Include Contract Clauses for Protection Against Ever-Evolving Construction Challenges
May 30, 2022 —
Michael Henry & Kevin J. Riexinger - Construction ExecutiveThe first quarter of 2022 provided a valuable glimpse into some of the major issues the construction industry can expect to continue impacting jobsites for the rest of the year.
Early in the pandemic, construction was not immune from the shut-downs that swept across market sectors. Workers were staying home to shield themselves and their families from the COVID-19 virus (and variants). This caused delays with construction projects and failures to meet negotiated benchmarks or deadlines. Contractors were left to wonder whether they remained obligated to perform under their contracts, or whether COVID-19 allowed them to invoke force majeure clauses. Over the past two years, there has been much debate about whether force majeure clauses encompass COVID-19 risks.
Traditionally, force majeure is only invoked for significant weather events or natural disasters. Unsurprisingly, outcomes of legal actions regarding COVID-19 and force majeure varied by state and by contract. It didn’t take long for contractors to seek a more predictable and certain solution.
Reprinted courtesy of
Michael Henry & Kevin J. Riexinger, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Mr. Riexinger may be contacted at kriexinger@gllawgroup.com
Mr. Henry may be contacted at MbHenry@tcco.com
Read the court decisionRead the full story...Reprinted courtesy of
Concrete Worker Wins Lawsuit and Settles with Other Defendant
December 04, 2013 —
CDJ STAFFHildo De Franca was injured in 2010 while pouring concrete for a residence in Perkasie, Pennsylvania. According to the lawsuit, when a concrete line plugged, the truck operator increased pump pressure, despite this not being the appropriate procedure. Mr. De Franca was injured when the hose snapped back after the clog burst free. Mr. De Franca sued both the Trans-Fleet Concrete Inc. and Albino Concrete Construction. Mr. De Franca was employed by a third party, Girafa Construction Inc., which had been hired by Albino.
Albino Construction settled with Mr. De Franca for $500,000. Trans-Fleet did not settle. The judgment against them was for $2.25 million, of which $2 million was for pain and suffering. As a result of the accident, Mr. De Franca suffered a mild brain injury and a compression fracture in his spine.
Read the court decisionRead the full story...Reprinted courtesy of
Women Make Slow Entry into Building Trades
December 04, 2013 —
CDJ STAFFIn the next seven years, about 200,000 carpenters will be added to workforce, but few of those are likely to be women. Sylas Demello, an electrical apprentice noted that it isn’t “made clear for women in high school to say, ‘hey, this is an option for you.’”
Tiffany Bluemle is trying to do something about that. She runs Vermont Works for Women, which trains women for jobs in which there are few women, including the building trades. She notes that “seventy-five percent of owners say they face labor shortages.”
Amy Judd is now one of those owners. Fifteen years ago, failing to find a teaching job, she started working as a carpenter. “It had never occurred to me that I would want to be a carpenter,” she said. Her firm employs eight people, half of whom are women.
Read the court decisionRead the full story...Reprinted courtesy of
Margins May Shrink for Home Builders
November 06, 2013 —
CDJ STAFFHome builders are worried that the rising prices of new homes might not rise enough and be caught by the rising costs of building them, cutting into the profit margin. “If builders say the trajectory of margins is beginning to peak, then in a cyclical business, people tend to go from thinking the best to thinking the worst,” Stephen Kim, a Barclays analyst told the Wall Street Journal. As of the end of October, the U.S. Home Construction Index was 21% below its highest point in 2013, set back in May.
Margins are still over those of last year. Meritage Homes saw a gross margin of 22.8% in 2013’s third quarter, when the same quarter in 2012 had a gross margin of 18.6%. Steven Hilton, the firm’s Chairman and CEO, predicted little or no growth and a decline toward 20% or 21%. On the other hand, with margins at 20.6%, Ryland Homes sees itself at a normal point. Larry Nicholson, the President and CEO of Ryland, said “there’s not a lot of room for it to grow.”
Read the court decisionRead the full story...Reprinted courtesy of
Actual Cost Value Includes Depreciation of Repair Labor Costs
November 07, 2022 —
Tred R. Eyerly - Insurance Law HawaiiThe court granted the insurer's motion to dismiss after determining that benefits paid for actual cost value (ACV) did not include repair or replacement labor costs. Shahan v. Allstate Vehicle & Prop. Ins. Co., 2022 U.S. Dist. LEXIS 135488 (W.D. La. July 29, 2022).
