Georgia Court of Appeals Upholds Denial of Coverage Because Insurance Broker Lacked Agency to Accept Premium Payment
December 07, 2020 —
Lawrence J. Bracken II, Michael S. Levine & Rachel E. Hudgins - Hunton Insurance Recovery BlogIn American Reliable Insurance Company v. Lancaster, the Georgia Court of Appeals reversed the denial of a property insurer’s summary judgment motion concerning the insurer’s denial of a fire loss claim. The basis of the denial was that the policyholders had failed to pay the policy premium. The policyholders, Charlie and Wanda Lancaster, claimed that they had paid their policy premiums for several years to their insurance agent, Macie Yawn. In October 2014, American Reliable mailed a renewal notice to the Lancasters notifying them that premium payments had to be made directly to the insurer. After it did not receive payment from the Lancasters, American Reliable sent them a cancellation notice in December 2014, again notifying them that payments be made directly to the insurer. The Lancasters denied having received either notice from American Reliable, but the record included a receipt for certificate of mailing.
After the Lancaster’s home burned down in 2015, American Reliable denied coverage on the grounds that the policy had been cancelled for nonpayment of premium. In the subsequent coverage action, the trial court denied American Reliable’s motion for summary judgment, ruling that a factual issue existed as to the actual and apparent agency of the insurance agent, Yawn. On appeal, the Court of Appeals found that the trial court erred in deciding that there was a factual issue concerning Yawn’s agency. Specifically, the Court of Appeals ruled that the record showed American Reliable had terminated Yawn’s agency to accept policy premiums, and that the Lancaster’s received notice of that termination in the renewal and cancellation notices. In addition to determining that Yawn was not an actual agent, the Court held that Yawn did not have apparent agency, because the notices sent to the Lancasters stated that the premium payment was to be paid to American Reliable, not to the agent.
Reprinted courtesy of
Lawrence J. Bracken II, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Rachel E. Hudgins, Hunton Andrews Kurth
Mr. Bracken may be contacted at lbracken@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Ms. Hudgins may be contacted at rhudgins@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
2024 Update to CEB’s Mechanics Liens Now Available
October 15, 2024 —
Garret Murai - California Construction Law BlogFor a number of years we have had the honor to serve as update authors for several publications of California’s Continuing Education of the Bar (CEB).
I didn’t realize it until now but the CEB, a program of the University of California, was started
more than 75 years ago following WWII to provide veterans who were attorneys with practical guidance on changes to the law as they returned to their practices following the war. Pretty cool!
Reprinted courtesy of
Garret Murai, Nomos LLP
Mr. Murai may be contacted at gmurai@nomosllp.com
Read the full story... Read the court decisionRead the full story...Reprinted courtesy of
Filling Out the Contractor’s Final Payment Affidavit
February 03, 2020 —
David Adelstein - Florida Construction Legal UpdatesWhen preparing a contractor’s final payment affidavit, I always suggest for a contractor (or anyone in privity of contract with the owner) to identify the undisputed amounts their accounting reflects is owed to ALL subcontractors, etc., regardless of whether that entity preserved their lien rights. If the contractor provided a payment bond, I footnote this simply to support that none of the lower-tiered subcontractors have lien rights or are the traditional “lienor.” (Thus, there is no prejudice to the owner if an entity is inadvertently omitted from the affidavit.)
There are times, however, where a contractor does not identify a subcontractor that did not serve a notice to owner and, therefore, has no valid lien rights. Or, a contractor omits a lienor that actually did serve a notice to owner and preserve its lien rights; this happens.
There was an older First District Court of Appeals case that harshly (and, quite, unfairly) held that the contractor must identify everyone in the final payment affidavit regardless of whether that entity timely served a notice to owner or their lien is invalid. This case, however, predated, a 1998 statutory change to Florida’s Lien Law.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin Norris, P.A.Mr. Adelstein may be contacted at
dma@kirwinnorris.com
Mortgage Applications in U.S. Jump 11.6% as Refinancing Surges
October 22, 2014 —
Danielle Trubow – BloombergMortgage applications in the U.S. soared last week as a plunge in borrowing costs led to biggest gain in home refinancing since January 2012.
The Mortgage Bankers Association’s index rose 11.6 percent in the period ended Oct. 17, the biggest gain since January, after a 5.6 percent advance the week before, figures from the Washington-based group showed today.
The refinancing gauge jumped 23.3 percent while the purchase applications measure dropped 4.6 percent.
Read the court decisionRead the full story...Reprinted courtesy of
Danielle Trubow, BloombergMs. Trubow may be contacted at
dtrubow@bloomberg.net
Rather Than Limit Decision to "That Particular Part" of Developer's Policy Necessary to Bar Coverage, 10th Circuit Renders Questionable Decision on Exclusion j(6)
September 06, 2021 —
William S. Bennett - Saxe Doernberger & Vita, P.C. The 10th Circuit Court of Appeals, applying Colorado law, recently extended Colorado’s broad application of the phrase “arising out of” in insurance interpretation, barring an insured real estate developer from receiving a defense to a suit alleging liability for construction of a defective retaining wall and associated resulting damage.1 The decision also included a questionable analysis of the commercial general liability (“CGL”) policy’s exclusion j(6), contradicting both the plain meaning of the exclusion as well as existing 10th Circuit case law.
The underlying dispute concerned a land developer, HT Services, LLC, who was sued by the homeowner’s association (“HOA”) of one of its developments. The HOA alleged that HT Services negligently designed and constructed a retaining wall in the community. HT Services had CGL policies from Western Heritage Insurance Company in place from 2010 to 2013 that insured it for liability associated with four acres of land that the community was built upon.
