The Right to Repair Act Means What it Says and Says What it Means
December 18, 2022 —
Garret Murai - California Construction Law BlogA rather short case for a short week.
In Gerlach v. K. Hovnanian’s Four Seasons at Beaumont, LLC, 82 Cal.App.5th 303 (2022), the 4th District Court of appeals examined provisions of the Right to Repair Act (Civ. Code §§895 et. seq), also known as “SB 800” after its original bill number, as it applies to roofs.
The Gerlach Case
Lynn Gerlach and Lola Seals are homeowners who purchased their homes in the Four Seasons at Beaumont adult community, for those 55 year old and older, located in Beaumont, California. Gerlach purchased her home when it was built in 2006. Seals purchased her home from the original owners in 2015.
In 2015 and 2016, Gerlach and Seals served the developer, K. Hovnanian’s Four Seasons at Beaumont, LLC, with claim notices under the Right to Repair Act. The Right to Repair Act, as its name implies, provides notice requirements and repair rights by developers of new single-family homes. The Right to Repair Act also includes construction standards, the violation of which, provides homeowners with a statutory basis for bringing construction defect claims.
Read the court decisionRead the full story...Reprinted courtesy of
Garret Murai, Nomos LLPMr. Murai may be contacted at
gmurai@nomosllp.com
Lewis Brisbois Appellate Team Scores Major Victory in Bad Faith Insurance Action
May 24, 2021 —
Raul Martinez & Elise Klein - Lewis Brisbois NewsroomAppellate Partner Raul L. Martinez and Los Angeles Partners Elise D. Klein and Celia Moutes-Lee recently secured a major win in an appeal of a bad faith insurance action. In Wexler v. California Fair Plan Association (Apr. 14, 2021, B303100) __Cal.App.5th__, Division Eight of the Second Appellate District (Los Angeles), the court held that the plaintiff, the daughter of insurance policy holders, had no standing to pursue bad faith allegations against her parents’ insurer for smoke damage to her personal possessions.
The daughter’s parents owned a home in the mountains where there was a heightened risk of fires. The parents insured their home with a California FAIR Plan Association (FAIR Plan) owner-occupied dwelling policy (the FAIR Plan Policy). The FAIR Plan Policy only insured the dwelling and its contents against damage from fire, lightning, and internal explosion with limited coverage for smoke damage. The FAIR Plan Policy also expressly disclaimed coverage for individuals not specifically named in the policy. Furthermore, the plaintiff’s name did not appear in any of her parents’ insurance documents.
Reprinted courtesy of
Raul Martinez, Lewis Brisbois and
Elise Klein, Lewis Brisbois
Mr. Martinez may be contacted at Raul.Martinez@lewisbrisbois.com
Ms. Klein may be contacted at Elise.Klein@lewisbrisbois.com
Read the court decisionRead the full story...Reprinted courtesy of
Paycheck Protection Program Forgiveness Requirements Adjusted
June 29, 2020 —
Jacob W. Scott - Smith CurrieOn June 5, 2020, the President signed into law the Paycheck Protection Program Flexibility Act of 2020, amending portions of the Paycheck Protection Program (“PPP”). Most importantly, the PPP Flexibility Act adjusted the forgiveness requirements for PPP loans.
The CARES Act allowed borrowers to apply for forgiveness of loan amounts used for payroll and other covered costs during an eight-week period beginning on the date of origination, or by June 30, 2020, whichever came first. The CARES Act also allowed borrowers to use the loan funds by June 30 to restore employee and payroll levels that had been reduced as a result of COVID-19. The Small Business Administration instructed borrowers that at least 75% of the loan funds had to be used to cover payroll costs during the covered period to be eligible for forgiveness.
Read the court decisionRead the full story...Reprinted courtesy of
Jacob W. Scott, Smith CurrieMr. Scott may be contacted at
jwscott@smithcurrie.com
Hurricane Harvey: Understanding the Insurance Aspects, Immediate Actions for Risk Managers
September 07, 2017 —
Gregory D. Podolak - Saxe Doernberger & Vita, P.C.As it’s been more than 10 years since a major hurricane made landfall in the U.S., Hurricane Harvey will test many risk managers’ insurance programs and response plans. Such disasters are complex, and decisive decision-making could mean the difference between staying in business and closing for good.
In this Alert, SDV’s Gregory Podolak and Frank Russo of Procor outline, in clear language, what risk managers need to know about large-scale natural disasters in order to mitigate risks up front and stay sound once they’ve hit.