Hurricane Laura damaged the insured's home. She filed a claim with Allstate under her homeowners policy. Allstate issued payment. The insured filed suit alleging Allstate wrongfully withheld amounts by depreciating labor when calculating the ACV of the damaged property. Allstate moved to dismiss.
The policy was a replacement cost policy where the insured would receive the actual cash value of her insured property when it was damaged or destroyed by a covered peril. ACV was calculated by taking the repair/replacment which included both material and labor, and then deducting for depreciation. If no repairs or replacements were made, the insured was paid the ACV. If repairs or replacement was done, Allstate reimbursed the insured for the depreciation deduction. The insured challenged Allstate's refusal to pay 100% of the future labor costs, without any depreciation, even if the insured did not replace or repair the damaged property.
Read the court decisionRead the full story...Reprinted courtesy of
Tred R. Eyerly, Damon Key Leong Kupchak HastertMr. Eyerly may be contacted at
te@hawaiilawyer.com
4 Lessons Contractors Can Learn From The COVID-19 Crisis
May 25, 2020 —
Patrick Hogan - Handle.comAt the start of 2020, the industry outlook in construction was positive. Many contractors were optimistic about what the year had in store for construction businesses in terms of profit, expansion of operations, and even payment issues. That was until the COVID-19 pandemic put a wrench in everyone’s business plans.
There’s no question about how huge the impact of the novel coronavirus crisis is on business operations. With the federal and state governments implementing strict measures to slow down the spread of COVID-19, construction businesses are experiencing significant delays and disruptions in their operations. Because of the lockdowns and stay-at-home orders, many construction projects are forced to postpone operations or, worse, cancel them altogether.
Nevertheless, there are lessons in the COVID-19 pandemic that contractors can learn. Here are some of them.
1. Contractors need to be proactive in meeting preliminary notice requirements
Cash is tight in times of crisis. As the economy comes to a standstill, construction businesses will need to deal with decreasing profits. They may even have to dip into their own cash reserves to cover fixed expenses and their employees’ salaries.
In times like this, it is crucial that contractors perform due diligence in protecting their right to get paid. The first step in doing so is to prepare
preliminary notices. These notices are an important step in the mechanics lien process and without them, chances contractors will not be able to recover the unpaid compensation for the materials they furnished and services they rendered.
2. Force majeure provisions are crucial parts of a contract
The novel coronavirus pandemic has highlighted the importance of force majeure provisions in construction contracts. Before the COVID-19 crisis hit business operations, force majeure provisions were typically considered as simple boilerplate clauses. This means they were just there as a standard part of contracts.
However, the same force majeure clauses, as well as impossibility of performance provisions, have become crucial in the current crisis. As many construction businesses experience difficulties with their operations, they may not be able to fulfill their contractual responsibilities. The said clauses can give contractors a much-needed reprieve.
As the current crisis continues, contractors should review contracts as these provisions can give them more time to finish the job. And in the hopefully near future when the crisis ends, business owners should review the contract creation process and ensure that these clauses included in contracts will be able to address the impact of situations similar to COVID-19.
3. Having solid internal communication is crucial
There’s a lot of uncertainty with the COVID-19 situation. With work operations temporarily stopping, the circumstances can be quite stressful for employees. There will be doubts and fears within your workforce on whether work will be back to normal as soon as possible or not.
Keeping your workforce well-informed and trusting of your organization is crucial, especially in this time of uncertainty. That is why it is paramount that you have a solid internal communication infrastructure to disseminate information about the current work situation and the next steps that the business will take. In addition, only through proper employee communication can the implementation of social distancing and hygiene measures be effective.
4. Contractors can benefit from flexible work arrangements
As the coronavirus crisis has made it necessary for everyone to stay at home, construction businesses should look for ways to continue operations. Expanded work arrangements such as work-from-home setups may just be the solution.
Of course, most of the physical work that is needed to be done on-site will be impossible to do at home, but office-based functions such as sales, client relations, design, and administrative roles can still continue. This can even have additional benefits to productivity and health. And when the crisis is over, business owners should consider incorporating these work arrangements into their operations permanently.
The COVID-19 crisis is not showing any sign of stopping soon, and even when it ends, it will take quite a long time before we can be back to business as usual. As the crisis continues, however, business owners should take the situation as a learning experience.
