design-bid-build, design-build, construction manager at risk, and even public private partnerships, various project delivery methods, which, at their heart, focus on balancing the interests of the various parties involved in a construction project, from owners, to design professionals, to contractors. There’s one project delivery method you may not be as familiar with though: Job Order Contracting, also known by its acronym JOC.
JOC contracting is a project delivery method used on public works projects and has been authorized to be used by California K-12 school districts, community colleges, CalState universities, and the Judicial Council of California, which, among other things, is responsible for the construction of California state courts. It is intended to be used on smaller, independent, long-horizon project typically involving maintenance, repair and refurbishment. Think periodic maintenance of facilities.
JOC contracts are administered by public entities issuing a request for proposals. The public entity then awards a JOC contract to the lowest responsible bidder. The lowest responsible bidder then enters into a JOC contract with the public entity. JOC contracts typically have a duration of one (1) year and are limited to a total construction value of $4.9 million increased annually based on the Consumer Price Index. When entering into a JOC contract, a JOC contractor agrees to perform work at prices set forth in a Construction Task Catalog also known as a unit price book which includes current local labor, material and equipment costs. Unit prices are then adjusted by a “bid adjustment factor” based on the JOC contractor’s bid. When work is needed, the public entity will then issue a job order to the JOC contractor.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
How Berger’s Peer Review Role Figures In Potential Bridge Collapse Settlement
August 26, 2019 —
Richard Korman - Engineering News-RecordAs negotiations near a conclusion for a settlement with victims of last year’s fatal Florida International University bridge collapse, the role of the Louis Berger Group as peer review consultant is proving crucial. Attorneys for families of the six people who were killed and survivors say Berger is the last defendant that has not agreed to terms in lawsuits in state court in Miami against the companies that designed and built the bridge.
Read the court decisionRead the full story...Reprinted courtesy of
Richard Korman, ENRMr. Korman may be contacted at
kormanr@enr.com
Congratulations 2019 DE, NJ and PA Super Lawyers and Rising Stars
May 26, 2019 —
White and Williams LLPFifteen White and Williams lawyers have been named by Super Lawyers as a Delaware, New Jersey or Pennsylvania "Super Lawyer" while eight received "Rising Star" designations. Each lawyer who received the distinction competed in a rigorous selection process which took into consideration peer recognition and professional achievement. The lawyers named to this year's Super Lawyer list represent a multitude of practices throughout the firm.
Super Lawyers 2019 |
Attorney | Practice Area |
John Balaguer |
PI Defense: Med Mal |
Kevin Cottone |
PI Defense: Med Mal |
Thomas Goutman |
Class Action |
David Haase |
Business Litigation |
Christopher Leise |
Civil Litigation: Defense |
Randy Maniloff |
Insurance Coverage |
David Marion |
Business Litigation |
Peter Mooney |
Business Litigation |
Michael Olsan |
Insurance Coverage |
John Orlando |
General Litigation |
Wesley Payne |
Insurance Coverage |
Daryn Rush |
Insurance Coverage |
Anthony Salvino |
Workers’ Comp |
Patricia Santelle |
Insurance Coverage |
Andrew Susko |
Civil Litigation: Defense |
Read the court decisionRead the full story...Reprinted courtesy of
White and Williams LLP