A Homeowner’s Subsequent Action is Barred as a Matter of Law by way of a Prior “Right to Repair Act” Claim Resolved by Cash Settlement for Waiver of all Known or Unknown Claims
February 26, 2015 —
Richard H. Glucksman, Esq., Jon A. Turigliatto, Esq., and David A. Napper, Esq. – Chapman Glucksman Dean Roeb & Barger BulletinDavid Belasco v. Gary Loren Wells et al. (2015) B254525
OVERVIEW
In a decision published on February 17, 2015, the Second District Court of Appeal made clear that settlement agreements containing waivers of unknown claims in connection with a construction of a property, absent fraud or misrepresentation, will be upheld. In brief, the homeowner plaintiff had made a claim against the builder pursuant to California Code of Civil Procedure Section 896 (“Right to Repair”) and settled for a cash payment and obtained a Release of all Claims including for all known and unknown claims. The court held that homeowner’s subsequent construction defect claim was barred pursuant to the terms and conditions of the earlier release.
DISCUSSION
Plaintiff and Appellant, David Belasco ("Belasco"), purchased a newly construction home in Manhattan Beach from builder Gary Loren Wells ("Wells"). Two years after purchasing the property, Belasco filed a Complaint for construction defects, which eventually resulted in settlement between the parties. The settlement agreement included a California Civil Code Section 1524 waiver of all known or unknown claims with the word "claims" defined in part as “any and all known and unknown construction defects." Six years later in 2012, Belasco filed a Complaint alleging a claim, amongst others, that the defective and leaky roof breached the statutory warranty on new construction under California Civil Code section 896 ("Right to Repair Act").
Relying on San Diego Hospice v. County of San Diego (1995) 31 Cal.App.4th 1048, Wells and Wells' surety, American Contractors Indemnity Company (collectively "Wells"), filed a motion for summary judgment contending that the 2012 action was barred by the settlement of Belasco’s prior Complaint against Wells for construction defects to his home. When the trial court ruled in favor of Wells, Belasco appealed. Belasco, a patent attorney, made the following contentions:(1) the general release and section 1542 wavier in the settlement agreement for patent construction defects is not a "reasonable release" of a subsequent claim for latent construction defects within the meaning of section 929 and the “Right to Repair” Act; (2) a reasonable release can only apply to a "particular violation" and not to a latest defect under the language of section945.5, subdivision (f), and the settlement was too vague to be valid because it does not reference a "particular violation;" (3) section 932 of the California Civil Code specifically authorizes an action on "[s]subsequently discovered claims of unmet standards;" (4) public policy prohibits use of a general release and section 1542 waiver to bar a subsequent claim for latent residential construction defects; and (5) a genuine issue of material fact exists concerning Belasco's fraud and negligence claims that would have voided the settlement pursuant to section 1668.
Pursuant to the "Right to Repair Act" Section 929 subsection (a), a builder can make a cash offer in lieu of a repair and the homeowner is free to accept or reject such offer. Section 929subsection (b) goes on to state that
"[t]he builder may obtain a reasonable release in exchange for the cash payment. The builder may negotiate the terms and conditions of any reasonable release in terms of scope and consideration in conjunction with a cash payment under this chapter."
The Second District Court of Appeal ruled that the prior cash settlement, with a release and section 1524 wavier, was a "reasonable release" under the language of California Civil Code Section 929.
On multiple occasions, the Court noted that Belasco is an attorney and was represented by an attorney during the negotiation of the settlement agreement. By executing the agreement with express language regarding what claims were to be release, Belasco released Wells of "any and all claims" due to "any and all known and unknown construction defects." The Court reasoned that because Belasco is an attorney in his own right, he should have understood the import of the Section 1542 waiver and had the opportunity to reject or revise the settlement agreement prior to binding himself to it. The Court further found that the agreement "could not have been more clear" regarding the waiver of all unknown and known construction defect claims and therefore was not vague. Belasco's additional contentions were found to be without merit because Belasco availed himself of the statutory remedy of a cash settlement in lieu of repairs and voluntarily entered into a negotiated settlement agreement. Lastly, Belasco failed to present any evidence regarding his misrepresentation claim.
When a homeowner files a "Right to Repair Act" claim, often it seems that only two options exist: either repair the alleged defects or go to court. However, Belasco is a reminder to builders that the "Right to Repair Act" does offer an avenue for settlement. The Second District Court of Appeal presented a clear, unqualified opinion regarding the validity and enforceability of settlement agreements releasing all known or unknown construction defects in a single family home case. The Court will hold parties to the settlements they agree to. This is especially so when one of the parties is an attorney and provides deposition testimony expressly acknowledging that he understood the scope of the agreement. Attorneys for builders should always include a waiver of all known and unknown claims, which pursuant to Belasco and San Diego Hospice, will ensure that any future claims at the property will be effectively barred by the terms of the settlement agreement.