Once the COVID-19 crisis is over, it will take a long time for things to go back to normal. In fact, things may not end up going back to the way they were before and businesses will need to adapt to the new normal. However the situation evolves, business owners should take this opportunity to learn new things and maintain resilience in trying times.
About the Author:
Patrick Hogan is the CEO of Handle.com, where they build software that helps contractors, subcontractors, and material suppliers with late payments. Handle.com also provides funding for construction businesses in the form of invoice factoring, material supply trade credit, and mechanics lien purchasing.
Read the court decisionRead the full story...Reprinted courtesy of
A Court-Side Seat: Waters, Walls and Pipelines
August 03, 2020 —
Anthony B. Cavender - Gravel2GavelSeveral interesting decisions have recently been made by federal and state courts.
FEDERAL APPELLATE COURTS
The U.S. Seventh Circuit Court of Appeals – ARCO Shifts from State to Federal and No Vigor for VIM
On June 18, 2020, the court decided the case of Baker, et al. v. ARCO, holding that the revised federal removal statutes authorize the removal to federal court of a state-filed complaint against several defendants by the former residents of an Indiana housing complex who contended that the defendants were responsible for the industrial pollution attributed to the operations of a now-closed industrial plant. The housing complex was constructed at the site of the former U.S. Smelter and Lead Refinery. During the Second World War, the plant produced products for the use of the government war effort, thus triggering the applicability of the federal removal statutes.
On June 25, 2020, the court decided the case of Greene, et al. v. Westfield Insurance Company. As the court notes, this is a matter that “began as a case about environmental pollution and evolved into a joint garnishment action.” An Indiana wood recycling facility, VIM Recycling, was the subject of many complaints by nearby residents that its operations and waste disposal activities exposed then to dust and odors in violation of federal law and triggered state tort law claims. VIM was sued in state court, but neglected to notify its insurer, as required by its insurance policy with Westfield Insurance. One thing led to another, and a default judgment in the amount of $ 50 million was entered against VIM. Since VIM at that point had no assets, the plaintiffs and later VIM sought recovery from Westfield. When this dispute landed in federal court, the court, after reviewing the policy, concluded that there was a provision excluding coverage when the insured knew it had these liabilities when it purchased the insurance. As a result, the lower court dismissed the lawsuit, and this decision has been affirmed by the Seventh Circuit.
Read the court decisionRead the full story...Reprinted courtesy of
Anthony B. Cavender, PillsburyMr. Cavender may be contacted at
anthony.cavender@pillsburylaw.com
Policyholders' Coverage Checklist in Times of Coronavirus
March 16, 2020 —
Richard W. Brown & Andres Avila - Saxe Doernberger & Vita, P.C.Every state but West Virginia have reported hundreds of Coronavirus (COVID-19) cases in the U.S. More than half are in California, Washington, New York, and Massachusetts. The unprecedented social and economic impact of the Coronavirus makes it necessary for policyholders to keep open all lines of communications with their insurance brokers, insurance carriers, financial advisors, safety & compliance experts, and insurance coverage counsel even if it is not certain whether they will need to file insurance claims.
As always, the specific terms of the insurance policies and the way losses are documented and presented to insurance carriers will be pivotal in securing coverage for Coronavirus-related exposures, such as jobsite closures, stop-work orders, remote work mandated measures, business interruption, event cancelation, employees’ claims, among others.
Policyholders should consider the following checklist of key insurance coverage tasks to be better positioned to face the risks posed by the Coronavirus:
- Pre-Loss Risk Management: A careful review of the policyholder’s insurance program may show coverage for the Coronavirus outbreak. Now is the time to assess, with the guidance of your brokers and insurance coverage counsel, the specific coverages in place. Policyholders may want to particularly review the terms and conditions of their Property, General Liability, Pollution, Directors & Officers, Professional Liability, Fiduciary Liability, as well as Event Cancelation Insurance coverages, among others depending on their specific business trade. For instance, Policyholders would want to assess, ahead of time, whether there are bacterial/virus/communicable diseases/pandemics exclusions in their policies. It is also relevant to review, with a keen eye, the insuring agreements and pose hypotheticals to stress test them and see how far coverage would go with respect to a Coronavirus exposure;
Reprinted courtesy of
Richard W. Brown, Saxe Doernberger & Vita, P.C. and
Andres Avila, Saxe Doernberger & Vita, P.C.
Mr. Brown may be contacted at rwb@sdvlaw.com
Mr. Avila may be contacted at ara@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of