HT Services tendered the HOA’s lawsuit to Western Heritage, which declined to defend and indemnify HT Services. After that matter settled, HT Services sued Western Heritage, alleging breach of contract and bad faith. Western Heritage moved for summary judgment, asserting two exclusions, and the District Court granted the motion in Western Heritage’s favor. In upholding the District Court’s decision, the 10th Circuit discussed two exclusions that the District Court determined precluded coverage.
Read the court decisionRead the full story...Reprinted courtesy of
William S. Bennett, Saxe Doernberger & Vita, P.C.Mr. Bennett may be contacted at
wsb@sdvlaw.com
Critical Updates in Builders Risk Claim Recovery: Staying Ahead of the "Satisfactory State" Argument and Getting the Most Out of LEG 3
December 11, 2023 —
Gregory D. Podolak & Cheryl L. Kozdrey - Saxe Doernberger & Vita, P.C.Builders risk claims routinely involve complicated and aggressive debate about the interplay between covered physical loss and uncovered faulty work. However, denials on this front have recently experienced a noticeable uptick in frequency, creativity, and aggressiveness. The insurer arguments concentrate in two key areas with a common theme – that any damage associated with a construction defect is not covered:
- Defective construction does not qualify as a “physical” loss to trigger the insuring agreement; and
- Any natural results of defective construction are excluded as faulty workmanship, even with favorable LEG 3 or similar language.
Neither of these arguments should impede access to coverage in the majority of scenarios. To ensure as much, it is incumbent on the savvy policyholder to understand the insurer tactics, be prepared to spot them early, and have thoughtful counter positions at the ready to address them decisively.
Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C. and
Cheryl L. Kozdrey, Saxe Doernberger & Vita, P.C.
Mr. Podolak may be contacted at GPodolak@sdvlaw.com
Ms. Kozdrey may be contacted at CKozdrey@sdvlaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Florida Appeals Court Rules in Favor of Homeowners Unaware of Construction Defects and Lack of Permits
December 09, 2011 —
CDJ STAFFThe Florida Court of Appeals has ruled that a homeowner is not liable for defects in unpermitted alterations, reversing a lower court’s decision in Jensen v. Bailey. The Jensens sold their house to the Baileys. During the sale, the Jensens filled out a property disclosure statement, checking “no” to a question about “any improvement or additions to the property, whether by your or by others that have been constructed in violation of building codes or without necessary permits.”
After moving in, the Baileys discovered several problems with the home. One involved a defective sewer connection leading to repeated backups. The Baileys also found problems with remodeling the Jensens had done in the kitchen, master bath, and bedroom. The remodeling work was not done with required permits nor was it up to code.
The court noted that an earlier case, Johnson v. Davis, established four criteria: “the seller of a home must have knowledge of a defect in the property; the defect must materially affect the value of the property; the defect must not be readily observable and must be unknown to the buyer; and the buyer must establish that the seller failed to disclose the defect to the buyer.” The court found that the first of these criteria was crucial to determining the case.
In the Johnson ruling, the then Chief Justice dissented, fearing that the courts “would ultimately construe Johnson’s requirement of actual knowledge to permit a finding of liability based on constructive knowledge,” quoting Justice Boyd, “a rule of constructive knowledge will develop based on the reasoning that if the seller did not know of the defect, he should have known about it before attempting to sell the property.” The Appeals Court concluded that the lower court hit this point in ruling on Jensen v. Bailey.
Citing other Florida cases, the court noted that the Johnson rule does require “proof of the seller’s actual knowledge of the defect.” The court cited a case in which it was concluded that the seller “should have known” that there was circumstantial evidence was that the seller did know about the defects, as the seller had been involved in the construction of the home.
In the case of the Jensens, the lower court concluded that they did not know that the work was defective, nor did they know that they were obligated to obtain permits for it. The Appeals Court found this one fact sufficient to reverse the decision and remand the case to the lower court for a final judgment in favor of the Jensens.
Read the court’s decision…
Read the court decisionRead the full story...Reprinted courtesy of
The EEOC Targets Construction Industry For Heightened Enforcement
May 15, 2023 —
Meghan Douris & Andrew Scroggins - The Construction SeytSeyfarth Synopsis: On January 10, 2023, the Equal Employment Opportunity Commission (EEOC) released for public comment its
draft 2023-2027 Strategic Enforcement Plan (“SEP”)—a document that will guide the Commission’s enforcement priorities for the next five years. The EEOC’s prior Strategic Plan described how it would pursue its enforcement goals. (See our earlier blog on the Strategic Plan
here). The Strategic Enforcement Plan, on the other hand, describes what the EEOC’s enforcement priorities will be. Earlier actions by the EEOC suggested that it might be turning its attention to the construction industry. In the SEP, the EEOC makes its intentions explicit, putting the construction industry—and especially those receiving federal funding—squarely in its sights.
History of the SEP
The EEOC’s
first SEP covered Fiscal Years 2013-2016 (the EEOC’s fiscal years begin on October 1) and identified six broad subject-matter priorities. The EEOC’s
second SEP set the course for enforcement priorities for FY2017-2022. The
latest proposed SEP, published in the Federal Register for comment for the first time, provides notable additional details that put the employer community on notice of the Commission’s intentions for FY2023-2027.[
1]
Reprinted courtesy of
Meghan Douris, Seyfarth and
Andrew Scroggins, Seyfarth
Ms. Douris may be contacted at mdouris@seyfarth.com
Mr. Scroggins may be contacted ascroggins@seyfarth.com
Read the court decisionRead the full story...Reprinted courtesy of