Reprinted courtesy of Chapman Glucksman Dean Roeb & Barger attorneys
Richard H. Glucksman,
Jon A. Turigliatto and
David A. Napper
Mr. Glucksman may be contacted at rglucksman@cgdrblaw.com
Mr. Turigliatto may be contacted at jturigliatto@cgdrblaw.com
Mr. Napper may be contacted at dnapper@cgdrblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
Defenses Raised Three-Years Too Late Estop Insurer’s Coverage Denial
February 21, 2022 —
Michael S. Levine & Yaniel Abreu - Hunton Insurance Recovery BlogLiability insurance typically affords broad defense coverage. But insurers sometimes reserve their right to challenge the insured’s right to a defense, or even outright terminate the defense. When this occurs after the insurer has been in exclusive control of the defense, some courts recognize that the consequences can be catastrophic for the insured defendant. Insurers, therefore, may be estopped from denying coverage where doing so will prejudice the insured. This is exactly what transpired in RLI Ins. Co. v. AST Engineering Corp., No. 20-214 (2d Cir. Jan. 12, 2022), where the Second Circuit affirmed the district court’s decision that an insurer’s attempt to withdraw the defense it had provided to its insured for three years would prejudice the insured.
In AST Engineering, RLI sought a declaration that it did not have to defend the insured, AST, in two underlying cases in which AST was sued as a third-party defendant. The underlying cases concerned a construction project in New York City for which AST provided engineering drawings on October 28, 2012.
Reprinted courtesy of
Michael S. Levine, Hunton Andrews Kurth and
Yaniel Abreu, Hunton Andrews Kurth
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Abreu may be contacted at yabreu@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
The Future of Construction Tech Is Decision Tech
August 06, 2019 —
Bassem Hamdy - Construction ExecutiveIt doesn’t take much to be catastrophically wrong in construction; some bad information, a touch of misleading intel, a few biased opinions mixed with human error and perhaps a little bad luck to top it off. A poor decision early in a project plants itself like a weed—it grows benignly at first, and becomes gravely pervasive at the end.
Being wrong in construction is dangerous. Error leads to leaning towers and broken buildings. Poorly-built structures can hinder economic growth and deprive communities of good infrastructure. For the enterprise, bad decisions can lead to massive financial loss and—worse—human loss on a jobsite.
Despite knowing all the dangers, it seems that flawed data, misleading intel and human error have become traits the industry can’t shake. To be clear, construction is one of—if not the most—complex industry in today’s economy. Companies walk a tight rope between a 2% margin on one side and ruinous loss on the other. Under such conditions, it’s easy to see why sustained good judgement is difficult.
Reprinted courtesy of
Bassem Hamdy, Construction Executive, a publication of Associated Builders and Contractors. All rights reserved.
Read the court decisionRead the full story...Reprinted courtesy of
Supreme Court Opens Door for Challenges to Older Federal Regulations
August 05, 2024 —
Jane C. Luxton - Lewis BrisboisWashington, D.C. (July 1, 2024) – On July 1, 2024, the U.S. Supreme Court issued another end-of-term major decision limiting the scope of federal agency actions in Corner Post, Inc. v. Board of Governors of the Federal Reserve System. Adding to the tectonic shift in the regulatory landscape created by the Court’s June 27 and 28 rulings constraining the role of administrative law judges and overturning longstanding “Chevron deference” by courts to federal agency expertise, the decision in Corner Post establishes a newly expanded time frame for affected entities to challenge final agency action. Instead of confirming that final agency action is subject to a default six-year statute of limitations, the Court held that under the Administrative Procedure Act (APA), the time limit for appeal begins to run when a plaintiff is injured by the agency's action, not when the action becomes final. This decision has important implications for businesses and others affected by federal regulations.
The case arose when Corner Post, a truck stop and convenience store in North Dakota that opened in 2018, challenged a 2011 Federal Reserve Board regulation (Regulation II) that set maximum interchange fees for debit card transactions. Corner Post filed suit in 2021, arguing that Regulation II allowed higher fees than permitted by statute. The lower courts dismissed the suit as time-barred under 28 U.S.C. § 2401(a), which effectively requires APA claims to be filed "within six years after the right of action first accrues."
Read the court decisionRead the full story...Reprinted courtesy of
Jane C. Luxton, Lewis BrisboisMs. Luxton may be contacted at
Jane.Luxton@lewisbrisbois.com
Has Hydrogen's Time Finally Come?