Read the court decisionRead the full story...Reprinted courtesy of
Gregory D. Podolak, Saxe Doernberger & Vita, P.C.Mr. Podolak may be contacted at
gdp@sdvlaw.com
Charles Carter v. Pulte Home Corporation
October 12, 2020 —
Michael Velladao - Lewis BrisboisIn Carter v. Pulte Home Corp., __Cal.App.5th__(July 23, 2020), the California Court of Appeal affirmed the entry of judgment in favor of subcontractors in connection with a Complaint for Intervention based on equitable subrogation filed by Travelers Property Casualty Company of America (“Travelers”) seeking to recover defense costs incurred in defending Pulte Home Corporation (“Pulte”) in an underlying construction defect lawsuit. The parties’ dispute arose out of Travelers’ defense of Pulte as an additional insured under policies issued to four subcontractors involved in the underlying construction defect lawsuit. Several subcontractors involved in the underlying construction defect lawsuit refused to defend Pulte based on the indemnity clauses in their subcontracts. Such clauses promised to indemnify Pulte as follows:
“all liability, claims, judgments, suits, or demands for damages to persons or property arising out of, resulting from, or relating to Contractor’s performance of work under the Agreement (“Claims”) unless such Claims have been specifically determined by the trier of fact to be the sole negligence of Pulte. . . .”
Pulte eventually settled the construction defect lawsuit and its claims against all of the subcontractors. Travelers ultimately paid $320,491.82 for Pulte’s defense and recovered $164,400 from some of the subcontractors. Travelers’ intervention in the underlying lawsuit was intended to recover the remaining $156,091.82 from the subcontractors that refused to indemnify Pulte for the defense of the construction defect lawsuit. In the underlying trial, Travelers argued that the subcontractors were obligated to pay defense costs on a joint and several basis (minus what Travelers had already recovered). The trial court did not agree and held that Travelers was not entitled to equitable subrogation for the remaining defense costs.
Read the court decisionRead the full story...Reprinted courtesy of
Michael Velladao, Lewis BrisboisMr. Velladao may be contacted at
Michael.Velladao@lewisbrisbois.com
Construction Employment Rose in 38 States from 2013 to 2014
March 19, 2014 —
Beverley BevenFlorez-CDJ STAFFThe Associated General Contractors of America (AGC) reported that 38 states experienced construction job growth from January 2013 to January 2014, and 27 states showed gains from December 2013 to January 2014. AGC stated that “the fact so many states added construction jobs for the year and month despite harsh winter conditions in many parts of the country is a sign that demand appears to be recovering.”
Kansas ranked first in the “12-month gain or loss” category with a 10.7% gain. Wyoming came in last with a -5.9% over a 12-month period. However, if examining a one-month period (between December 2013 and January 2014), Idaho showed the highest growth with a 5.8% gain, while Vermont was ranked 51 at -5.5%.
Read the full story, Article...
Read the full story, Rankings... Read the court decisionRead the full story...Reprinted courtesy of
Disputes Over Arbitrator Qualifications: The Northern District of California Offers Some Guidance
August 10, 2021 —
Justin K. Fortescue - White and WilliamsThe selection of an arbitration panel can often lead to disputes between the parties regarding things like whether a particular candidate is qualified, whether a challenge to an arbitrator’s qualifications can be addressed pre-award and whether a party that names an unqualified arbitrator should lose the opportunity to name a replacement. In Public Risk Innovations v. Amtrust Financial Services, No. 21-cv-03573, 2021 U.S. Dist. LEXIS 129464 (N.D. Ca. July 12, 2021), the court provided answers on all three of these issues.
In Amtrust, the parties filed cross-motions to compel arbitration. Although both parties agreed the dispute was arbitrable, they disagreed about whether Public Risk Innovations, Solutions and Management’s (PRISM) arbitrator was qualified under the terms of the applicable contract. In seeking to have PRISM’s arbitrator disqualified, Amtrust argued that he: (1) was not a “current or former official of an insurance or reinsurance company”; and (2) was not “disinterested.” Amtrust also argued that because PRISM named an unqualified arbitrator (and presumably the time to appoint had passed), PRISM should be deemed to have failed to select an arbitrator as required by the contract and that Amtrust had the right to select a second arbitrator of its choice.
Read the court decisionRead the full story...Reprinted courtesy of
Justin K. Fortescue, White and WilliamsMr. Fortescue may be contacted at
fortescuej@whiteandwilliams.com
New Safety Requirements added for Keystone Pipeline
June 11, 2014 —
Beverley BevenFlorez-CDJ STAFFAfter learning about construction defects on the “southern leg of the Canada-to-Texas project,” safety regulators have added two additional conditions “on construction of TransCanada Corp.’s Keystone XL oil pipeline,” according to Claims Journal. The defects, which have been fixed, included “high rates of bad welds, dented pipe and damaged pipeline coating.”
The first condition requires “TransCanada to hire a third-party contractor chosen by the pipeline safety agency to monitor the construction” and report to the U.S. government, while the second condition requires “TransCanada to adopt a quality management program.”
Both conditions were “buried near the end of the 26 appendices in a voluminous environmental impact statement on Keystone XL released by the State Department on Jan. 31.”
Read the court decisionRead the full story...Reprinted courtesy of