Fixing the Problem – Not the Blame
November 30, 2016 —
Curtis W. Martin – Peckar & Abramson, P.C. BulletinWho is responsible for defective design under Texas law? The contractor, under Lonergan? The
owner, under Spearin? A recent Fifth Circuit decision suggests that in some cases this might be the
wrong question when design responsibility is disputed. The appellate court recently remanded a
case back to the district court to determine whether the contractor or owner breached an implied
duty to cooperate in discovering defects in design and subsequently pricing the change required
to correct the problem.
Read the court decisionRead the full story...Reprinted courtesy of
Curtis W. Martin, Peckar & Abramson, P.C.Mr. Martin may be contacted at
cmartin@pecklaw.com
Agile Project Management in the Construction Industry
January 09, 2023 —
Mohammad Saki - AEC BusinessThe linear workflows used in the construction industry, such as the RIBA plan of work, have a history of starting when the previous phases end. The stages in these workflows are often distinct and sequential, and it might be difficult or expensive to go back after a stage is finished. Design reviews are required in this method, which is also known as the “Waterfall,” and they must be completed before moving on to the next level.
Cross-phase iterations are a rare symptom of problems, and the majority of design specifications will be locked early to prevent rework. Additionally, common planning and scheduling methods for the construction industry, like the Critical Path Method (CPM) and Program Evaluation and Review Technique (PERT), lack the ability to represent feedback and iteration in projects because they only permit one-way progression.
As a result, these processes have come under fire for being a linear paradigm that encourages a fragmented approach to project management, and the need for a more iterative procedure has increased.
Read the court decisionRead the full story...Reprinted courtesy of
Mohammad Saki, AEC Business
Another Reason to Love Construction Mediation (Read: Why Mediation Works)
December 02, 2015 —
Christopher G. Hill – Construction Law MusingsI’ll bet you’re thinking by now that I have beaten the mediation drum to death and that I wouldn’t have any more praise for the process than I have heaped upon it here at this corner of the construction law “blawgosphere.” Well, just about every time I am involved with the process, whether acting in my capacity as a Virginia Supreme Court certified mediator, or as counsel to a client seeking to resolve a matter and move on with the business of making money, I become more convinced that mediation can work in even the most contentious of situations.
What do I mean by “work?” The obvious answer is that mediation “works” when the parties come up with a solution to their problem. In most instances, the solution involves money changing hands. After all, it is money that is usually the tangible and outwardly driving force behind a dispute. Money is also what a court or arbitrator (in most cases) will be awarding to one side or the other at the end of what is likely to be an expensive process.
Read the court decisionRead the full story...Reprinted courtesy of
Christopher G. Hill, Law Office of Christopher G. Hill, PCMr. Hill may be contacted at
chrisghill@constructionlawva.com
Expansion of Statutes of Limitations and Repose in K-12 and Municipal Construction Contracts
March 27, 2019 —
Henry Bangert - Colorado Construction LitigationThe purpose of this whitepaper is to bring attention to a trend in K-12 and municipal construction contracts, which expands the time periods for law suits against construction professionals.
Introduction and Background
Under Colorado statute, the period of time within which a legal action for construction defects may be brought against a construction professional in Colorado is two years from when the claimant (or its predecessor in interest) discovers or in the exercise of reasonable diligence should have discovered the physical manifestations of a defect (the “Statute of Limitations”), but in no case may an action be brought more than six years after substantial completion of the improvement, unless the claim arises in the fifth or sixth year after substantial completion, in which event the action may be brought within two years of such date, i.e., up to eight years after substantial completion (the “Statute of Repose”). See C.R.S. § 13-80-104. While the triggering events differ for the Statute of Limitations and Statue of Repose, the periods are intended to run concurrently to limit the period of time an action may be brought against construction professionals for construction defects to, at most, eight years after substantial completion. Importantly, these limitations periods may be expanded by agreement.
Prior to 1986, Colorado law provided for a 10-year Statute of Repose. However, in 1986, Colorado’s legislature shortened the Statute of Repose time limit to the current six (or up to eight) year period. In 1986, Colorado also redefined the date the claim arises from the date the defect was discovered or should have been discovered to the date the physical manifestation of a defect was discovered or should have been discovered. Therefore, after 1986, the two-year limitations period could begin to run when a claimant should have discovered the manifestation of a defect, even if the claimant did not recognize that a defect existed.
Read the court decisionRead the full story...Reprinted courtesy of
David McLain, Higgins, Hopkins, McLain & Roswell, LLCMr. McLain may be contacted at
mclain@hhmrlaw.com
Dust Obscures Eleventh Circuit’s Ruling on “Direct Physical Loss”
October 12, 2020 —
Walter J. Andrews, Michael S. Levine & Daniel Hentschel - Hunton Insurance Recovery BlogOn August 18, 2020, the United States Court of Appeals for the Eleventh Circuit affirmed a District Court’s 2018 ruling that Sparta Insurance Company need not cover a south Florida restaurant’s lost income and extra expenses resulting from nearby road construction. But, in doing so, the appeals court appears to deviate from even its own understanding of “direct physical loss” under controlling Florida law.