April 05, 2021 —
Mary B. Powers, Debra K. Rubin, Michael Dumiak, and Pam Radtke Russell - Engineering News-RecordGlobal conditions to harness the potential of hydrogen to fuel the developing clean energy transformation—particularly technology innovation, political investment and growing acceptance that climate change is a reality—finally appear to be lining up. While reports have noted hydrogen eyed as a fossil fuel replacement as far back as Jules Verne’s 1875 novel “The Mysterious Island,” with costs high and changemaking slow, it never captured the market many hoped for.
Reprinted courtesy of
Mary B. Powers, ENR,
Debra K. Rubin, ENR,
Michael Dumiak, ENR, and
Pam Radtke Russell, ENR
Ms. Rubin may be contacted at rubind@enr.com
Ms. Russell may be contacted at Russellp@bnpmedia.com
Read the full story...
Read the court decisionRead the full story...Reprinted courtesy of
Defective Sprinklers Not Cause of Library Flooding
October 30, 2013 —
CDJ STAFFSprinklers are important in any public building, but libraries with their large collections of nicely flammable paper. Of course, you also want to keep those books dry. The Hilton Head Island library investigated its sprinklers after a malfunctioning sprinkler head flooded the Friends of the Library bookshop, ruining thousands of books.
The investigation found that, apart from the malfunction, the sprinklers had a defect that could have lead to their failure to operate in the event of a fire. The sprinklers had been the subject of a voluntary recall in 2001, however the 220 sprinkler heads were not replaced at that time. The county claimed that they were unaware of the recall at the time, and so failed to take advantage of program under which the manufacturer would pay for the recall. That program ended in 2007.
Read the court decisionRead the full story...Reprinted courtesy of
Fifth Circuit Holds Insurer Owes Duty to Defend Latent Condition Claim That Caused Fire Damage to Property Years After Construction Work
September 21, 2020 —
Jeremy S. Macklin - Traub LiebermanMost general liability policies only provide coverage for “property damage” that occurs during the policy period. Thus, when analyzing coverage for a construction defect claim, it is important to ascertain the date on which damage occurred. Of course, the plaintiffs’ bar crafts pleadings to be purposefully vague as to the date (or period) of damage to property. A recent Fifth Circuit decision applying Texas law addresses this coverage issue in the context of allegations of a condition created by an insured during the policy period that caused damage after the policy expired.
In Gonzalez v. Mid-Continent Cas. Co., 969 F.3d 554 (5th Cir. 2020), Gilbert Gonzales (the insured) was a siding contractor. In 2013, the underlying plaintiff hired Gonzales to install new siding on his house. In 2016, the underlying plaintiff’s house was damaged in a fire. The underlying plaintiff sued Gilbert in Texas state court alleging that when Gonzalez installed the siding in 2013, he hammered nails through electrical wiring and created a dangerous condition that caused a fire three years later in 2016.
At the time Gilbert performed construction work, he was insured by Mid-Continent Casualty Company. Mid-Continent disclaimed coverage to Gonzales on the basis that the complaint unequivocally alleged that property was damaged in 2016 and there were no allegations that property damage occurred prior to 2016 or was continuing in nature.
Read the court decisionRead the full story...Reprinted courtesy of
Jeremy S. Macklin, Traub LiebermanMr. Macklin may be contacted at
jmacklin@tlsslaw.com
Indemnification Provisions Do Not Create Reciprocal Attorney’s Fees Provisions
November 21, 2018 —
CDJ STAFFIn a good, recent decision, the Eleventh Circuit in International Fidelity Insurance Co. v. Americabe-Moriarity, JV, 2018 WL 5306683 (11th Cir. 2018), held that Florida Statute s. 57.105(7) cannot be used to shift attorney’s fees in a contractual indemnification clause in a dispute between a general contractor and subcontractor’s performance bond surety, when the dispute does not involve an actual indemnification claim stemming from a third-party.
In this case, a prime contractor terminated a subcontractor and looked to the subcontractor’s performance bond surety to pay for the completion work. The subcontractor had a standard AIA A312 performance bond that requires the prime contractor to comply with the terms of the bond, as well as the incorporated subcontract, in order to trigger the surety’s obligations under the bond. The surety filed an action for declaratory relief against the prime contractor arguing that the prime contractor breached the terms of the performance bond through non-compliance thereby discharging the surety’s obligations. The trial court agreed and the surety moved for attorney’s fees.
Read the court decisionRead the full story...Reprinted courtesy of
David Adelstein, Kirwin NorrisMr. Adelstein may be contacted at