In the underlying coverage action, the insured, Mama Jo’s Inc. operating as Berries in the Grove, sought coverage under its “all risk” commercial property insurance policy for business income loss and incurred extra expenses caused by construction dust and debris that migrated into the restaurant.
Reprinted courtesy of
Walter J. Andrews, Hunton Andrews Kurth,
Michael S. Levine, Hunton Andrews Kurth and
Daniel Hentschel, Hunton Andrews Kurth
Mr. Andrews may be contacted at wandrews@HuntonAK.com
Mr. Levine may be contacted at mlevine@HuntonAK.com
Mr. Hentschel may be contacted at dhentschel@HuntonAK.com
Read the court decisionRead the full story...Reprinted courtesy of
Construction Law Alert: Unlicensed Contractors On Federal Projects Entitled To Payment Under The Miller Act
May 07, 2014 —
Steven M. Cvitanovic and Jessica M. Lassere Ryland - Haight Brown & Bonesteel, LLPAs a matter of first impression, the Ninth Circuit Court of Appeals in Technica LLC ex rel. U.S. v. Carolina Cas. Ins. Co., 12-56539, 2014 WL 1674108 (9th Cir. Apr. 29, 2014), allowed an unlicensed subcontractor to recover from a prime contractor for unpaid services relating to a federal construction project under a federal Miller Act claim. California law otherwise prevents unlicensed contractors from recovering for unpaid work on non-federal projects as a penal measure intended to encourage contractors to maintain a valid license at all times.
Technica LLC (“Technica”) worked as a sub-subcontractor on a large federal fence replacement project (the “Project”). Over the course of a year, Technica supplied nearly a million dollars worth of labor, materials, and services for the Project. However, Technica received only $287,861.81 in partial payments for its work. Technica proceeded to file suit in district court against the prime contractor Candelaria Corporation (“Candelaria”) and its payment surety Carolina Casualty Insurance Company (“CCIC”) under the Miller Act to recover amounts owed to it on the subcontract against the payment bond.
Reprinted courtesy of
Steven M. Cvitanovic, Haight Brown & Bonesteel, LLP and
Jessica M. Lassere Ryland, Haight Brown & Bonesteel, LLP
Mr. Cvitanovic may be contacted at scvitanovic@hbblaw.com; Ms. Lassere Ryland may be contacted at jlassere@hbblaw.com
Read the court decisionRead the full story...Reprinted courtesy of
At $350 Million, Beverly Hillbillies Mansion Is Most Expensive in U.S.
August 10, 2017 —
Matt Gross - BloombergThe story of Jed Clampett is, by now, a legend. A poor mountaineer, he could barely feed his family of four, but one day, while he was out hunting for food, he fired his rifle into the swamp behind his shack—and struck oil. The sale of the resource-rich land, in 1962, would eventually net him between $25 million and $100 million, and he did what anyone with sudden riches would do: He packed up his truck and moved his clan to Beverly Hills, where their adventures would be the subject of nine seasons of the Beverly Hillbillies.
Now the Bel Air estate featured in the (fictional) show’s opening credits is up for sale—and as befits a wealthy, cultured oilman like Jed Clampett, it’s the most expensive listing in the country at $350 million.
“Chartwell”—10.3 acres of land centering on a 25,000-square-foot mansion inspired by French Neoclassical design—went on the market this week, besting its closest competitor, a Beverly Hills spec house, by $100 million.
Read the court decisionRead the full story...Reprinted courtesy of
Matt Gross, Bloomberg
Thank Your Founding Fathers for Mechanic’s Liens
August 04, 2015 —
Craig Martin – Construction Contract AdvisorYep, our founding fathers, Thomas Jefferson and James Madison specifically, Craig Martin, Construction Attorney Lamson Dugan & Murray LLPwere responsible for proposing the first mechanic’s lien laws in the United States. Mechanic’s liens were not a new concept when the first law was passed in the United States; France, Spain and other countries already had them. But, in England, where landownership was limited to the upper classes, the concept of giving a tradesman an interest in the land for his labors was a truly foreign concept.
The Early Years—Pre Mechanic Lien
In the 1700s, there was no right to a mechanic’s lien. The possession of land was never deemed to be changed by its improvement and the laborer or material supplier was held to have acquired no right of lien in the property. The only remedy the laborer or material supplier had was to bring an action against the land owner. If the laborer or material supplier obtained a judgment, he would acquire the lien of a judgment creditor. A Treatise on the law of Mechanics’ Liens on Real and Person Property, 1893.
Read the court decisionRead the full story...Reprinted courtesy of
Craig Martin, Lamson, Dugan and Murray, LLPMr. Martin may be contacted at